Requirement of number of FTE staff in May through August.
Concept Introduction:
FTE is (Full time equivalent) is the number of hours a full time employee works in a stipulated time period. It shows an average hours for work.

Explanation of Solution
Variables used to calculate FTE staff are:
- Month
- Number of days in a month
- Average
forecast of a month - Percentage in product mix
Formula to be used are:
.
For the four-month time horizon, the mix percentages will remain the same as given.
Month | May | |||
Working days | 22 | |||
Total forecast | 750 | |||
Products | Product Mix (%) | No. of files | Hours per file | Hours |
1 | 22 | 165.00 | 3.60 | 594.00 |
2 | 17 | 127.50 | 2.00 | 255.00 |
3 | 13 | 97.50 | 1.70 | 165.75 |
4 | 12 | 90.00 | 5.50 | 495.00 |
5 | 10 | 75.00 | 4.00 | 300.00 |
6 | 9 | 67.50 | 3.00 | 202.50 |
7 | 7 | 52.50 | 2.00 | 105.00 |
8 | 5 | 37.50 | 2.00 | 75.00 |
9 | 3 | 22.50 | 1.50 | 33.75 |
10 | 2 | 15.00 | 4.00 | 60.00 |
Total | 100 | 750 | 2286 | |
Required # of workers | 15 |
Month | June | |||
Working days | 20 | |||
Total forecast | 825 | |||
Products | Product Mix (%) | No. of files | Hours per file | Hours |
1 | 22 | 181.50 | 3.60 | 653.40 |
2 | 17 | 140.25 | 2.00 | 280.50 |
3 | 13 | 107.25 | 1.70 | 182.33 |
4 | 12 | 99.00 | 5.50 | 544.50 |
5 | 10 | 82.50 | 4.00 | 330.00 |
6 | 9 | 74.25 | 3.00 | 222.75 |
7 | 7 | 57.75 | 2.00 | 115.50 |
8 | 5 | 41.25 | 2.00 | 82.50 |
9 | 3 | 24.75 | 1.50 | 37.13 |
10 | 2 | 16.50 | 4.00 | 66.00 |
Total | 100 | 825 | 2514.6 | |
Required # of workers | 18 |
Month | July | |||
Working days | 22 | |||
Total forecast | 900 | |||
Products | Product Mix (%) | No. of files | Hours per file | Hours |
1 | 22 | 198.00 | 3.60 | 712.80 |
2 | 17 | 153.00 | 2.00 | 306.00 |
3 | 13 | 117.00 | 1.70 | 198.90 |
4 | 12 | 108.00 | 5.50 | 594.00 |
5 | 10 | 90.00 | 4.00 | 360.00 |
6 | 9 | 81.00 | 3.00 | 243.00 |
7 | 7 | 63.00 | 2.00 | 126.00 |
8 | 5 | 45.00 | 2.00 | 90.00 |
9 | 3 | 27.00 | 1.50 | 40.50 |
10 | 2 | 18.00 | 4.00 | 72.00 |
Total | 100 | 900 | 2743.2 | |
Required # of workers | 18 |
Month | July | |||
Working days | 22 | |||
Total forecast | 775 | |||
Products | Product Mix (%) | No. of files | Hours per file | Hours |
1 | 22 | 170.50 | 3.60 | 613.80 |
2 | 17 | 131.75 | 2.00 | 263.50 |
3 | 13 | 100.75 | 1.70 | 171.28 |
4 | 12 | 93.00 | 5.50 | 511.50 |
5 | 10 | 77.50 | 4.00 | 310.00 |
6 | 9 | 69.75 | 3.00 | 209.25 |
7 | 7 | 54.25 | 2.00 | 108.50 |
8 | 5 | 38.75 | 2.00 | 77.50 |
9 | 3 | 23.25 | 1.50 | 34.88 |
10 | 2 | 15.50 | 4.00 | 62.00 |
Total | 100 | 775 | 2362.2 | |
Required # of workers | 16 |
In summary, the FTEs required can be written in the following table:
Month | FTE |
May | 15 |
Jun | 18 |
Jul | 18 |
Aug | 16 |
Want to see more full solutions like this?
Chapter 13 Solutions
OM (with OM Online, 1 term (6 months) Printed Access Card)
- Imagine you are Susan Kim and are faced with a difficult choice to either follow the orders she was given, or refusing to do so. Using each lens determine what the ethical response would be. Suppot your answer with materials from readings and lectures. For example, using Universalism what would the ethical response be? Do the same for all four lenses.arrow_forwardAnswer all these questions, selecting any company of your choice. Choose a specific type of food company. Select a specific product. Develop all the inputs that are part of the process. Develop the transformation process in a graphic (diagram, etc.). Develop all the outputs or finished products that are part of the process. Describe all the processes involved in one line of production in any manufacturing facility. Also describing how good management is the center of any part of a production company.arrow_forwardUsing exponential smoothing with α =0.2, forecast the demand for The initial forecast for January is 2000 tons. Calculate the capacity utilization for June, July and Discuss the implications of underutilized or over utilized capacity for Green Harvestarrow_forward
- In organizational development when results are improving but relationships are declining, what leadership style is appropriate? directing delegating supporting coachingarrow_forwardWhat is the first thing a leader should do when moving through a cultural change? conduct an assessment comparing the practices to other high-performing organizations learn about the current organizational culture continue to monitor key metrics define expectationsarrow_forwardThe third change leadership strategy, Collaborate on Implementation, is designed to address what type of concerns? impact concerns personal concerns refinement concerns collaboration concernsarrow_forward
- If team members are concerned with specifics such as their tasks, contingency plans, resources, and timeline, what concerns do they have? implementation concerns impact concerns refinement concerns personal concernsarrow_forwardAt the developing stage of organizational development, which leadership style is most appropriate? supporting coaching delegating directingarrow_forwardDuring the start-up phase of organizations, which leadership style is appropriate? supporting coaching directing delegatingarrow_forward
- Regarding relationships and results, what is typically seen in start-up orgnanizations? low results/high relationships low results/low relationships high results/high relationships high results/ low relationshipsarrow_forwardWhat issues lie within Employee and Labor relations with hours worked and how to solve the issues effectively.arrow_forwardName the key stakeholders in the case. Consider the stakeholder map in the lecture material. Which stakeholders would be the most important under your default lens?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning