Concept explainers
a)
To determine: Sequence of jobs based on decision rule First Come First Served (FCFS).
Introduction: First Come First Served is the
a)

Answer to Problem 19P
The sequence is A-B-C-D-E.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Due date |
A | 110 | 20 | 180 |
B | 120 | 30 | 200 |
C | 122 | 10 | 175 |
D | 125 | 16 | 230 |
E | 130 | 18 | 210 |
All the jobs are arrived on day 130.
Determine the sequence of the job using FCFS:
Job sequence | Processing time | Flow time | Due date | Start day | End day | Lateness |
A | 20 | 20 | 180 | 130 | 149 | |
B | 30 | 50 | 200 | 150 | 179 | |
C | 10 | 60 | 175 | 180 | 189 | 14 |
D | 16 | 76 | 230 | 190 | 205 | |
E | 18 | 94 | 210 | 206 | 223 | 13 |
Total | 94 | 300 | 27 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 130.
End day of Job A:
Jobs arrival rate is given as 130. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 149.
End day of Job B:
Start day of Job B is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 179.
End day of Job C:
Start day of Job C is the next day of the end day of Job B. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 189.
End day of Job D:
Start day of Job D is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 205.
End day of Job E:
Start day of Job E is the next day of the end day of Job D. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job E is 223.
Lateness of Job A, Job B, and Job D:
End day of Job A, Job B, and Job D is less than its respective due date. Hence, there would be no lateness.
Lateness of Job C:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job C is 14.
Lateness of Job E:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job E is 13.
b)
To determine: Sequence of jobs based on decision rule Earliest Due Date (EDD).
Introduction: Earliest Due Date is the scheduling rule, which helps to arrange the sequence in the order. Here, the job with the earliest due date would be served first. Then, the process would be going on from the earliest due date to the latest due date.
b)

Answer to Problem 19P
The sequence is C-A-B-E-D.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Due date |
A | 110 | 20 | 180 |
B | 120 | 30 | 200 |
C | 122 | 10 | 175 |
D | 125 | 16 | 230 |
E | 130 | 18 | 210 |
All the jobs are arrived on day 130.
Determine the sequence of the job using EDD:
Job sequence | Processing time | Flow time | Due date | Start day | End day | Lateness |
C | 10 | 10 | 175 | 130 | 139 | |
A | 20 | 30 | 180 | 140 | 159 | |
B | 30 | 60 | 200 | 160 | 189 | |
E | 18 | 78 | 210 | 190 | 207 | |
D | 16 | 94 | 230 | 208 | 223 | |
Total | 94 | 272 |
Working note:
Duration and due date for the jobs have been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 130. The job should be arranged based on due date. Due date should be assembled in the ascending order.
End day of Job C:
Jobs arrival rate is given as 130. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 139.
End day of Job A:
Start day of Job A is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 159.
End day of Job B:
Start day of Job B is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 189.
End day of Job E:
Start day of Job E is the next day of the end day of Job B. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job E is 207.
End day of Job D:
Start day of Job D is the next day of the end day of Job E. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 223.
Lateness of Job A, Job B, Job C, Job D, and Job E:
End day of all the jobs is less than its respective due date. Hence, there would be no lateness.
c)
To determine: Sequence of jobs based on decision rule Shortest Processing Time (SPT).
Introduction: Shortest Processing Tine is the scheduling rule which helps to arrange the sequence in the order. Here, the job with the shortest duration would be served first. Then, the process would be going on from shortest to largest duration.
c)

Answer to Problem 19P
The sequence is C-D-E-A-B.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Due date |
A | 110 | 20 | 180 |
B | 120 | 30 | 200 |
C | 122 | 10 | 175 |
D | 125 | 16 | 230 |
E | 130 | 18 | 210 |
All the jobs are arrived on day 130.
Determine the sequence of the job using SPT:
Job sequence | Processing time | Flow time | Due date | Start day | End day | Lateness |
C | 10 | 10 | 175 | 130 | 139 | |
D | 16 | 26 | 230 | 140 | 155 | |
E | 18 | 44 | 210 | 156 | 173 | |
A | 20 | 64 | 180 | 174 | 193 | 13 |
B | 30 | 94 | 200 | 194 | 223 | 23 |
Total | 94 | 238 | 36 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 130. The job should be arranged based on the duration (processing time). The duration should be assembled in the ascending order.
End day of Job C:
Jobs arrival rate is given as 130. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 139.
End day of Job D:
Start day of Job D is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 155.
End day of Job E:
Start day of Job E is the next day of the end day of Job D. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job E is 173.
End day of Job A:
Start day of Job A is the next day of the end day of Job E. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 193.
End day of Job B:
Start day of Job B is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 223.
Lateness of Job C, Job D, and Job E:
End day of Job C, Job D, and Job E are less than its respective due date. Hence, there would be no lateness.
Lateness of Job A:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job A is 13.
Lateness of Job B:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job B is 23.
d)
To determine: Sequence of jobs based on decision rule Longest Processing Time (LPT).
Introduction: Largest Processing Tine is the scheduling rule, which helps to arrange the sequence in the order. Here, the job with the largest duration would be served first. Then, the process would be going on from largest to shortest duration.
d)

Answer to Problem 19P
The sequence is B-A-E-D-C.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Due date |
A | 110 | 20 | 180 |
B | 120 | 30 | 200 |
C | 122 | 10 | 175 |
D | 125 | 16 | 230 |
E | 130 | 18 | 210 |
All the jobs are arrived on day 130.
Determine the sequence of the job using LPT:
Job sequence | Processing time | Flow time | Due date | Start day | End day | Lateness |
B | 30 | 30 | 200 | 130 | 159 | |
A | 20 | 50 | 180 | 160 | 179 | |
E | 18 | 68 | 210 | 180 | 197 | |
D | 16 | 84 | 230 | 198 | 213 | |
C | 10 | 94 | 175 | 214 | 223 | 48 |
Total | 94 | 326 | 48 |
Working note:
Duration and due date for the jobs have been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 130. The job should be arranged based on the duration (processing time). The duration should be assembled in the descending order
End day of Job B:
Jobs arrival rate is given as 130. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 159.
End day of Job A:
Start day of Job A is the next day of the end day of Job B. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 179.
End day of Job E:
Start day of Job E is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job E is 197.
End day of Job D:
Start day of Job D is the next day of the end day of Job E. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 213.
End day of Job C:
Start day of Job C is the next day of the end day of Job D. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 223.
Lateness of Job B, Job A, Job E, and Job D:
End day of Job B, Job A, Job E, and Job D are less than its respective due date. Hence, there would be no lateness.
Lateness of Job C:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job C is 48.
Summary:
Scheduling rule | Average lateness | Average flow time | Average number of jobs in system |
FCFS | 5.4 | 60.0 | 3.2 |
EDD | 0.0 | 54.4 | 2.9 |
SPT | 7.2 | 47.6 | 2.5 |
LPT | 9.6 | 65.2 | 3.5 |
First Come First Served (FCFS):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 5.4.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 60.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 3.2.
Earliest Due Date (EDD):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 0.0.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 54.4.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.9.
Shortest Processing Time (SPT):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 7.2.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 47.6.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.5.
Longest Processing Time (LPT):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 9.6.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 65.2.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 3.55.
Hence, Earliest Due Date is the best method for the average lateness. Shortest processing time has the minimum average flow time and average number of jobs in systems.
Want to see more full solutions like this?
Chapter 15 Solutions
Principles Of Operations Management
- This crosstab shows product sub-category sales within categories, broken out by sales quarter. The quarterly values for each sub-category increase within each category, with the largest value at the bottom. Using Running Total as the calculation type, which scope and direction option gives this result?arrow_forwardHow do management leaders, in order top meet organizational objectives, modify group behavior by using terms and concepts of diagnose, explain, predict and modify with examples?arrow_forwardNot use ai pleasearrow_forward
- In what ways does self-leadership affect the world around us?arrow_forward6:35 nvas.liberty.edu < 72% i You must post before seeing replies. Edit history will be available to instructors. ☑ Due Feb 13 33 Replies (33) 50 points Discussion Thread: How to Look at the Bible After reading the assigned chapters in Everyday Bible Study (Chapters 1-5), create a learning log that lists 10 quotes from the assigned reading that highlight either a concept that resonated with you or a concept that represents new learning for you. Following each of these quotes, you must provide a 3-5 sentence explanation of how the selected quote represents either what resonated with you or this new learning. For an example of this type of thread, please see the provided example. Pleas ◄ Previous cussion Assignment instructions ✓ and the ||| Next ▸arrow_forwardDo a report to promote an innovative product/service within an organization of your choice. In your assignment, you need to focus on the below: 1. Give a brief introduction of the innovative product/service you are thinking about within an organization of your choice. 2. Analyze how you are going to promote your idea internally to your colleagues (e.g. meetings, presenting and disseminating the information). 3. Explain how you are going to convince them that this product/service is applicable and that it will create a competitive advantage in the market. 4. Refer to a similar product/service that your competitors have and analyze how the competitors’ product can be considered as a threat to your new product/service. 5. Estimate how much will the whole procedure cost to the business. 6. In your conclusions, describe how the new product/service will influence the whole organization’s environment. 3000 words and include and introducion, conclusion and references.arrow_forward
- For my learning and not a assignment question: Tesla, the U.S. electric vehicle manufacturer, has recently proposed to join Indonesia’s initiative to develop an EV battery supply chain within the country. This information was shared by a senior Indonesian government official, who noted that the government received Tesla's proposal on Thursday. Indonesia, known for its rich nickel reserves, is already in discussions with companies like China's Contemporary Amperex Technology (CATL) and South Korea's LG Chem to establish a comprehensive EV battery supply chain that covers everything from raw materials to the final product. Sepian Hari Seto, the deputy for investment and mining at the Coordinating Ministry of Maritime Affairs and Investment, expressed enthusiasm for Tesla's advanced lithium battery technology. He conveyed that the collaboration with Tesla, along with CATL and LG, presents a valuable opportunity for technology transfer and learning. Furthermore, Seto mentioned the…arrow_forwardYour company is considering investing in a Human Resource Information System (HRIS).Briefly explain the strategies for justifying HRIS investments.arrow_forwardPresent the criteria you would utilize to determine if a right should be extended to an employee or if it would unnecessarily impact a manager’s ability to manage. Additionally, assess how you would balance the need for management rights against the need for employee rights, and how greater employee rights positively and negatively affect the future of the organization.arrow_forward
- provide schoarly research and references as to how internal and exteral audit is a risk management strategy to mitigate risk in a financial institutionarrow_forwardLearning Activity 4: Strategic Sales Management How has the advent and rapid evolution of digital technology transformed traditional sales management strategies, and what do you think are the most significant challenges and opportunities this transformation brings? In addition, please select and describe an example of company that has embraced change and implemented a unique and effective sales strategy.arrow_forward1) View the two video excerpts (Ctrl+Click on the two links), Preview 1 to the Goal Movie (Goldratt) (11.17 minutes), https://www.youtube.com/watch?v=2RVMgV37O_k and Preview 2 to the Goal Movie – How to Version (Goldratt) (9.40 minutes) https://www.youtube.com/watch?v=t_oM9LvK0rU and answer the following questions: a) What problems is UniCo facing and how are they tackling these problems currently? b) What advice did Jonah give to Rogo, and what lessons did Rogo learn from “Herbie’s Hike”? c) How do you think Rogo can leverage Jonah’s advice (as well as the lessons learnt from “Herbie’s Hike”) to solve UniCo’s problems? 2) A business program has the facilities and faculty to handle an enrollment of 2,000 new students per semester. However, in an effort to limit class sizes to a “reasonable” level the business dean, placed a ceiling on enrollment of 1,500 new students. Although there was ample demand for business courses last semester, conflicting schedules allowed only 1,450 new…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Foundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage LearningFoundations of Business - Standalone book (MindTa...MarketingISBN:9781285193946Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage Learning