Practical Operations Management
Practical Operations Management
2nd Edition
ISBN: 9781939297136
Author: Simpson
Publisher: HERCHER PUBLISHING,INCORPORATED
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 14, Problem 29P

(a)

Summary Introduction

Interpretation:

The time period required on an average to finish the job.

Concept Introduction:

Schedule the job on the basis of the FCFS . Then determine the average flow time for the each job. Calculate the average flow time that is required to finish the each job. Then calculate the average tardiness by adding the delay time of the order.

(a)

Expert Solution
Check Mark

Explanation of Solution

Given information:

The owner of an in HM Catering Company has four jobs to deliver today, shown in the order in which they are received:

    JobProcessing Time
    (hrs)
    Due (hrs)
    W45
    X39
    Y22
    Z11

Schedule the jobs based on the first come first served:

    Hours12345678910
    JobWXYZ

From the table, it is observed that the flow time of the job W is 4 hours which due in 5 hours. Thus, W has no delay in job.

The flow time of the job X is 7 hours which due in 9 hours. Thus, X has no delay in job.

The flow time of the job Y is 9 hours which due in 2 hours. Thus, X has 7 hours delay in job.

In order of the job Y :

The flow time of the job Z is 10 hours which due in 1 hour. Thus, it has a delay of 9 hours.

In order of the job Z :

Thus, calculate the average flow time that is required to finish the each job:

  4hours+7hours+9hours+10hours4=7.5hours

Now, calculating the average tardiness, adding the delay time of the order and divide it by the number of the orders;

  AT=0+0+7+94AT=4hours

(b)

Summary Introduction

Interpretation:

The job that will be late and the average job tardiness.

Concept Introduction:

Schedule the job on the basis of the SPT . Then determine the average flow time for the each job. Calculate the average flow time that is required to finish the each job. Then calculate the average tardiness by adding the delay time of the order.

(b)

Expert Solution
Check Mark

Explanation of Solution

Given information:

The owner of an in home meal catering company has four jobs to deliver today, shown in the order in which they are received:

    JobProcessing Time
    (hrs)
    Due (hrs)
    W45
    X39
    Y22
    Z11

Schedule the jobs based on the SPT ,

    Hours12345678910
    JobZYXW

From the table, it can be observed that Z has the 1 hour flow time which due in 1 hour. Z will be deliver on time.

  Y has the 3 hour flow time which due in 2 hour. Y will be delay 1 hour of the job.

  X has the 6 hour flow time which due in 9 hour. There will be no delay in order of the job X .

  W has the 10 hours flow time which due in 5 hours. Thus, there is delay of 5 hours on job order of W

Thus, calculate the average flow time that is required to finish the each job:

  1hours+3hours+6hours+10hours4=4hours

Now, calculating the average tardiness, adding the delay time of the order and divide it by the number of the orders;

  AT=0+1+0+54AT=1.5hours

(c)

Summary Introduction

Interpretation:

The job that will be late and the average job tardiness.

Concept Introduction:

Schedule the job on the basis of the EDD . Then determine the average flow time for the each job. Calculate the average flow time that is required to finish the each job. Then calculate the average tardiness by adding the delay time of the order.

(c)

Expert Solution
Check Mark

Explanation of Solution

Given information:

The owner of an in home meal catering company has four jobs to deliver today, shown in the order in which they are received:

    JobProcessing Time
    (hrs)
    Due (hrs)
    W45
    X39
    Y22
    Z11

Schedule the jobs based on the EDD ,

    Hours12345678910
    JobZYWX

From the table, it can be observed that Z has the 1 hour flow time which due in 1 hour. Z will be no delay.

  Y has the 3 hour flow time which due in 2 hour. Y will be delay 1 hour of the job.

  W has the 7 hour flow time which due in 5 hour. There will be delay of 2 hours for the job.

  X has the 10 hour flow time which due in 9 hours. There will be delay of 1 hour in order of the job X .

Now, calculating the tardiness, adding the delay time of the order and divide it by the number of the orders;

  AT=0+1+2+14AT=1hour

Thus, calculate the average flow time that is required to finish the each job:

  1hour+3hours+7hours+10hours4=5.25hours

(d)

Summary Introduction

Interpretation:

The most efficient sequence from the FCFS,SPT,EDD .

Concept Introduction:

The efficiency can be measured as the average tardiness or the number of jobs delayed and the average flow time.

(d)

Expert Solution
Check Mark

Explanation of Solution

Given information:

The owner of an in home meal catering company has four jobs to deliver today, shown in the order in which they are received:

    JobProcessing Time
    (hrs)
    Due (hrs)
    W45
    X39
    Y22
    Z11

The efficiency can be measured as the average tardiness or the number of jobs delayed and the average flow time.

Average flow time:

By comparing the average flow time, it is observed that SPT method gives the lowest average flow time.

Average tardiness:

By comparing the average tardiness, it is observed that EDD method gives the lowest average tardiness.

Number of jobs delayed:

Both FCFS and SPT have the lower number of the jobs delayed as compared to the EDD method.

Therefore, it depends on the owner which gives the priority to the most efficient method will vary.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Simplex Method  Three types of paints are manufactured in one machine; Interior paint, Exterior paint and Paint for metal structures. The preparation time for each type of paint is 2, 3 and 4 minutes respectively and the processing time is 3, 2 and 1 minute. The profit contributed by each product is 12, 10 and 15 dollars respectively. The machine availability is 100 minutes and 200 minutes for machine setup.  1. Determine the optimum number of types of paints to be manufactured. 2.      Determine the optimal utility value.
The company LED S.A DE C.V. produces 2 devices for lamps, devices 1 and 2 that require metal parts and electrical parts. The manager wants to determine how many units of each product should be manufactured to maximize the profit for each unit, device 1 requires 2 metal parts and 4 electrical parts, device 2 requires 4 metal parts and 2 electrical parts, the company has 24 units of each material available for batch production, device 1 generates $4 profit and device 2 generates $6 profit. a) Formulate PL model. b) Solve by the graphical method and determine what is the resulting maximum profit. Translated with DeepL.com (free version)
Question 3 i. Using the Center of Gravity method, determine the optimal location (X, Y) for the new distribution center. [7 marks] [TOTAL 25 MARKS] Time (sec.) Power steering assembly firm wants to set up an assembly line which must have an output of 60 units per hour. The work elements, task times and their precedence relationships are shown in Table 2: Table 1 Work Element Immediate Predecessor(s) A 30 NONE B 26 A C 50 A D 44 B E 10 с F 20 с G 15 D.E H 30 E,G,F Required: a. Draw the precedence diagram showing the task precedence and their times b. Determine the cycle time associated with the rate of output required. [3 marks] c. What is the theoretical number of work stations required to satisfy this output rate? [3 marks] [4 marks] d. Allocate the tasks to work stations taking into consideration the precedence requirements and using the LOT rule to break ties between feasible tasks. e. Calculate the total idle time [8 marks] [3 marks] f. What is the efficiency of the line and the…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY