Question
Book Icon
Chapter 15, Problem 7P

a)

Summary Introduction

To solve: The given information by using the assignment method.

Introduction: The assignment method is one of the methods available in the process of optimization. Here, the jobs are assigned to every available resource.

a)

Expert Solution
Check Mark

Answer to Problem 7P

The problem has been solved by using the assignment method.

Explanation of Solution

Given information:

Squad Case
A B C D E
1 14 7 3 7 27
2 20 7 12 6 30
3 10 3 4 5 21
4 8 12 7 12 21
5 13 25 24 26 8

Assign cases to respective squads:

Row minimum:

Squad Case Row minimum
A B C D E
1 14 7 3 7 27 3
2 20 7 12 6 30 6
3 10 3 4 5 21 3
4 8 12 7 12 21 7
5 13 25 24 26 8 8

Table after the row subtraction is given below:

The row minimum value mentioned in the above table should be subtracted from each value of the row.

Squad Case
A B C D E
1 11 4 0 4 24
2 14 1 6 0 24
3 7 0 1 2 18
4 1 5 0 5 14
5 5 17 16 18 0

Column minimum:

Squad Case
A B C D E
1 11 4 0 4 24
2 14 1 6 0 24
3 7 0 1 2 18
4 1 5 0 5 14
5 5 17 16 18 0
Column minimum 1 0 0 0 0

Table after the column subtraction is given below:

The column minimum value mentioned in the above table should be subtracted from each value of the column.

Squad Case
A B C D E
1 10 4 0 4 24
2 13 1 6 0 24
3 6 0 1 2 18
4 0 5 0 5 14
5 4 17 16 18 0

Assigning squads to the cases:

Step 1: The first row must be checked for the zero. As there is only one zero in the first row, it must be marked and the entire column should be striked out.

Principles Of Operations Management, Chapter 15, Problem 7P , additional homework tip  1

Step 2: As only one zero is available in the second row, it must be marked and the entire column should be striked out.

Principles Of Operations Management, Chapter 15, Problem 7P , additional homework tip  2

Step 3: As only one zero is available in the third row, it must be marked and the entire column should be striked out.

Principles Of Operations Management, Chapter 15, Problem 7P , additional homework tip  3

Step 4: As only one zero is available in the fourth row, it must be marked and the entire column should be striked out.

Principles Of Operations Management, Chapter 15, Problem 7P , additional homework tip  4

Step 5: As only one zero is available in the fourth row, it must be marked and the entire column should be striked out.

Principles Of Operations Management, Chapter 15, Problem 7P , additional homework tip  5

Step 5: All the zeroes in the table have been striked out. The marked zeroes help to assign the cases to the squads.

Calculate the total person-days that are projected by using the assignment method:

The value has been taken in the given information where, the zeroes have been marked in the final answer.

Squad Case Value
1 C 3
2 D 6
3 B 3
4 A 8
5 E 8
Total 28
Conclusion

According to the table, Squad 1 should be assigned to Case C, Squad 2 should be assigned to Case D, Squad 3 should be assigned to Case B, Squad 4 should be assigned to Case A, and Squad 5 should be assigned to Case E. The total person days are 28 days.

b)

Summary Introduction

To solve: The given information by using assignment method.

Introduction: The assignment method is one of the methods available in the process of optimization. Here, the jobs are assigned to every available resource.

b)

Expert Solution
Check Mark

Answer to Problem 7P

The problem has been solved by using the assignment method.

Explanation of Solution

Given information:

Squad Case
A B C D E
1 14 7 3 7 27
2 20 7 12 6 30
3 10 3 4 5 21
4 8 12 7 12 21
5 13 25 24 26 8

It is given that the squad 5 cannot work on Case 5 because of the conflict.

Modified given information:

It is given that the squad 5 cannot work on Case 5 because of the conflict. Thus, the value should be modified from 8 to any other higher values. It is taken as 50 here.

Squad Case
A B C D E
1 14 7 3 7 27
2 20 7 12 6 30
3 10 3 4 5 21
4 8 12 7 12 21
5 13 25 24 26 50

Assign cases to respective squads:

Row minimum:

Squad Case Row minimum
A B C D E
1 14 7 3 7 27 3
2 20 7 12 6 30 6
3 10 3 4 5 21 3
4 8 12 7 12 21 7
5 13 25 24 26 50 13

Table after the row subtraction is given below:

The row minimum value mentioned in the above table should be subtracted from each value of the row.

Squad Case
A B C D E
1 11 4 0 4 24
2 14 1 6 0 24
3 7 0 1 2 18
4 1 5 0 5 14
5 0 12 11 13 37

Column minimum:

Squad Case
A B C D E
1 11 4 0 4 24
2 14 1 6 0 24
3 7 0 1 2 18
4 1 5 0 5 14
5 0 12 11 13 37
Column minimum 0 0 0 0 14

Table after the column subtraction is given below:

The column minimum value mentioned in the above table should be subtracted from each value of the column.

Squad Case
A B C D E
1 11 4 0 4 10
2 14 1 6 0 10
3 7 0 1 2 4
4 1 5 0 5 0
5 0 12 11 13 23

Assigning squads to the cases:

Step 1: The first row must be checked for the zero. As there is only one zero in the first row, it must be marked and the entire column should be striked out.

Principles Of Operations Management, Chapter 15, Problem 7P , additional homework tip  6

Step 2: As only one zero is available in the second row, it must be marked, and the entire column should be striked out.

Principles Of Operations Management, Chapter 15, Problem 7P , additional homework tip  7

Step 3: As only one zero is available in the third row, it must be marked, and the entire column should be striked out.

Principles Of Operations Management, Chapter 15, Problem 7P , additional homework tip  8

Step 4: As only one zero is available in the fourth row, it must be marked, and the entire column should be striked out.

Principles Of Operations Management, Chapter 15, Problem 7P , additional homework tip  9

Step 5: As only one zero is available in the fifth row, it must be marked, and the entire column should be striked out.

Principles Of Operations Management, Chapter 15, Problem 7P , additional homework tip  10

Step 5: All the zeroes in the table have been strikedout. The marked zeroes help to assign the cases to the squads.

Calculate the total person days that are projected by using the assignment method:

The value has been taken in the given information where, the zeroes have been marked in the final answer.

Squad Case Value
1 C 3
2 D 6
3 B 3
4 E 21
5 A 13
Total 46
Conclusion

According to the table, Squad 1should be assigned to Case C, Squad 2 should be assigned to Case D, Squad 3 should be assigned to Case B, Squad 4 should be assigned to Case E, and Squad 5 should be assigned to Case A. The total person days are 46 days.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
A small furniture manufacturer produces tables and chairs. Each product must go through three stages of the manufacturing process – assembly, finishing, and inspection. Each table requires 3 hours of assembly, 2 hours of finishing, and 1 hour of inspection. The profit per table is $120 while the profit per chair is $80. Currently, each week there are 200 hours of assembly time available, 180 hours of finishing time, and 40 hours of inspection time. Linear programming is to be used to develop a production schedule. Define the variables as follows:  T = number of tables produced each week C= number of chairs produced each week According to the above information, what would the objective function be? (a) Maximize T+C (b) Maximize 120T + 80C (c) Maximize 200T+200C (d) Minimize 6T+5C (e) none of the above According to the information provided in Question 17, which of the following would be a necessary constraint in the problem? (a) T+C ≤ 40 (b) T+C ≤ 200 (c) T+C ≤ 180 (d) 120T+80C ≥ 1000…
As much detail as possible. Dietary Management- Nursing Home  Don't add any fill-in-the-blanks
Menu Planning Instructions Use the following questions and points as a guide to completing this assignment. The report should be typed. Give a copy to the facility preceptor. Submit a copy in your Foodservice System Management weekly submission. 1. Are there any federal regulations and state statutes or rules with which they must comply? Ask preceptor about regulations that could prescribe a certain amount of food that must be kept on hand for emergencies, etc. Is the facility accredited by any agency such as Joint Commission? 2. Describe the kind of menu the facility uses (may include standard select menu, menu specific to station, non-select, select, room service, etc.) 3. What type of foodservice does the facility have? This could be various stations to choose from, self-serve, 4. conventional, cook-chill, assembly-serve, etc. Are there things about the facility or system that place a constraint on the menu to be served? Consider how patients/guests are served (e.g. do they serve…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Foundations of Business (MindTap Course List)
Marketing
ISBN:9781337386920
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning
Text book image
Foundations of Business - Standalone book (MindTa...
Marketing
ISBN:9781285193946
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,