Practical Operations Management
Practical Operations Management
2nd Edition
ISBN: 9781939297136
Author: Simpson
Publisher: HERCHER PUBLISHING,INCORPORATED
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 14, Problem 29P

(a)

Summary Introduction

Interpretation:

The time period required on an average to finish the job.

Concept Introduction:

Schedule the job on the basis of the FCFS . Then determine the average flow time for the each job. Calculate the average flow time that is required to finish the each job. Then calculate the average tardiness by adding the delay time of the order.

(a)

Expert Solution
Check Mark

Explanation of Solution

Given information:

The owner of an in HM Catering Company has four jobs to deliver today, shown in the order in which they are received:

    JobProcessing Time
    (hrs)
    Due (hrs)
    W45
    X39
    Y22
    Z11

Schedule the jobs based on the first come first served:

    Hours12345678910
    JobWXYZ

From the table, it is observed that the flow time of the job W is 4 hours which due in 5 hours. Thus, W has no delay in job.

The flow time of the job X is 7 hours which due in 9 hours. Thus, X has no delay in job.

The flow time of the job Y is 9 hours which due in 2 hours. Thus, X has 7 hours delay in job.

In order of the job Y :

The flow time of the job Z is 10 hours which due in 1 hour. Thus, it has a delay of 9 hours.

In order of the job Z :

Thus, calculate the average flow time that is required to finish the each job:

  4hours+7hours+9hours+10hours4=7.5hours

Now, calculating the average tardiness, adding the delay time of the order and divide it by the number of the orders;

  AT=0+0+7+94AT=4hours

(b)

Summary Introduction

Interpretation:

The job that will be late and the average job tardiness.

Concept Introduction:

Schedule the job on the basis of the SPT . Then determine the average flow time for the each job. Calculate the average flow time that is required to finish the each job. Then calculate the average tardiness by adding the delay time of the order.

(b)

Expert Solution
Check Mark

Explanation of Solution

Given information:

The owner of an in home meal catering company has four jobs to deliver today, shown in the order in which they are received:

    JobProcessing Time
    (hrs)
    Due (hrs)
    W45
    X39
    Y22
    Z11

Schedule the jobs based on the SPT ,

    Hours12345678910
    JobZYXW

From the table, it can be observed that Z has the 1 hour flow time which due in 1 hour. Z will be deliver on time.

  Y has the 3 hour flow time which due in 2 hour. Y will be delay 1 hour of the job.

  X has the 6 hour flow time which due in 9 hour. There will be no delay in order of the job X .

  W has the 10 hours flow time which due in 5 hours. Thus, there is delay of 5 hours on job order of W

Thus, calculate the average flow time that is required to finish the each job:

  1hours+3hours+6hours+10hours4=4hours

Now, calculating the average tardiness, adding the delay time of the order and divide it by the number of the orders;

  AT=0+1+0+54AT=1.5hours

(c)

Summary Introduction

Interpretation:

The job that will be late and the average job tardiness.

Concept Introduction:

Schedule the job on the basis of the EDD . Then determine the average flow time for the each job. Calculate the average flow time that is required to finish the each job. Then calculate the average tardiness by adding the delay time of the order.

(c)

Expert Solution
Check Mark

Explanation of Solution

Given information:

The owner of an in home meal catering company has four jobs to deliver today, shown in the order in which they are received:

    JobProcessing Time
    (hrs)
    Due (hrs)
    W45
    X39
    Y22
    Z11

Schedule the jobs based on the EDD ,

    Hours12345678910
    JobZYWX

From the table, it can be observed that Z has the 1 hour flow time which due in 1 hour. Z will be no delay.

  Y has the 3 hour flow time which due in 2 hour. Y will be delay 1 hour of the job.

  W has the 7 hour flow time which due in 5 hour. There will be delay of 2 hours for the job.

  X has the 10 hour flow time which due in 9 hours. There will be delay of 1 hour in order of the job X .

Now, calculating the tardiness, adding the delay time of the order and divide it by the number of the orders;

  AT=0+1+2+14AT=1hour

Thus, calculate the average flow time that is required to finish the each job:

  1hour+3hours+7hours+10hours4=5.25hours

(d)

Summary Introduction

Interpretation:

The most efficient sequence from the FCFS,SPT,EDD .

Concept Introduction:

The efficiency can be measured as the average tardiness or the number of jobs delayed and the average flow time.

(d)

Expert Solution
Check Mark

Explanation of Solution

Given information:

The owner of an in home meal catering company has four jobs to deliver today, shown in the order in which they are received:

    JobProcessing Time
    (hrs)
    Due (hrs)
    W45
    X39
    Y22
    Z11

The efficiency can be measured as the average tardiness or the number of jobs delayed and the average flow time.

Average flow time:

By comparing the average flow time, it is observed that SPT method gives the lowest average flow time.

Average tardiness:

By comparing the average tardiness, it is observed that EDD method gives the lowest average tardiness.

Number of jobs delayed:

Both FCFS and SPT have the lower number of the jobs delayed as compared to the EDD method.

Therefore, it depends on the owner which gives the priority to the most efficient method will vary.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Can you guys help me with this? Thank you! Here's the question: Compared to the CONSTRAINT model, how has the network changed? How do you plan to add contingency to your network? Please answer this thoroughly Here's the what-if scenario: Assume that the LA warehouse becomes temporarily or even indefinitely disabled since facing a large-scale labor disruption. Re-optimize the network considering this new constraint. Here's the scenario comparison analysis:  Scenario Constraint Scenario vs What-if Scenario Summary The Constraint Scenario exhibits a higher total cost of $7,424,575.45 compared to the What-if Scenario's total cost of $6,611,905.60, signifying a difference of approximately $812,669.85, which indicates a more expensive operation in the Constraint Scenario. The average service time is slightly higher in the Constraint Scenario (0.72 days vs. 0.70 days), suggesting that the What-if Scenario provides a marginally quicker service. Moreover, the average end-to-end service time…
Can you guys help me with this? Thank you! Here's the question: Compared to the CONSTRAINT model, how has the network changed? How do you plan to add contingency to your network? Please answer this throughly Here's the what-if scenario: Assume that Dallas plant has lost power. It cannot serve the DCs anymore and has to remain locked indefinitely. Re-optimize the network considering this new constraint. Here's the scenario comparison analysis:  Scenario Constraint Scenario vs What-if Scenario Summary In comparing the Constraint Scenario to the What-if Scenario, a few key differences highlight the efficiencies evident in the supply chain. Firstly, the total cost in the Constraint Scenario is lower at $7,424,575.45, while the What-if Scenario incurs a total cost of $7,486,369.12, resulting in a cost delta of $61,793.67. Additionally, although both scenarios exhibit the same average service time of 0.72 days, the What-if Scenario has a more favorable average end-to-end service time of 2.41…
Employee In-Service Training ASSIGNMENT: In-Service Training. The intern is required to plan and implement two in-service training sessions for employees. Each in-service should last at least 10 but not more than 30 minutes and should be given to all employees affected. The preceptor or supervisor/unit manager must approve all in-service topics. 1) One presentation should be related to a policy or procedure of any kind (e.g. proper use of equipment); 2) The second presentation must be related to sanitation or safety. For each in-service presentation, the intern must develop a written class plan and a visual aid (may be a handout, poster, PowerPoint slide presentation, etc.) appropriate to the life experiences, cultural diversity and educational background of the target audience. The intern must also measure behavior change. Note, this cannot be measured by a written pre- and post- test. That would be measuring knowledge. The intern mustactually observe and document that the learners…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY