a)
To develop: A gross requirements plan for item C.
Introduction:
Gross requirements plan:
The gross requirements plan is the plan where the independent and dependent demands for a product or a component before the on-hand inventory and the
b)
To develop: A net requirements plan for item C.
Introduction:
Net requirements plan:
The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.
Trending nowThis is a popular solution!
Chapter 14 Solutions
Operations Management: Sustainability and Supply Chain Management (12th Edition)
- Define material requirements planning (MRP)arrow_forward4.11 Given the following product tree, complete the MRP records for parts X, Y, and Z. Note that parts X and Y have specified order quantities. Y(3) Z(1) W(1) Part X Week Gross Requirements Scheduled Receipts Lead Time: 1 week Projected Available Net Requirements Planned Order Receipt Planned Order Release Z(2) 1 2 3 4 5 20 225 15 5 15 10 15 10 Part Y Gross Requirements Scheduled Receipts 50 Lead Time: 2 weeks Projected Available 30 Net Requirements Lot Size: 50 Planned Order Receipt Planned Order Release Part J Gross Requirements Scheduled Receipts Lead Time: 1 week Projected Available Net Requirements Lot Size: lot-for-lot Planned Order Receipt Planned Order Release Part K Gross Requirements Scheduled Receipts Lead Time: 1 week Projected Available Lot Size: 400 Net Requirements Planned Order Receipt Planned Order Release 90arrow_forwardBuild a gross requirements planarrow_forward
- Help me to solve thisarrow_forwardDEVELOPING A PRODUCT STRUCTURE AND GROSS REQUIREMENTS Speaker Kits, Inc., packages high-fidelity components for mail order. Components for the top-of-the-line speaker kit, “Awesome” (A), include 2 Bs and 3 Cs. Each B consists of 2 Ds and 2 Es. Each of the Cs has 2 Fs and 2 Es. Each F includes 2 Ds and 1 G.It is an awesome sound system. (Most purchasers require hearing aids within 3 years, and at least onecourt case is pending because of structural damage to a men’s dormitory.) As we can see, the demand forB, C, D, E, F, and G is completely dependent on the master production schedule for A—the Awesomespeaker kits.arrow_forwardGiven the following information, develop a material requirements plan for end item A and its components. 50 and 80 units of A are needed at the beginning of week 6 and 8, respectively. On-Order Item A B с D E Item A BUDE C C(2) Week 3: 50 On-Hand 20 60 150 10 On-Hand 20 60 150 10 Week 3:30, Week 5:80 Week 3:50, Week 5:100 B Week 4: 50, Week 6: 100 Week 3: 50, Week 5: 80 D(3) The planned order release for Product B is: E 200 (Week 2) On-Order 200 (Week 2) A E D(3) Lead Time 1 wk 2 wks 1 wk 2 wks 1 wk Lead Time 1 wk 2 wks 1 wk 2 wks 1 wk C Order Size lot-for-lot 50 100 200 lot-for-lot Order Size lot-for-lot 50 100 200 lot-for-lot C Earrow_forward
- m1arrow_forwardOnce a material requirements plan (MRP) has been estab-lished, what other managerial applications might be found for the technique?arrow_forwardExplain the concept of a Requirements Management Plan (RMP) and its importance in guiding the management of requirements throughout a project.arrow_forward
- 1.arrow_forward6. Given the following product structure diagram, complete the MRP records for parts A, B, and C. с Part A Gross requirements Scheduled receipts Projected available balance Planned order releases Q=20; LT= 1; SS = 0. 21 1 5 B (2 required) с Week 4 5 6 12 22 2 3 15 18 8arrow_forwardQ3. Discuss Material and Capacity Requirements Planning and scope or function of Material Managementarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.