a)

1)

Summary Introduction

To determine: The system utilization rate.

Introduction: System utilization refers to percentage amount of capacity which is utilized or we can say that actual output is divided by potential output. It is operational metric for business which indicates aggregate productive capacity.

It reflects the ratio of demand to capacity or supply, it is also commonly known as Capacity utilization rate.

a)

1)

Expert Solution
Check Mark

Answer to Problem 1P

The system utilization rate is 0.600.

Explanation of Solution

Given information:

λ=3customer/hours

μ=5customer/hours

M=1

Formula,

ρ=λMμ

Where,

System utilization rate denoted by ρ

Demand rate (measured as arrival) denoted by λ

Supply rate (measured as service) denoted by Mμ

Calculation of the system utilization:

ρ=λMμ=31×5=0.6000

Therefore, system utilization rate is 0.6000.

1)

Summary Introduction

To determine: The system utilization rate.

Introduction: System utilization refers to percentage amount of capacity which is utilized or we can say that actual output is divided by potential output. It is operational metric for business which indicates aggregate productive capacity.

It reflects the ratio of demand to capacity or supply, it is also commonly known as Capacity utilization rate.

1)

Expert Solution
Check Mark

Answer to Problem 1P

The system utilization rate is 0.600.

Explanation of Solution

Given information:

λ=3customer/hours

μ=5customer/hours

M=1

Formula,

ρ=λMμ

Where,

System utilization rate denoted by ρ

Demand rate (measured as arrival) denoted by λ

Supply rate (measured as service) denoted by Mμ

Calculation of the system utilization:

ρ=λMμ=31×5=0.6000

Therefore, system utilization rate is 0.6000.

2)

Summary Introduction

To determine: The average number customers waiting for service in line.

2)

Expert Solution
Check Mark

Answer to Problem 1P

Average number of customers waiting in line (Lq) is 0.9000.

Explanation of Solution

Explanation

Given information:

λ=3customer/hours

μ=5customer/hours

Formula as per single server model of average number customers waiting for service in line

Lq=λ2μ(μλ)

Where,

Lq is denoted by average number customers waiting for service in line

Demand rate (measured as arrival) denoted by λ

Supply rate per server denoted by μ

Calculation of Average number of customers waiting in line (Lq):

Lq=λ2μ(μλ)=325(53)=0.900

Therefore, average number of customers waiting in line (Lq) is 0.9000.

3)

Summary Introduction

To determine: Average number of customers waiting time.

3)

Expert Solution
Check Mark

Answer to Problem 1P

The average number customers waiting time ( Wq ) is 0.3000.

Explanation of Solution

Given information:

λ=3customer/hours

Formula as per single server model of average number customers waiting for service in line:

Wq=Lqλ

Where,

Lq is denoted by average number customers waiting for service in line

Wq is denoted by average number customers waiting time

Demand rate (measured as arrival) denoted by λ

Calculation of Average number of customers waiting in line ( Wq ):

Wq=Lqλ=0.90003=0.3000

Therefore, average number customers waiting time ( Wq ) is 0.3000.

b)

1)

Summary Introduction

To determine: The average number of customer waiting for repairs.

b)

1)

Expert Solution
Check Mark

Answer to Problem 1P

Average number of customers waiting in line (Lq) is 2.250.

Explanation of Solution

Given information:

λ=3 repair calls/8-hour day

Mean service time: 2 hours

M =1

Calculation of μ

μ=productivehoursmeanservicetime=82=4repaircall/8-hour day

Formula as per single server model of average number customers waiting for service in line:

Lq=λ2μ(μλ)

Where,

Lq is denoted by average number customers waiting for service in line

Demand rate (measured as arrival) denoted by λ

Supply rate per server denoted by μ

Calculation of Average number of customers waiting in line (Lq):

Lq=λ2μ(μλ)=324(43)=2.250

Therefore, Average number of customers waiting in line (Lq) is 2.250.

1)

Summary Introduction

To determine: The average number of customer waiting for repairs.

1)

Expert Solution
Check Mark

Answer to Problem 1P

Average number of customers waiting in line (Lq) is 2.250.

Explanation of Solution

Given information:

λ=3 repair calls/8-hour day

Mean service time: 2 hours

M =1

Calculation of μ

μ=productivehoursmeanservicetime=82=4repaircall/8-hour day

Formula as per single server model of average number customers waiting for service in line:

Lq=λ2μ(μλ)

Where,

Lq is denoted by average number customers waiting for service in line

Demand rate (measured as arrival) denoted by λ

Supply rate per server denoted by μ

Calculation of Average number of customers waiting in line (Lq):

Lq=λ2μ(μλ)=324(43)=2.250

Therefore, Average number of customers waiting in line (Lq) is 2.250.

2)

Summary Introduction

To determine: The system utilization rate.

Introduction: It reflects the ratio of demand to capacity or supply, it is also commonly known as Capacity utilization rate.

2)

Expert Solution
Check Mark

Answer to Problem 1P

The system utilization rate is 0.750.

Explanation of Solution

Given information:

λ=3customer/hours

μ=4 repair calls/8-hour day

M=1

Formula,

ρ=λMμ

Where,

System utilization rate denoted by ρ

Demand rate (measured as arrival) denoted by λ

Supply rate (measured as service) denoted by Mμ

Calculation of the system utilization:

ρ=λMμ=31×4=0.750

Therefore, system utilization rate is 0.750.

3)

Summary Introduction

To determine: The idle time.

3)

Expert Solution
Check Mark

Answer to Problem 1P

The idle time is 2hours per day.

Explanation of Solution

Calculation of the idle time:

Idletimepercentage=1Systemutilization=10.75=25.00%

Idletimehours=Idletimepercentage ×working hour perday=25%×8hours/day=2hours

Therefore, idle time per day per hours is 2hours per day.

4)

Summary Introduction

To determine: Probability of two or more customers in the system.

4)

Expert Solution
Check Mark

Answer to Problem 1P

The probability of two or more customers in the system is 0.5625.

Explanation of Solution

Step 1: Calculate the probability of less than two:

P<2=1(λμ)=1(34)2=10.5625=0.4375

Therefore, probability of less than two is 0.4375.

Step 2: Calculation probability of two or more than customer in the system:

P2=1P<2=10.4375=0.5625

Therefore, probability of less than two is 0.5625.

c)

1)

Summary Introduction

To determine: The system utilization rate.

c)

1)

Expert Solution
Check Mark

Answer to Problem 1P

The system utilization rate is 0.750.

Explanation of Solution

Given information

λ=18customer/hours

μ=12customer/hours

M=2

Formula:

ρ=λMμ

Where,

System utilization rate denoted by ρ

Demand rate (measured as arrival) denoted by λ

Supply rate (measured as service) denoted by Mμ

Calculation of the system utilization:

ρ=λMμ=182×12=0.750

Therefore, system utilization rate is 0.7500.

1)

Summary Introduction

To determine: The system utilization rate.

1)

Expert Solution
Check Mark

Answer to Problem 1P

The system utilization rate is 0.750.

Explanation of Solution

Given information

λ=18customer/hours

μ=12customer/hours

M=2

Formula:

ρ=λMμ

Where,

System utilization rate denoted by ρ

Demand rate (measured as arrival) denoted by λ

Supply rate (measured as service) denoted by Mμ

Calculation of the system utilization:

ρ=λMμ=182×12=0.750

Therefore, system utilization rate is 0.7500.

2)

Summary Introduction

To determine: Average number of customers in the system (Ls).

2)

Expert Solution
Check Mark

Answer to Problem 1P

Average number of customers in the system (Ls) is 3.429.

Explanation of Solution

Step 1: Calculation of the average number of customer served

r=λμ=1812=1.5

Therefore average number of customer served is 1.5.

Step 2: find the value of Lq

Given information:

λμ = 1.5 and M is 2

Then, from Infinite-source values table we find that value for Lq is 1.929.

For reference:

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 18, Problem 1P

Step 3Calculation of the average number of customers in the system (Ls)

Ls=Lq+λμ=1.929+1812=1.929+1.5=3.429

Therefore, the average number of customers in the system (Ls) is 3.429.

3)

Summary Introduction

To determine: Average time customers wait in line for service (Wq).

3)

Expert Solution
Check Mark

Answer to Problem 1P

Average time customers wait in line for service (Wq).is 0.107.

Explanation of Solution

Wq=Lqλ=1.92918=0.107

Therefore, the average time customers wait in line for service (Wq).is 0.107.

4)

Summary Introduction

To determine: The average waiting time for an arrival not immediately served (hours) (Wa).

4)

Expert Solution
Check Mark

Answer to Problem 1P

The average waiting time for an arrival not immediately served (hours) (Wa) is 0.167.

Explanation of Solution

Calculation of average waiting time for an arrival not immediately served (hours) (Wa):

Wa=1Mμλ=1(2×12)18=12418=16=0.167

Therefore, average waiting time for an arrival not immediately served (hours) (Wa) is 0.167 hours.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
“Implementing a Performance Management Communication Plan at Accounting, Inc.” Evaluate Accounting Inc.’s communication plan.  Specifically, does it answer all of the questions that a good communication plan should answer? Which questions are left unanswered?  How would you provide answers to the unanswered questions? “Implementing an Appeals Process at Accounting, Inc.”   If you were to design an appeals process to handle these complaints well, what would be the appeal process?  Describe the recommended process and why.
The annual demand for water bottles at Mega Stores is 500 units, with an ordering cost of Rs. 200 per order. If the annual inventory holding cost is estimated to be 20%. of unit cost, how frequently should he replenish his stocks? Further, suppose the supplier offers him a discount on bulk ordering as given below. Can the manager reduce his costs by taking advantage of either of these discounts? Recommend the best ordering policy for the store. Order size Unit cost (Rs.) 1 – 49 pcs. 20.00 50 – 149 pcs. 19.50 150 – 299 pcs. 19.00 300 pcs. or more 18.00
Help answer showing level work and formulas
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,