Practical Operations Management
Practical Operations Management
2nd Edition
ISBN: 9781939297136
Author: Simpson
Publisher: HERCHER PUBLISHING,INCORPORATED
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 14, Problem 29P

(a)

Summary Introduction

Interpretation:

The time period required on an average to finish the job.

Concept Introduction:

Schedule the job on the basis of the FCFS . Then determine the average flow time for the each job. Calculate the average flow time that is required to finish the each job. Then calculate the average tardiness by adding the delay time of the order.

(a)

Expert Solution
Check Mark

Explanation of Solution

Given information:

The owner of an in HM Catering Company has four jobs to deliver today, shown in the order in which they are received:

    JobProcessing Time
    (hrs)
    Due (hrs)
    W45
    X39
    Y22
    Z11

Schedule the jobs based on the first come first served:

    Hours12345678910
    JobWXYZ

From the table, it is observed that the flow time of the job W is 4 hours which due in 5 hours. Thus, W has no delay in job.

The flow time of the job X is 7 hours which due in 9 hours. Thus, X has no delay in job.

The flow time of the job Y is 9 hours which due in 2 hours. Thus, X has 7 hours delay in job.

In order of the job Y :

The flow time of the job Z is 10 hours which due in 1 hour. Thus, it has a delay of 9 hours.

In order of the job Z :

Thus, calculate the average flow time that is required to finish the each job:

  4hours+7hours+9hours+10hours4=7.5hours

Now, calculating the average tardiness, adding the delay time of the order and divide it by the number of the orders;

  AT=0+0+7+94AT=4hours

(b)

Summary Introduction

Interpretation:

The job that will be late and the average job tardiness.

Concept Introduction:

Schedule the job on the basis of the SPT . Then determine the average flow time for the each job. Calculate the average flow time that is required to finish the each job. Then calculate the average tardiness by adding the delay time of the order.

(b)

Expert Solution
Check Mark

Explanation of Solution

Given information:

The owner of an in home meal catering company has four jobs to deliver today, shown in the order in which they are received:

    JobProcessing Time
    (hrs)
    Due (hrs)
    W45
    X39
    Y22
    Z11

Schedule the jobs based on the SPT ,

    Hours12345678910
    JobZYXW

From the table, it can be observed that Z has the 1 hour flow time which due in 1 hour. Z will be deliver on time.

  Y has the 3 hour flow time which due in 2 hour. Y will be delay 1 hour of the job.

  X has the 6 hour flow time which due in 9 hour. There will be no delay in order of the job X .

  W has the 10 hours flow time which due in 5 hours. Thus, there is delay of 5 hours on job order of W

Thus, calculate the average flow time that is required to finish the each job:

  1hours+3hours+6hours+10hours4=4hours

Now, calculating the average tardiness, adding the delay time of the order and divide it by the number of the orders;

  AT=0+1+0+54AT=1.5hours

(c)

Summary Introduction

Interpretation:

The job that will be late and the average job tardiness.

Concept Introduction:

Schedule the job on the basis of the EDD . Then determine the average flow time for the each job. Calculate the average flow time that is required to finish the each job. Then calculate the average tardiness by adding the delay time of the order.

(c)

Expert Solution
Check Mark

Explanation of Solution

Given information:

The owner of an in home meal catering company has four jobs to deliver today, shown in the order in which they are received:

    JobProcessing Time
    (hrs)
    Due (hrs)
    W45
    X39
    Y22
    Z11

Schedule the jobs based on the EDD ,

    Hours12345678910
    JobZYWX

From the table, it can be observed that Z has the 1 hour flow time which due in 1 hour. Z will be no delay.

  Y has the 3 hour flow time which due in 2 hour. Y will be delay 1 hour of the job.

  W has the 7 hour flow time which due in 5 hour. There will be delay of 2 hours for the job.

  X has the 10 hour flow time which due in 9 hours. There will be delay of 1 hour in order of the job X .

Now, calculating the tardiness, adding the delay time of the order and divide it by the number of the orders;

  AT=0+1+2+14AT=1hour

Thus, calculate the average flow time that is required to finish the each job:

  1hour+3hours+7hours+10hours4=5.25hours

(d)

Summary Introduction

Interpretation:

The most efficient sequence from the FCFS,SPT,EDD .

Concept Introduction:

The efficiency can be measured as the average tardiness or the number of jobs delayed and the average flow time.

(d)

Expert Solution
Check Mark

Explanation of Solution

Given information:

The owner of an in home meal catering company has four jobs to deliver today, shown in the order in which they are received:

    JobProcessing Time
    (hrs)
    Due (hrs)
    W45
    X39
    Y22
    Z11

The efficiency can be measured as the average tardiness or the number of jobs delayed and the average flow time.

Average flow time:

By comparing the average flow time, it is observed that SPT method gives the lowest average flow time.

Average tardiness:

By comparing the average tardiness, it is observed that EDD method gives the lowest average tardiness.

Number of jobs delayed:

Both FCFS and SPT have the lower number of the jobs delayed as compared to the EDD method.

Therefore, it depends on the owner which gives the priority to the most efficient method will vary.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The results of your four plans will provide an indicative EOQ value. State this value and discuss in a precise manner, why it is not the exact, true value.  Additional calculations in the form of plans E, F etc. may also assist your explanation of the EOQ and can be included
i). Complete the table assuming a Level production plan. ii) Comment on your results and explain whether at this stage, you consider a Level plan is a suitable approach for this particular business. Your comment should include reference to a calculated ‘fill rate’.
In the following sawtooth inventory profile diagram, two inventory plans with different order quantities (Q) and different frequencies of delivery are shown; order quantity for Plan A = 200 units and Plan B = 50 units. i). Total demand (D) is 350 units, the holding cost per unit (Ch) is equal to (£0.8) and the ordering cost per order (Co) is (£12.5). Calculate the total costs for each plan and state which one is more preferable along with the reason why.  ii). There is a stark difference in the composition of the total costs of Plans A and B. Explain this difference and why it occurs. Use the breakdown of costs for each plan to help illustrate your answer.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY