Textbook Question
Chapter 14, Problem 17QP
SML and WACC [LO1] An all-equity firm is considering the following projects:
Project | Beta | |
W | .75 | 8.9% |
X | .90 | 10.8 |
Y | 1.15 | 12.8 |
Z | 1.45 | 13.9 |
The T-bill rate is 4 percent, and the expected return on the market is 11 percent.
a. Which projects have a higher expected return than the firm’s 11 percent cost of capital?
b. Which projects should be accepted?
c. Which projects would be incorrectly accepted or rejected if the firm’s overall cost of capital were used as a hurdle rate?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
SML and WACC [LO1] An all-equity firm is considering the following projects:
Project
W
X
Y
Z
Beta
0.80
0.90
1.45
1.60
Expected Return
10%
12
13
15
The T-bill rate is 5 percent, and the expected return on the market is 11 percent.
a. Which projects have a higher expected return than the firm's 11 percent cost of
capital?
b. Which projects should be accepted?
c. Which projects would be incorrectly accepted or rejected if the firm's overall
cost of capital were used as a hurdle rate?
6. An all-equity firm is considering the following projects. The T-bill rate (risk-free rate) is 3.5 percent,
and the expected return on the market is 11 percent.
|Project
Beta
IRR
80
.95
9.4%
X
10.9%
13.0%
14.2%
Y
1.15
1.45
• Which projects have a higher expected return than the firm's 11 percent overall cost of capital?
• Which projects should be accepted according to the risk (beta) of the project?
• Which projects would be incorrectly accepted or rejected if the firm's overall cost of capital was used
as a hurdle rate?
An all-equity firm is considering the following projects:
Project Beta
IRR
W
.58
X
.87
Y
1.13
Z
1.47
9.0%
9.7
12.1
15.2
The T-bill rate is 4.2 percent and the expected return on the market is 11.2 percent.
a. Compared with the firm's 11.2 percent cost of capital, Project W has a
expected return, Project Y has a
expected return.
expected return, Project X has a
expected return, and Project Z has a
Chapter 14 Solutions
Fundamentals of Corporate Finance
Ch. 14.1 - What is the primary determinant of the cost of...Ch. 14.1 - What is the relationship between the required...Ch. 14.2 - What do we mean when we say that a corporations...Ch. 14.2 - Prob. 14.2BCQCh. 14.3 - Why is the coupon rate a bad estimate of a firms...Ch. 14.3 - How can the cost of debt be calculated?Ch. 14.3 - How can the cost of preferred stock be calculated?Ch. 14.4 - Prob. 14.4ACQCh. 14.4 - Prob. 14.4BCQCh. 14.4 - Under what conditions is it correct to use the...
Ch. 14.5 - Prob. 14.5ACQCh. 14.5 - Prob. 14.5BCQCh. 14.6 - Prob. 14.6ACQCh. 14.6 - Why do you think we might prefer to use a ratio...Ch. 14.7 - What are flotation costs?Ch. 14.7 - How are flotation costs included in an NPV...Ch. 14 - A firm has paid dividends of 1.02, 1.10, 1.25, and...Ch. 14 - Prob. 14.3CTFCh. 14 - Why is the tax rate applied to the cost of debt...Ch. 14 - What approach to a projects costs of capital...Ch. 14 - What is the flotation cost of equity for a firm...Ch. 14 - WACC [LO3] On the most basic level, if a firms...Ch. 14 - Book Values versus Market Values [LO3] In...Ch. 14 - Project Risk [LO5] If you can borrow all the money...Ch. 14 - Prob. 4CRCTCh. 14 - DCF Cost of Equity Estimation [LO1] What are the...Ch. 14 - SML Cost of Equity Estimation [LO1] What are the...Ch. 14 - Prob. 7CRCTCh. 14 - Cost of Capital [LO5] Suppose Tom OBedlam,...Ch. 14 - Company Risk versus Project Risk [LO5] Both Dow...Ch. 14 - Divisional Cost of Capital [LO5] Under what...Ch. 14 - Calculating Cost of Equity [LO1] The Absolute Zero...Ch. 14 - Calculating Cost of Equity [LO1] The Graber...Ch. 14 - Calculating Cost of Equity [LO1] Stock in Daenerys...Ch. 14 - Estimating the DCF Growth Rate [LO1] Suppose...Ch. 14 - Prob. 5QPCh. 14 - Calculating Cost of Debt [LO2] Drogo, Inc., is...Ch. 14 - Calculating Cost of Debt [LO2] Jiminys Cricket...Ch. 14 - Prob. 8QPCh. 14 - Calculating WACC [LO3] Mullineaux Corporation has...Ch. 14 - Taxes and WACC [LO3] Lannister Manufacturing has a...Ch. 14 - Finding the Target Capital Structure [LO3] Famas...Ch. 14 - Book Value versus Market Value [LO3] Dinklage...Ch. 14 - Calculating the WACC [LO3] In Problem 12, suppose...Ch. 14 - WACC [LO3] Fyre, Inc., has a target debtequity...Ch. 14 - Prob. 15QPCh. 14 - Prob. 16QPCh. 14 - SML and WACC [LO1] An all-equity firm is...Ch. 14 - Calculating Flotation Costs [LO4] Suppose your...Ch. 14 - Calculating Flotation Costs [LO4] Caughlin Company...Ch. 14 - WACC and NPV [LO3, 5] Scanlin, Inc., is...Ch. 14 - Flotation Costs [LO4] Pardon Me, Inc., recently...Ch. 14 - Calculating the Cost of Debt [LO2] Ying Import has...Ch. 14 - Calculating the Cost of Equity [LO1] Epley...Ch. 14 - Adjusted Cash Flow from Assets [LO3] Ward Corp. is...Ch. 14 - Adjusted Cash Flow from Assets [LO3] In the...Ch. 14 - Prob. 26QPCh. 14 - Prob. 27QPCh. 14 - Flotation Costs and NPV [LO3, 4] Photochronograph...Ch. 14 - Flotation Costs [LO4] Sheaves Corp. has a...Ch. 14 - Project Evaluation [LO3, 4] This is a...Ch. 14 - Prob. 31QPCh. 14 - Prob. 1MCh. 14 - Cost of Capital for Swan Motors You have recently...Ch. 14 - Prob. 3MCh. 14 - Cost of Capital for Swan Motors You have recently...Ch. 14 - Cost of Capital for Swan Motors You have recently...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.Similar questions
- An all-equity firm is considering the following projects: Project Beta IRR W .67 9.5 % X .74 10.6 Y 1.37 14.1 Z 1.48 17.1 The T-bill rate is 5.1 percent, and the expected return on the market is 12.1 percent. a. Which projects have a higher/lower expected return than the firm’s 12.1 percent cost of capital?arrow_forwardcan i have help solving this using Excel pls?arrow_forwardQ24arrow_forward
- 5. a. b. C. d. e. Suppose that two firms, A and B, are considering the same project which has the same risk as firm B's overall operations. The project has an IRR of 14.0%. Firm A has a beta of 1.4, while firm B's beta is 1.1. If the risk-free rate is 5.25% and the market risk premium is 7.0%, which firm(s) should take the project? A only B only Both A and B Neither A nor B Cannot be determined without additional informationarrow_forwardQ16arrow_forward8 GoldPure is considering the following independent, average-risk investment projects:Project Size of Project Project IRRProject V P1.0 million 12.0%Project W 1.2 million 11.5Project X 1.2 million 11.0Project Y 1.2 million 10.5Project Z 1.0 million 10.0The company has a target capital structure that consists of 50 percent debt and 50 percent equity. Its after-tax cost of debt is 8 percent, its cost of equity is estimated to be 16.5 percent, and its net income is P2.5 million. If the company follows a residual dividend policy, what will be its plowback ratio? Group of answer choices 0 54% 68% 100% 32% 12% 66%arrow_forward
- An all-equity firm is considering the projects shown below. The T-bill rate is 4 percent and the market risk premium is 7 percent. Project Expected Return A Project A Project B Project C Project D 8.0% 19.0 13.0 17.0 Calculate the project-specific benchmarks for each project. (Round your answers to 1 decimal place.) O Project C O Project D Beta 0.5 1.2 1.4 % % % % If the firm uses its current WACC of 12 percent to evaluate these projects, which project(s), will be incorrectly accepted? O Project A O Project Barrow_forward15.2arrow_forwardSolve fast thank uarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- EBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:9781337514835
Author:MOYER
Publisher:CENGAGE LEARNING - CONSIGNMENT
Financial leverage explained; Author: The Finance story teller;https://www.youtube.com/watch?v=GESzfA9odgE;License: Standard YouTube License, CC-BY