EP PRIN.OF OPERATIONS MGMT.-MYOMLAB
10th Edition
ISBN: 9780134183848
Author: HEIZER
Publisher: PEARSON CO
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 14, Problem 5P
The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z.
a) Construct a product structure. Identify all levels, parents, and components.
b) Prepare a time-phased product structure.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The demand for subassembly Sis 100 units in week 7.Each unit ofS requires 1 unit ofT and 2 units ofU. Each unit ofT requires I unit ofY, 2 units ofW, and 1 unit of X. Finally, eachunit of U requires 2 units of Y and 3 units of Z. One firm manufacturesall items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make Y, 3 weeks to make W,I week to make X, 2 weeks to make Y, and I week to make Z.a) Construct a product structure. Identify all levels, parents, and components.b) Prepare a time-phased product structure.
Oh No!, Inc., sells three models of radar detector units. It buys the three basic models (E, F, and G)from a Japanese manufacturer and adds one, two, or four lights (component DLead times are one week for all items except C, which is two weeks. There are ample suppliesof the basic units (E, F, and G) on hand. There are also 10 units of B, 10 units of C, and 25 units ofD on hand. Lot-sizing rules are lot-for-lot ordering for all items except D, which must be ordered inmultiples of 100 units. There is a scheduled receipt of 100 units of D in week 1.The master schedule calls for 40 units of A in week 4, 60 units of B in week 5, and 30 units of Cin week 6. Prepare a material requirements plan for D and its parents) to further differentiate the models. D is bought from a domestic producer.
One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; items A, B, E, and F have two-week lead times; and item D has a lead time of three weeks. Lot-for-lot (L4L) lot sizing is used for items C, E, and F; lots of size 20, 40, and 160 are used for items A, B, and D, respectively. Items A, B, D, and E have on-hand (beginning) inventories of 5, 10, 100, and 100, respectively; all other items have zero beginning inventories. We are scheduled to receive 10 units of A in week 3, 20 units of B in week 7, 40 units of F in week 5, and 60 units of E in week 2; there are no other scheduled receipts. If 20 units of A are required in week 10, use the low-level-coded bill-of-materials (product structure tree) to find thenecessary planned order releases for all components.
Chapter 14 Solutions
EP PRIN.OF OPERATIONS MGMT.-MYOMLAB
Ch. 14 - Ethical Dilemma For many months your prospective...Ch. 14 - What is the difference between a gross...Ch. 14 - Prob. 2DQCh. 14 - What are the similarities between MRP and DRP?Ch. 14 - How does MRP II differ from MRP?Ch. 14 - Which is the best lot-sizing policy for...Ch. 14 - What impact does ignoring carrying cost in the...Ch. 14 - MRP is more than an inventory system; what...Ch. 14 - What are the options for the production planner...Ch. 14 - Master schedules are expressed in three different...
Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Using the information in Problem (The demand for subassembly Sis 100 units in week 7.Each unit ofS requires 1 unit ofT and 2 units ofU. Each unit ofT requires I unit ofY, 2 units ofW, and 1 unit of X. Finally, eachunit of U requires 2 units of Y and 3 units of Z. One firm manufacturesall items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make Y, 3 weeks to make W,I week to make X, 2 weeks to make Y, and I week to make Z.a) Construct a product structure. Identify all levels, parents, and components.b) Prepare a time-phased product structure. ), construct a netmaterial requirements plan using the following on-hand inventory.arrow_forwardUsing the information in Problem(The demand for subassembly Sis 100 units in week 7.Each unit ofS requires 1 unit ofT and 2 units ofU. Each unit ofT requires I unit ofY, 2 units ofW, and 1 unit of X. Finally, eachunit of U requires 2 units of Y and 3 units of Z. One firm manufacturesall items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make Y, 3 weeks to make W,I week to make X, 2 weeks to make Y, and I week to make Z.a) Construct a product structure. Identify all levels, parents, and components.b) Prepare a time-phased product structure. ), construct agross material requirements plan.arrow_forwardA product (A) consists of a base (B) and a casting (C). The base consists of a plate(P) and three fasteners (F). The lead time, current on-hand inventory and scheduledreceipts are given in the table below. All components are lot for lot. The MasterSchedule requires 100 units of product A be available in week 4 and 150 in week 6. Part Lead time On - Hand inventory Scheduled receipts A 1 20 None B 1 100 50 in Week 1 C 3 30 20 in Week 1, 30 in Week 2 P 2 0 50 in Week 1 F 3 0 30 in Week 1, 40 in Week 3 Required:A. Draw the product structure tree. B. Develop the MRP for Parts A, B, C, P, and F in order to meet the demand. Therows for MRP tables are Gross Requirement (GR), Scheduled Receipt (SR),On-Hand Inventory (OHI), Net Requirement (NR), and Planned Production (PP).arrow_forward
