Question
Chapter 13, Problem 4P
Summary Introduction
To evaluate: Plan B
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Using the information in Problem 13.3, develop planB. Produce at a constant rate of 1,400 units per month, which will
meet minimum demands. Then use subcontracting, with addi-tional units at a premium price of $75 per unit. Evaluate this plan
by computing the costs for January through August.
Calculate Total Cost of Stockout
Lorie Nursery plans to sell 6,000 potted plants during
May, 5, 700 in June, and 6,000 during July. The
company keeps 10% of the next month's sales as
ending inventory. How many units should Lorie Nursery
produce during June?
Chapter 13 Solutions
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Ch. 13 - Make the case for, and then against, this pricing...Ch. 13 - Prob. 1DQCh. 13 - Why are SOP teams typically cross-functional?Ch. 13 - Prob. 3DQCh. 13 - Prob. 4DQCh. 13 - Prob. 5DQCh. 13 - Prob. 6DQCh. 13 - Prob. 7DQCh. 13 - Prob. 8DQCh. 13 - Prob. 9DQ
Ch. 13 - Prob. 10DQCh. 13 - Prob. 11DQCh. 13 - Prob. 12DQCh. 13 - Prob. 13DQCh. 13 - Prob. 14DQCh. 13 - Prob. 1PCh. 13 - Prob. 2PCh. 13 - The president of Hill Enterprises, Terri Hill,...Ch. 13 - Prob. 4PCh. 13 - Prob. 5PCh. 13 - Prob. 6PCh. 13 - Consuelo Chua, Inc., is a disk drive manufacturer...Ch. 13 - Prob. 8PCh. 13 - Prob. 9PCh. 13 - Prob. 10PCh. 13 - Prob. 11PCh. 13 - Southeast Soda Pop, Inc., has a new fruit drink...Ch. 13 - Ram Roys firm has developed the following supply,...Ch. 13 - Jerusalem Medical Ltd., an Israeli producer of...Ch. 13 - Prob. 15PCh. 13 - Prob. 16PCh. 13 - Prob. 17PCh. 13 - Prob. 18PCh. 13 - Dwayne Cole, owner of a Florida firm that...Ch. 13 - Prob. 24PCh. 13 - Prob. 25PCh. 13 - Prob. 26PCh. 13 - Evaluate the various configurations of operating...Ch. 13 - Prob. 2CSCh. 13 - After researching revenue (yield) management in...Ch. 13 - The Magic used its original pricing systems of...Ch. 13 - Prob. 3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Scenario 3 Ben Gibson, the purchasing manager at Coastal Products, was reviewing purchasing expenditures for packaging materials with Jeff Joyner. Ben was particularly disturbed about the amount spent on corrugated boxes purchased from Southeastern Corrugated. Ben said, I dont like the salesman from that company. He comes around here acting like he owns the place. He loves to tell us about his fancy car, house, and vacations. It seems to me he must be making too much money off of us! Jeff responded that he heard Southeastern Corrugated was going to ask for a price increase to cover the rising costs of raw material paper stock. Jeff further stated that Southeastern would probably ask for more than what was justified simply from rising paper stock costs. After the meeting, Ben decided he had heard enough. After all, he prided himself on being a results-oriented manager. There was no way he was going to allow that salesman to keep taking advantage of Coastal Products. Ben called Jeff and told him it was time to rebid the corrugated contract before Southeastern came in with a price increase request. Who did Jeff know that might be interested in the business? Jeff replied he had several companies in mind to include in the bidding process. These companies would surely come in at a lower price, partly because they used lower-grade boxes that would probably work well enough in Coastal Products process. Jeff also explained that these suppliers were not serious contenders for the business. Their purpose was to create competition with the bids. Ben told Jeff to make sure that Southeastern was well aware that these new suppliers were bidding on the contract. He also said to make sure the suppliers knew that price was going to be the determining factor in this quote, because he considered corrugated boxes to be a standard industry item. Is Ben Gibson acting legally? Is he acting ethically? Why or why not?arrow_forwardScenario 3 Ben Gibson, the purchasing manager at Coastal Products, was reviewing purchasing expenditures for packaging materials with Jeff Joyner. Ben was particularly disturbed about the amount spent on corrugated boxes purchased from Southeastern Corrugated. Ben said, I dont like the salesman from that company. He comes around here acting like he owns the place. He loves to tell us about his fancy car, house, and vacations. It seems to me he must be making too much money off of us! Jeff responded that he heard Southeastern Corrugated was going to ask for a price increase to cover the rising costs of raw material paper stock. Jeff further stated that Southeastern would probably ask for more than what was justified simply from rising paper stock costs. After the meeting, Ben decided he had heard enough. After all, he prided himself on being a results-oriented manager. There was no way he was going to allow that salesman to keep taking advantage of Coastal Products. Ben called Jeff and told him it was time to rebid the corrugated contract before Southeastern came in with a price increase request. Who did Jeff know that might be interested in the business? Jeff replied he had several companies in mind to include in the bidding process. These companies would surely come in at a lower price, partly because they used lower-grade boxes that would probably work well enough in Coastal Products process. Jeff also explained