Concept explainers
UPD Manufacturing produces a range of health care appliances for hospital as well as for home use. The company has experienced a steady demand for its products, which are highly regarded in the health care field. Recently the company has undertaken a review of its inventory ordering procedures as part of a larger effort to reduce costs.
One of the company's products is a blood pressure testing kit. UPD manufactures all of the components for the kit in house except for the digital display unit. The display units are ordered at six-week intervals from the supplier. This ordering system began about five years ago, because the supplier insisted on it. However, that supplier was bought out by another supplier about a year ago, and the six-week ordering requirement is no longer in place. Nonetheless, UPD has continued to use the six-week ordering policy. According to purchasing manager Tom Chambers, "Unless somebody can give me a reason for changing, I'm going to stick with what we've been doing. I don't have time to reinvent the wheel."
Further discussions with Tom revealed a cost of $32 to order and receive a shipment of display units from the supplier. The company assembles 89 kits a week. Also, information from Sara James, in Accounting, indicated a weekly carrying cost of $.08 for each display unit.
The supplier has been quite reliable with deliveries; orders are received five working days after they are faxed to the supplier. Tom indicated that as far as he was concerned, lead-time variability is virtually nonexistent.
Would using an order interval other than every six weeks reduce costs? If so, what order interval would be best, and what order size would that involve?
Want to see the full answer?
Check out a sample textbook solutionChapter 13 Solutions
Operations Management
- Scenario 3 Ben Gibson, the purchasing manager at Coastal Products, was reviewing purchasing expenditures for packaging materials with Jeff Joyner. Ben was particularly disturbed about the amount spent on corrugated boxes purchased from Southeastern Corrugated. Ben said, I dont like the salesman from that company. He comes around here acting like he owns the place. He loves to tell us about his fancy car, house, and vacations. It seems to me he must be making too much money off of us! Jeff responded that he heard Southeastern Corrugated was going to ask for a price increase to cover the rising costs of raw material paper stock. Jeff further stated that Southeastern would probably ask for more than what was justified simply from rising paper stock costs. After the meeting, Ben decided he had heard enough. After all, he prided himself on being a results-oriented manager. There was no way he was going to allow that salesman to keep taking advantage of Coastal Products. Ben called Jeff and told him it was time to rebid the corrugated contract before Southeastern came in with a price increase request. Who did Jeff know that might be interested in the business? Jeff replied he had several companies in mind to include in the bidding process. These companies would surely come in at a lower price, partly because they used lower-grade boxes that would probably work well enough in Coastal Products process. Jeff also explained that these suppliers were not serious contenders for the business. Their purpose was to create competition with the bids. Ben told Jeff to make sure that Southeastern was well aware that these new suppliers were bidding on the contract. He also said to make sure the suppliers knew that price was going to be the determining factor in this quote, because he considered corrugated boxes to be a standard industry item. As the Marketing Manager for Southeastern Corrugated, what would you do upon receiving the request for quotation from Coastal Products?arrow_forwardMpho is an avid seamstress and want to sew and sell high quality, reusable, designer face masks during the current Covid-19 pandemic. She will design and sew the masks herself and use her automatic embroidery machine to put her logo on each mask sold. With the help of her son, deliveries will be made all over Gauteng within 3 days of placing the order. Every mask will have a unique three-layer design with adjustable straps to ensure comfort and fit. Mpho’s only expense is the material needed to sew the masks and delivery costs. At this stage, Mpho’s target market is limited to Gauteng. Question: Create a diagram to illustrate the transformation process of Mpho’s new business. Be sure to include all relevant elements, headings and arrows to indicate the flowof products/ services. What should be in the diagram: outputs, inputs, feedback, transformation process and flow of product and service ect.arrow_forwardX1= 29000 X2= 5 I need a clear step by step answer please :)arrow_forward