- Each A (finished product) requires 1 of component B and 2 of component C. Each B requires 2 of part D and 1 of part E and each C requires 1 of part D and 1 of part F.If the demand for product A is 50 units., and there are 15 units of B on hand and 50 units of C, how many units of Part D will be needed?arrow_forward3. The large parts of a playground A-frame (from which to hang a swing or glider) consist of a ridge pole, four legs, and two side braces. Each leg fastens to the ridge with one fastener set. Each side brace requires two fastener sets for attachment to the legs. There is one order outstanding, to make 180 frame kits. There are 500 legs and 20 ridge poles in inventory. There are no other large items in inventory, and no scheduled receipts. (a) Draw the product structure tree. (b) Calculate the net requirements to fulfill the outstanding order.arrow_forwardAssume that Product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. B is made of three units of E. If 50 units of Z is required to make, then how many units of C do they need?arrow_forward
- One unit of A is made of two units of B and one unit of C. B is made of three units of Dand one unit of F. C is composed of three units of B, one unit of D, and four units of E.D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F havetwo-week lead times; and Item D has a lead time of three weeks. Lot-for-lot (L4L) lot sizingis used for Items C, E, and F; lots of size 20, 40, and 160 are used for Items A, B, andD, respectively. Items A, B, D, and E have on-hand (beginning) inventories of 5, 10, 100,and 100, respectively; all other items have zero beginning inventories. We are scheduledto receive 10 units of A in Week 3, 20 units of B in Week 7, 40 units of F in Week 5, and60 units of E in Week 2; there are no other scheduled receipts. If 20 units of A are requiredin Week 10, use the low-level-coded bill-of-materials (product structure tree) to i nd thenecessary planned order releases for all components.arrow_forwardProduct PI is made of one unit of sub assembly A and four units of sub assembly B. Sub assembly A is made of 4 units of component X while sub assembly B is made of 2 units of X. one unit of Y and 3 units of Z. The manufacturing lead times PI, A, B, X, Y and Z are 1, 1, 1, 4, 6 and 1 (week) respectively. The lead time for delivery of PI in weeks isarrow_forwardAssume that Product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. B is made of three units of E. If 50 units of Z is required to make, then how many units of D do they need? Group of answer choices 250 400 300 150 550arrow_forward
- Courtney Kamauf schedules production of a popular Rustic Coffee Table at Kamauf Enterprises, Inc. The tablerequires a top, four legs, 18 gallon of stain, 116 gallon of glue, 2 shortbraces between the legs and 2 long braces between the legs, anda brass cap that goes on the bottom of each leg. She has 100 gallons of glue in inventory, but none of the other components. Allitems except the brass caps, stain, and glue are ordered on a lotfor-lot basis. The caps are purchased in quantities of 1,000, stainand glue by the gallon. Lead time is 1 day for each item. Schedulethe order releases necessary to produce 640 coffee tables on days5 and 6, and 128 on days 7 and 8.arrow_forwardItem STUVWX>N Y 2. The demand for assembly S is 100 units and it is due in Week 15. Each unit of S requires one unit of T and 0.5 units of U. Each unit of T requires one unit of V, two units of W, and one unit of X. Finally, each unit of U requires 0.5 units of Y and three units of Z. Z Item S T U V W X Y Z a) Calculate the planned orders for all the items. b) Use time phasing to determine an overall schedule. S OH Gross Requirements Inv 100 20 20 10 30 30 15 25 10 2 1 1 1 2 2 1 Lead Time Due Date (weeks) (week) 15 1 T W (2) X Net Requirements Release Date U (0.5) Y (0.5) Planned Order Z (3) Lot Size Policy L4L X10 X5 Min 50 F100 X50 F100 Min 100arrow_forwardEach A (finished good) requires 1 of component B and 2 of component C. Each B requires 2 of part D and 1 of part E; and each C requires 1 of part D and 1 of part F. If the demand for product A is 30 units, and there are 10 units of B on hand and none of C, how many units of part D will be needed?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY