Concept explainers
Three recent college graduates have formed a
a. Draw the precedence diagram.
b. What is the probability that the project can be completed in 24 days or less? In 21 days or less?
c. Suppose it is now the end of the seventh day and that activities A and B have been completed while activity D is 50 percent completed. Time estimates for the completion of activity D are 5, 6, and 7. Activities C and H are ready to begin. Determine the probability of finishing the project by day 24 and the probability of finishing by day 21.
d. The partners have decided that shortening the project by two days would be beneficial, as long as it doesn’t cost more than about $20,000. They have estimated the daily crashing costs for each activity in thousands, as shown in the following table. Which activities should be crashed, and what further analysis would they probably want to do?
Want to see the full answer?
Check out a sample textbook solutionChapter 17 Solutions
OPERATIONS MANAGEMENT CNCT W/EBK
- Key: A is optimist time, M is the most likely time and B is the pessimistic time. i). Calculate the expected time for each activity ii. Draw a Gantt Chart from the same information above iii. State the critical path and the maximum number of weeks the project will take to be completed. iv. Discuss the pros and cons of using the Gantt chart as a planning and scheduling tool?arrow_forwardIMPORTANT NOTE: All Project Management Questions are from the same Project. You only need to solve the project one time. The CEO of Carol O'Lights Manufacturing, produces custom-built relay devices for auto makers. The most recent project undertaken by Ms. O'Lights requires 11 different activities. The activities necessary to build an experimental relay model and related data are given in the following table. What is the Early Start on Activity G?arrow_forwardRecently, you were assigned to manage a project to remodelthe seminar room for your company. You have constructed anetwork diagram depicting the various activities in the project(Figure 7.13). In addition, you have asked your team to estimatethe amount of time that they would expect each of the activitiesto take. Their responses are shown in the following table: a. What is the expected completion time of the project?b. What is the probability of completing the project in 21 days?c. What is the probability of completing the project in 17 days?arrow_forward
- A) What is the critical path B) what is the expected completion time for the project? C) What is the expected or mean completion time for activity B ? D) what is the expected or mean completion time for activity F ?arrow_forwardThe following eight activities constitute an overall bar chart portrayal of a 4-month project. Two months after the start of the project. Activities A, C, D are completed, E is 50% complete and B is 25% complete. The total cost that has been spent is $10,500. For this project, using earned value concepts, determine the schedule and cost variance. Is the project ahead or behind schedule? Over or under budget? Activity A B VAHE с D F Cost $2,000 $8,000 $2,000 $5,000 $1,000 $15,000 Month 1 Month 2 Month 3 Month 4arrow_forwardThis is one of my practice questions!arrow_forward
- Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. Use Table B. ΤΙME IN DAYS Immediate Activity Predecessor Optimistic Most Likely Pessimistic A 7 B 8 8 11 C A 6 8 11 9. 12 15 E 6 F D 7 G F 2 3 7 H B 4 4 I H 7 8 End E, G, I Click here for the Excel Data File a. What is the probability that the project can be completed in 24 days or less? In 21 days or less? (Round your te and z values to 2 decimal places and "Standard deviation" to 3 decimal places. Round your final answers to 4 decimal places.) Days Probability 24 days or less 21 days or lessarrow_forwardAfter the first month of a project, the Actual Cost was $400 and the planned cost for the first month was $500. Currently, only 50% of the work have been completed. Based on this information, calculate the following: a.Earned Value b.Cost Variance c.Schedule Variancearrow_forwardThree activities are candidates for crashing on a project network for a large computer installation (all are, of course, critical) Activity details are in the following table: a) Activity that should be orashed first to reduce the project duration by 1 day is b) Activity that should be crashed next to reduce the project duration by one additional day is c) Total cost of crashing the project by 2 days = S (Enter your response as an integer) Normal Activity Time (days) A B C 7 4 11 Crash Normal Time (days) Cost $8,000 $1,200 $4,200 6 2 9 Total Cost with Crashing Immediate Predecessor(s) $6,500 $3,000 $6.200 A Barrow_forward
- A given task was estimated to cost $15,750 to complete. Currently, the project team has completed approximately 65% of the task, and have spent $10,500. a. Determine the indices: AC, PV, and EV b. Derive the values for cost and schedule variances, as well as cost performance and schedule performance indices. Is this project ahead or behind on schedule, and is it ahead or behind on budget?arrow_forwardPlease do not give solution in image format thanku Please answer for all of the activitiesarrow_forwardConsider the office renovation project data in Table 7.16. A “zero” time estimate means that the activity could take a very small amount of time and should be treated as a numeric zero in the analysis.a. Based on the critical path, find the probability of completing the office renovation project by 39 days.b. Find the date by which you would be 90 percent sure of completing the project.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.