- managment information systemarrow_forwardUPO Manufacturing produces a range of health care appliances for hospital as well as for home use. The company has expenenced a steady demand for as products. which are highly regarded in the health care I &id. Recently the company has undertaken a review of as memory ordering procedures as pan of a larger effort to reduce costs. One of the company's products is a blood pressure testing kit. UPD manufactures all of the components for the kit in-house except for the digital display unit The display units are ordered at six-week intervals from the supplier. This ordering system began about five years ago. because the supplier insisted on it. However, that supplier was bought out by another supplier about a year ago. and the six-week ordering requirement is no longer in place. None-theless. UPO has continued to use the six- week ordering policy. According to purchasing manager Tom Chambers. "Unless some body can give me a reason for changing. I'm going to stick with what we've been…arrow_forwardInventory Management You are the store manager at a local branch of DigiLife, a large electronics retail chain. A new version of a popular consumer electronics device called the Amulet is coming out this year. It is your job to sell as many Amulets as you can while minimizing your costs in order to maximize your store's profits. Your Goal Earn $1,000,000 in net profits of Amulet sales.arrow_forward
- A major automobile manufacturer located in Georgetown, Kentucky, has two certified vendors that produce brake pads with the information shown below. New Albany Manufacturing is located in Columbus, Ohio, and LaPlaya Manufacturing is located in Monterrey, Mexico. The automobile assembly factory is assumed to operate 250 days per year. CertifiedSupplier OrderSize (Q) Price per Unit (P) OversightCostper Unit (O) TransportCost perUnit (Ct) Order Cost(Co) Cost to StoreOne UnitOne Year (Ch) Order LeadTime inDays (L) New Albany Mfg. 59,000 $11.74 $0.00 $0.37 $255 $1.70 51 LaPlaya Mfg. 118,000 $11.08 $0.42 $0.87 $290 $1.35 99 Use the Total Supply Chain Cost Excel template to compute the supply chain costs associated with each supplier if the annual demand is 1,180,000 brake pads. Do not round intermediate calculations. Round your answer to the nearest dollar. Order quantity: 59,000 units 118,000 units Total procurement cost: $ $ Total management oversight…arrow_forwardMpho is an avid seamstress and want to sew and sell high quality, reusable designer face masks during the current Covid-19 pandemic. She will design and sew the masks herself and use her automatic embroidery machine to put her logo on each mask sold. With the help of her son, deliveries will be made all over Gauteng within 3 days of placing the order. Every mask will have a unique three-layer design with adjustable straps to ensure comfort and it. Mpho’s only expenseis the material needed to sew the masks and delivery costs. At this stage, Mpho’starget market is limited to Gauteng. Draw a diagram to illustrate the transformation process of Mpho’s new business. Be sure to include all relevant elements, headings and arrows to indicate the flow of products/ services. Question: 1. Draw a diagram to illustrate the transformation process of Mpho’s new business. Be sure to include all relevant elements, headings and arrows to indicate the flow of products/ services.arrow_forwardGreen Gardens' owner has asked your advice about a possible problem at his business. Over the last 6 months the large-sized lawn and garden inventory (ie, tables, chairs, planters, etc.) has appeared to be short. The inventory records that employees use to determine what is on hand show that more inventory is available than can actually be located. This has cause frustration and mis-trust in the inventory records for the sales employees. The owner realizes that the problem is bigger than just frustrated employees. He is afraid that inventory is being stolen, a problem he didn't think possible given that these are large items that are not easily moved. Requirements: Provide the owner with two internal controls that he could implement to reduce the likelihood of theft of the lawn and garden inventory.arrow_forward
- Sitka Industries uses a cost system that carries direct materials inventory at a standard cost. The controller has established these standards for one ladder (unit): StandardQuantity x StandardPrice = StandardCost Direct materials 3 pounds $4.50 per pound $13.50 Direct labor 2.00 hours 12.00 per hour 24.00 Total cost $37.50 Sitka Industries made 2,900 ladders in July and used 8,500 pounds of material to make these units. Sitka Industries bought 15,400 pounds of material in the current period. There was a $300 unfavorable direct materials price variance. Enter all amounts as positive numbers. A. How much in total did Sitka pay for the 15,400 pounds? B. What is the direct materials quantity variance? C. What is the total direct materials cost variance? D. What if 9,200 pounds were used to make these ladders, what would be the direct materials quantity variance? E. If there was a $340 favorable direct materials price variance, how much did Sitka pay…arrow_forward9. XYZ has developed the following data from its Material A Safety stock Average (normally) daily use Maximum daily use Minimum daily use ЕOQ Cost of placing an order Working days per year 280 200 240 180 1,000 P20 250 days Lead time 6 days What is the cost of carrying an inventory per unit per year? 10. XYZ has developed the following data from its Material A Safety stock Average (normally) daily use Maximum daily use Minimum daily use EOQ Cost of placing an order Working days per year 280 200 240 180 1,000 P20 250 days Lead time 6 days What is the average inventory?arrow_forwardX1= 29000 X2=5 I need a step by step answer please :)arrow_forward