Question
Chapter 14, Problem 9P
Summary Introduction
To determine: Takt time if match capacity and demand.
Introduction: Takt refers to “musical meter” or “pulse” in German. Takt time is the process duration required in a production system to counterpart the velocity of manufacturing to the request rate. It is once in a while said to be the pulse of a lean production system. It is the greatest measure of time in which an item should be delivered with a specific end goal to fulfill client request.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A call center has been serving 900 customers per day, with a 10% capacity cushion. There have been complaints about the length of time customers have to wait before their call is answered. If the manager of the call center wants to double the capacity cushion, how much extra capacity is needed?
Raj’s Dental Clinic provides general dental care to residents of Hoboken on a walk-in basis. Theclinic has started receiving complaints from patients that the waiting time is too long and has askedyou to investigate whether this problem can be solved.Upon arrival, customers first receive a series of paperwork from the receptionist and fill out relevantinformation such as personal health records and insurance provider. The form is then handed backto the receptionist who enters the information into the computer system for the dentist to see. Adental assistant then takes an X-ray from the patient. A dentist then performs the checkup anddiscusses any issues with the patient.Based on conversations with staff members at the clinic, you have obtained the following informationon the process:• It takes about 5 minutes for a customer to fill out the paperwork.• Entry of information on the paperwork into the system and verification with past recordstakes another 5 minutes for a receptionist.…
Compute the capacity (i.e. processing rate) for each of the following scenarios. Convertyour answers to parts per hour.a. A four-station line with single-machine stations, where the average processing timesare 15, 20, 10 and 12 minutes, respectively.b. A three-station line where the number of machines at stations 1, 2 and 3 is 2, 6, and3, respectively; and the average processing times are 10, 24 and 18 minutes,respectively.
Chapter 14 Solutions
Operations Management (McGraw-Hill Series in Operations and Decision Sciences)
Ch. 14.S - Prob. 1DRQCh. 14.S - Prob. 2DRQCh. 14.S - Prob. 3DRQCh. 14.S - Prob. 4DRQCh. 14.S - Prob. 5DRQCh. 14.S - Prob. 6DRQCh. 14.S - Prob. 7DRQCh. 14.S - Prob. 8DRQCh. 14.S - Prob. 9DRQCh. 14.S - Prob. 10DRQ
Ch. 14.S - The probability that equipment used in a hospital...Ch. 14.S - The frequency of breakdown of a machine that...Ch. 14.S - Prob. 3PCh. 14 - Prob. 1DRQCh. 14 - Prob. 2DRQCh. 14 - Prob. 3DRQCh. 14 - Prob. 4DRQCh. 14 - Prob. 5DRQCh. 14 - Prob. 6DRQCh. 14 - Prob. 7DRQCh. 14 - Contrast push and pull methods ofmovi.ttg goods...Ch. 14 - Prob. 9DRQCh. 14 - Prob. 10DRQCh. 14 - Prob. 1TSCh. 14 - Prob. 2TSCh. 14 - Prob. 3TSCh. 14 - Prob. 1CTECh. 14 - Prob. 2CTECh. 14 - Prob. 1PCh. 14 - Prob. 2PCh. 14 - Prob. 3PCh. 14 - Determine the number of cycles per day and the...Ch. 14 - Given this set of daily service operations, and...Ch. 14 - Determine the number of cycles per day and a...Ch. 14 - Compute the takt time for a system where the total...Ch. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - What might Stephanie determine as the best...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- . The School of Dentistry at Penn provides general dental care to residents of Philadelphiaon a walk-in basis. Upon arrival, customers first provide health-relevant informationsuch as personal health records and insurance provider to a receptionist who entersthe information into the computer system for the dentist to see. A dental assistant thentakes an X-ray of the patient. A dentist then performs the checkup and discusses anyissues with the patient. Depending on the day, patients might have to wait at any of theseresources. This concludes the process. Draw a process flow diagram of this process.arrow_forwardThe Holt Million Corporation’s plant manufactures two different products: X and Y. The plant has three different machines: A, B, and C. Each performs different tasks and can work on only one unit of material at a time. Details for each product are shown in the table below: Product X Y Demand Per Week 200 units 100 units Selling Price $150 $160 Machine Operation Required A, B, C B, B, C Operation Times in Minutes 20, 15, 15 15, 15, 15 Raw Materials Needed RM-1, RM-2 RM-2, RM-3 Raw Materials Costs RM-1 = $40/unit, RM-2 or RM-3 = $20/unit Each product uses raw materials with costs as shown in the above table where the processing times and the machine required for each operation are also shown. Each machine is available 4,800 minutes per week. There are no system foul-ups. Demand is deterministic (i. e., no uncertainty). Operating expenses, including labor (but excluding raw materials) total $12,000 per week. Assuming…arrow_forwardThe question states 80 minutes per customer but the solution uses 8 minutes per customerarrow_forward
- The roller coaster at Treasure Island Amusement Park consists of 20 cars, each of which can carry up to two passengers. According to a time study, each run takes 4.5 minutes, and the time to unload and load riders is 5.5 minutes. What is the theoretical capacity of the system in number of passengers per hour? Round your answer down to the nearest whole number. _________ passengers per hourarrow_forwardThe Avis Company is a car rental company and is located three miles from the Los Angeles airport (LAX). Avis is dispatching a bus from its offices to the airport every 3 minutes. The average traveling time (a round trip) is 27 minutes. a. How many Avis buses are traveling to and from the airport? Note: Round your answer to the nearest whole number. Number of Avis buses b. The branch manager wants to improve the service and suggests dispatching buses every 1.0 minute. She argues that this will reduce the average traveling time (a round trip) to 4.0 minutes. Is she correct? If your answer is negative, then what will the average traveling time be? average traveling time is minutesarrow_forwardCompute the takt time for a service system that intended to perform a standardized service. Thesystem will have a total work time of 440 minutes per day, two 10-minute breaks, and an hour forlunch. The service system must process 90 jobs a dayarrow_forward
- The Avis Company is a car rental company and is located three miles from the Los Angeles airport (LAX). Avis is dispatching a bus from its offices to the airport every 2 minutes. The average traveling time (a round trip) is 20 minutes. How many Avis buses are traveling to and from the airport? The branch manager wants to improve the service and suggests dispatching buses every 0.5 minute. She argues that this will reduce the average traveling time (a round trip) to Avis’s offices to 2.5 minutes. Is she correct? If your answer is negative, then what will the average traveling time be?arrow_forwardA company receives parts from suppliers to be used in its manufacturing departments. The quality control department must perform two operation when shipments are received:i) Operation A-draw a random sample, package, and deliver to testing, andii) Operation B-test the materials and issue a disposition reportThere are currently six shipments waiting to be processed. The time estimates for processing these six shipments through quality control are:Shipment Operation A (hours) Operation B (hours)1 1.5 1.02 1.1 2.73 1.2 1.44 0.7…arrow_forwardIn the given time study below, if they are working for 8 hours and a target output of 650, solve for the value of missing green boxesarrow_forward
- What is the classification of the service does the shopping center provide based on divergence(standardized/customized), customer contact(high/low), nature of service(continuous/discrete), labor intensity(lanor/equipment intensive)?arrow_forwardWith a 10% availability buffer, a contact centre has been handling 900 consumers per day. Customers have shown dissatisfaction with the amount of time it takes for their call to be replied. How much additional space is needed if the call centre manager wishes to double the capacity cushion?arrow_forwardCompute the capacity (i.e. processing rate) for each of the following scenarios. Convertyour answers to parts per hour. A three-station line where the number of machines at stations 1, 2 and 3 is 2, 6, and3, respectively; and the average processing times are 10, 24 and 18 minutes,respectively.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY