Concept explainers
Performance-based options
• LO19–2
Refer to the situation described in BE 19–8. Suppose that Farmer initially estimates that it is not probable the goal will be achieved, but then after one year, Farmer estimates that it is probable that divisional revenue will increase by 5% by the end of 2020. What action will be taken to account for the options in 2019 and thereafter?
BE 19–8
Performance-based options
• LO19–2
On October 1, 2018, Farmer Fabrication issued stock options for 100,000 shares to a division manager. The options have an estimated fair value of $6 each. To provide additional incentive for managerial achievement, the options are not exercisable unless divisional revenue increases by 5% in three years. Farmer initially estimates that it is probable the goal will be achieved. How much compensation will be recorded in each of the next three years?
Want to see the full answer?
Check out a sample textbook solutionChapter 19 Solutions
Intermediate Accounting
- P9arrow_forward5 Problem 13-6 (Algo) Coefficient of variation [LO13-1] Possible outcomes for three investment alternatives and their probabilities of occurrence are given next. Failure Acceptable eBook Successful Hint Alternative 1 Outcomes 30 Probability Outcomes Alternative 2 Probability Alternative 3 Outcomes Probability 0.20 80 0.40 90 0.40 60 120 0.20 140 0.20 225 0.40 0.60 210 0.40 380 0.20 Using the coefficient of variation, rank the three alternatives in terms of risk from lowest to highest. Note: Do not round intermediate calculations. Round your answers to 3 decimal places. Coefficient of Variation Rank Print Alternative 1 Alternative 2 Alternative 3 Referencesarrow_forwardHW #10 (continued) JK7 [7 pts] For the satellite contract described in the in-class exercise, the build plan and spending profile is shown below. - The contract calls for the following payment profile from the customer • Payments = 80% of company expenditures in each year, with an additional milestone payment of $100M in the year that each satellite is completed • Create a spreadsheet to model the full 10-year program and use it to (a) annual cash flow (b) IRR for the full 7-satellite, 10-year program 1 2 3 4 5 6 7 8 9 10 S1 10% 30% 40% 20% S2 30% 50% 20% S3 30% 50% 20% S4 30% 50% 20% S5 30% 50% 20% S6 30% 50% 20% S7 30% 50% 20%arrow_forward
- v.3arrow_forwardD13 Write down which options to long or short, and how many numbers of contracts of each option do you need to long or short to construct the pay off as follows:arrow_forwardid 1 :uonsenn siu i 29 o Consider the following two projects: Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Discount Project C/F Alpha C/F C/F C/F C/F C/F C/F C/F Rate -79 20 25 30 35 40 N/A N/A 12% Beta - 80 25 25 25 25 25 25 25 13% The net present value (NPV) for project alpha is closest to: A. $31 B. $25 OC. $21 D. $38 Click to select your answer. MacE esc D00 O O O 0arrow_forward
- Problem 13-6 (Algo) Coefficient of variation [LO13-1] Possible outcomes for three investment alternatives and their probabilities of occurrence are given next. Failure Acceptable Successful Alternative 1 Alternative 2 Outcomes Probability Outcomes Probability 0.10 80 0.20 0.50 195 0.40 0.40 250 0.40 Alternative 1 Alternative 2 Alternative 3 30 70 105 Coefficient of Variation Alternative 3 Using the coefficient of variation, rank the three alternatives in terms of risk from lowest to highest. Note: Do not round intermediate calculations. Round your answers to 3 decimal places. Rank Outcomes 110 350 400 Probability 0.30 0.50 0.20arrow_forwardQuestion 19 You are considering the following two mutually exclusive projects. Which project should be accepted if the discount rate is 12%? Year Project A Project B 0 -$42,000 -$42,000 1 14,000 30,000 2 14,000 10,000 3 30,000 14,000 Group of answer choices Project A because the crossover point is higher than the discount rate Project A because the crossover point is lower than the discount rate Project B because the crossover point is higher than the discount rate Project B because the crossover point is lower than the discount rate Either project A or B because you are indifferent.arrow_forwardProblem 13-1 (Algo) Risk-averse [LO13-2] Assume you are risk-averse and have the following three choices. Standard Deviation ABC Expected Value $ 2,790 2,860 2,200 A B с $ 1,670 1,520 630 a. Compute the coefficient of variation for each. Note: Round your answers to 3 decimal places. Coefficient of Variation b. Which project will you select? O Project A O Project B O Project Carrow_forward
- i נ ences Problem 13-5 Calculating Expected Return [LO1] Consider the following information: State of Economy Recession Boom Economy Probability of Portfolio State of Return if State Occurs -20 28 35 .65 Calculate the expected return. (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Expected return %arrow_forwardA 134.arrow_forwardProblem 10-9 Scenario Analysis (LO3) The most likely outcomes for a particular project are estimated as follows: \table[[Unit price:,$70arrow_forward
- Pkg Acc Infor Systems MS VISIO CDFinanceISBN:9781133935940Author:Ulric J. GelinasPublisher:CENGAGE LFundamentals of Financial Management (MindTap Cou...FinanceISBN:9781285867977Author:Eugene F. Brigham, Joel F. HoustonPublisher:Cengage Learning
- Fundamentals of Financial Management (MindTap Cou...FinanceISBN:9781337395250Author:Eugene F. Brigham, Joel F. HoustonPublisher:Cengage Learning