A project consists of three tasks: A, B, and C. Task A is known to take five days for sure. Tasks B and C are each dependent on A. B takes five days. C takes seven days with a probability of 0.5 and three days with a probability of 0.5. What is the expected completion time of the project?
- a. 8 days
- b. 10 days
- c. 11 days
- d. 12 days
Want to see the full answer?
Check out a sample textbook solutionChapter 19 Solutions
OPERATIONS MANAGEMENT
Additional Business Textbook Solutions
Intermediate Accounting (2nd Edition)
Gitman: Principl Manageri Finance_15 (15th Edition) (What's New in Finance)
Essentials of Corporate Finance (Mcgraw-hill/Irwin Series in Finance, Insurance, and Real Estate)
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Marketing: An Introduction (13th Edition)
- If a task had a cost variance (CV) = 150 and a schedule variance (SV) = -150, how would that be interpreted? Over budget, ahead of schedule Under budget, ahead of schedule Over budget, behind schedule Under budget, behind schedule On budget, on schedule Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forwardA project has a critical path with an expected duration of 22 and variance of 14. What is the probability it will be completed within 20-25 weeks (inclusive)? (the range of the answers account for rounding errors) Group of answer choices Between 55% and 58% Between 17% and 20% Between 47% and 52% Between 64% and 67% Between 60% and 63%arrow_forwardYou can accomplish any one of the following at an additional cost of $1500. If you will save $1000 for each day that the earliest completion time is reduced, which of the following actions should be taken, if any? 1. Reduce job 5 by two days. True or false 2. Reduce job 3 by two days. True or false 3. Reduce job 7 by two days. True or falsearrow_forward
- Given a project with three paths and their corresponding path lengths: A-B-C: 25 days, A-D-F: 15 days, and B-C-D-E: 20 days; which of the following statements is TRUE? * Activity B has the most slack The expected duration of the project is 60 days The earliest project completion time is 15 days The critical activities are A, B and Carrow_forwardA project has 92 activities, but only 13 of them are analyzed here. Activity P, 9 days, IP = not given Activity W, 10 days, IP = not given Activity S, 6 days, IP = not given Activity A, 25 days, IP = P, W Activity F, 24 days, IP W, S Activity N, 21 days, IP S Activity E, 28 days, IP = A Activity M, 13 days, IP A, F Activity B, 40 days, IP N Activity H, 10 days, IP = E, M Activity K, 14 days, IP = E, M, B Activity D, 11 days, IP = B Activity R, 10 days, IP = B It has been calculated that LS(K) = 118, LS(D) = 109, LS(H) = 124, LS(R) = 116. %3D %3! %3D What is LS(A)?arrow_forwardBased on the given scenario below, determine the common problems in project scheduling then explain howeach mistake can affect the project. 1. Client: “We want a completed project by next month.”You: “Can you give us some details about exactly what you need in the project deliverable?”Client: “You understand what we want. Just deliver that.” 2. You: “Ok, team. Phase 1 is due by next Monday. It is important. Let’s do it.” No further information. 3. You: “How long will it take to finish phase 1?”Team member: “I don’t know. Maybe 3 days.”You: “Sounds good!” 4. Client: “I know you said you won’t be done with this phase until Monday, but we really need it byThursday. What do you have to do to get it to us by then?”You (checking plan which shows this is impossible): “I really don’t think we can do that”Client: “Just get it done.”You: “Ok”. 5. Client: “When will the project be done?”You: “If everything goes according to plan, we will have the project complete in 3 weeks. So…3 weeks.” 6.…arrow_forward
- The activities necessary for the completion of a project are listed in the table below (Time in weeks). You are asked to complete the project 1 week ahead of time. You should crash Activity ________. This will incur an additional cost of $_________ .arrow_forward18 Select the correct answer. Paul is the CEO of a mid-sized IT firm. Three weeks ago, he started a new project in his company. Soon after, Paul planned, scheduled, and assigned necessary tasks to his project team members. This week, the employees have started performing the tasks according to the instructions given to them on a trial. Which phase in the task lifecycle would Paul carry out next? OA. planning OB. reporting tracking testing OE. organizing Reset Next served. 99+arrow_forwardWhich of the following best describes a task on the critical path? Select one: a. The task with the highest planned value b. The task with the highest actual cost c. The task with the longest duration d. The task with no slackarrow_forward
- A project has a budget of $300,000 and is expected to last 10 months, with the work results and budget spread evenly across all months. The project just completed its 3rd month, the work is on schedule, and $65,000 has been spent. What is the cost variance? How efficient (in %) must work progress be to complete on time and within budget?arrow_forwardWhat is the definition of the latest completion time (LCT) of a project activity?a. LCT(Ai) = Max{LST(Aj) for which Ajis a successor of Ai}b. LCT(Ai) = Min{LST(Aj) for which Ajis a successor of Ai}c. LCT(Ai) = Max{LST(Aj) for which Ajis a predecessor of Ai}d. LCT(Ai) = Min{LST(Aj) for which Ajis a predecessor of Ai}arrow_forwardNormal completion time and accelerated completion time Steps that can be taken to crash the project to the shortest time at the lowest cost. Hint: Determine each step's cost and the duration of the project at that stage.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.