that these suppliers were not serious contenders for the business. Their purpose was to create competition with the bids. Ben told Jeff to make sure that Southeastern was well aware that these new suppliers were bidding on the contract. He also said to make sure the suppliers knew that price was going to be the determining factor in this quote, because he considered corrugated boxes to be a standard industry item. As the Marketing Manager for Southeastern Corrugated, what would you do upon receiving the request for quotation from Coastal Products?arrow_forwardTwo items are omitted from each of the following three lists of cost of goods sold data from a manufacturing company income statement. Determine the amounts of the missing items, identifying them by letter. Finished goods Inventory,June1 $61,600 $46,200 (e) Cost of goods manufactured 329,000 (c ) 484,800 Cost of finished goods available for sales (a) $260,400 $540,000 Finished goods Inventory ,June30 72,800 61,600 (f) Cost of goods sold (b) (d) $513,600arrow_forward
- A manager has prepared a forecast of expected aggregate demand for the next six months. Develop an aggregate plan to meet this demand given this additional information: A level production rate of 1000 units per month can be used. Backorders are allowed, and they are charged at the rate of $20 per unit per month. Inventory holding costs are $1 per unit per month in ending inventory. Determine the cost of this plan if regular time cost is $10 per unit and beginning inventory is zero. Overtime costs $16 per unit and subcontracting costs $20 per unit. In the 4th month, overtime is not possible. While outsourcing is not allowed in the 3rd month. Overtime capacity is 100 units and subcontracting capacity is 100 units per month. Month Forecast 1 800 2 960 3 1120 4 1440 5…arrow_forwardA manager has prepared a forecast of expected aggregate demand for the next six months. Develop an aggregate plan to meet this demand given this additional information: A level production rate of 500 units per month can be used. Backorders are allowed, and they are charged at the rate of $20 per unit per month. Inventory holding costs are $1 per unit per month in ending inventory. Determine the cost of this plan if regular time cost is $10 per unit and beginning inventory is zero. Overtime costs $16 per unit and subcontracting costs $20 per unit. In the 4th month, overtime is not possible. While outsourcing is not possible in the 3rd month. Overtime capacity is 50 units and subcontracting capacity is 50 units. Month Forecast 1 400 2 480 3 560 4 720 5…arrow_forwardOpertion Management No handwritten solution. Maitain quality and accuracy in your answerarrow_forward
- Can you assist me with Question 10. Please display the step process. Thank youarrow_forwardA company wants to develop a level production plan for a family of products. The opening inventory is 550 units, and a decrease to 200 units is expected by the end of the plan.The demand for each of the periods is given in what follows. All periods have the samenumber of working days. How much should the company produce each period? Whatwill be the ending inventories in each period? Do you see any problems with the plan?arrow_forwardDO NOT ROUND ANY NUMBERS FOR THIS. Assume you can produce a fractional number of units, hold a fractional number of units in inventory, and run backlogs that include fractional units. I suggest you use excel for this homework. Please answer 5 & 6arrow_forward
- The president'of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows January February 1,450 1,600 May 2,300 2,200 1,900 June March 1,700 1,700 July April August 1,300 Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is $60 per unit. Inventory holding cost is $20 per unit per month Ignore any idle-lime costs. Evaluate the foilowing plan This exercise contains only Plan E Plan E Keep the current workforce, which is producing 1,600 units per month, and subcontract to meet the rest of the demand Subcontract cost is $75 per unit. Plan E Production Subcontract Ending Inventory Month O December 1 January Demand (Units) (Units) 200 1,450 1,600 2 February 1,600 1,600 3 March 1,700 1,600 4 April 1,700 1,600 5 May 2,300 1,600 6 June 7 July 8 August 2,200 1,600 1,900 1,600 1,300 1,600 The total subcontracting cost = S (Enter your response as a…arrow_forwardThe president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: Month 0 December 1 January 2 February 3 March 4 April 5 May 6 June January February March April 7 July 8 August Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is $60 per unit. Inventory holding cost is $20 per unit per month. Ignore any idle-time costs. Evaluate the following plan. This exercise contains only Plan D. Plan D: Keep the current workforce stable at producing 1,600 units per month. In addition to the regular production, another 20% of the normal production units can be produced in overtime at an additional cost of $50 per unit. A warehouse now constrains the maximum allowable inventory on hand to 600 units or less. Note: Do not produce in overtime if production or inventory are adequate to cover demand. Demand 1,450 1,600 1,600 1,700 1,450 1,600 1,600…arrow_forwardI do not understand this. Please help me get the answer. Please provide the solution/computation.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY