EP PRIN.OF OPERATIONS MGMT.-MYOMLAB
EP PRIN.OF OPERATIONS MGMT.-MYOMLAB
10th Edition
ISBN: 9780134183848
Author: HEIZER
Publisher: PEARSON CO
bartleby

Concept explainers

Question
Book Icon
Chapter 13, Problem 10P

a)

Summary Introduction

To evaluate: Plan C for the given information

Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.

b)

Summary Introduction

To determine: Evaluate plan D for the given information

Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.

Blurred answer
Students have asked these similar questions
The planner at a company that makes garden tractors is about to prepare an aggregate production plan that will cover the next 6 months. She has collected the following information: Month Demand Forecast Above the available capacity through permanent workforce 1 1,000 2 1,000 3 2,000 4 3,000 5 4,000 6 1,000 Total: 12,000 Production per month = 20 units per worker Initial inventory = 500 units Desired ending inventory (at the end of month 6) = 0 units Cost:               Hire cost = $500 per temporary worker               Inventory = $10 per tractor per month               Backorder = $150 per tractor per month The optimum aggregate plan is: Month 1 2 3 4 5 6 Total Forecast Demand above regular capacity 1,000 1,000 2,000 3,000 4,000 1,000 12,000 # of temporary workers required 50 50 100 150 200 50   Temp. Workers hired 25 25 50 75 0 0   Temp. workers laid off 0…
Jose Martinez of El Paso had developed a polished stainless-steel tortilla machine that makes it a “showpiece” for display in Mexican restaurants.  He needs to develop a 5-month aggregate plan.  His forecast of capacity and demand follows:   Month   1 2 3 4 5 Demand 150 160 130 200 210 Regular capacity 150 150 150 150 150 Overtime capacity 20 20 10 10 10 Subcontracting: 100 units available over the 5-month period (NOT 100 units each month) Beginning inventory: 0 units Ending inventory required at the last month (i.e. month 5): 20 units. Costs   Regular-time cost per unit $100 Overtime cost per unit $125 Subcontracting cost per unit $135 Inventory holding cost per unit per month $3 Assume that backorders are not permitted. a) Find an aggregate production plan using the intuitive lowest cost approach. (i.e. Develop an aggregate plan using the transportation method). b) State the corresponding…
3) AGGREGATE PLANNING Mark Tuan, Operations Manager at GOT7 Furniture, has received the following estimates of demand requirements: January 1,100 February 1,200 March 1,400 April 1,800 May 1,800 June 1,600 Assuming stockout costs for lost sales of RM100 per unit, inventory carrying costs of RM25 per unit per month, and a zero beginning and ending inventory. Analyze the extra cost if the company vary the workforce, which performs at a current production level of 1,300 units per month. The cost of hiring additional workers is RM3,000 per 100 units produced. The cost of layoffs is RM6,000 per 100 units cut back.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing