Concept explainers
A table is assembled using three components, as shown in the accompanying product structure tree. The company that makes the table wants to ship 100 units at the beginning of day 4, 150 units at the beginning of day 5, and 200 units at the beginning of day 7. Receipts of 100 wood sections are
Want to see the full answer?
Check out a sample textbook solutionChapter 12 Solutions
Operations Management
Additional Business Textbook Solutions
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Operations Management: Processes and Supply Chains (11th Edition)
Principles Of Operations Management
- 2)The castings need to be started in week ? (enter your response as a whole number).arrow_forwardAssume that you are the manager of Assembly, Inc. You have just received an order for 25 units of an industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine how many units of subassembly G to order and the timing of those orders, given that subassembly G must be ordered in multiples of 80 units and all other components are ordered lot-for-lot. Assume that the components are used only for this particular robot. Item Lead Time (weeks) On Hand Components Robot 2 10 B, G, C(3) B 1 5 E, F C 1 20 G(2), H E 2 4 — F 3 8 — G 2 15 — H 1 10 — Subassembly G order quantity (in units) Subassembly G should start at beginning of Week (Click to select) 1 2 3 4arrow_forwardAssume that you are the manager of Assembly, Inc. You have just received an order for 26 units of an industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine how many units of subassembly G to order and the timing of those orders, given that subassembly G must be ordered in multiples of 80 units and all other components are ordered lot-for-lot. Assume that the components are used only for this particular robot. Item Lead Time (weeks) On Hand Components Robot 2 10 B, G, C(3) B 1 5 E, F C 1 20 G(2), H E 2 4 — F 3 8 — G 2 15 — H 1 10 — Subassembly G order quantity (in units) Subassembly G should start at beginning of Weekarrow_forward
- One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; items A, B, E, and F have two-week lead times; and item D has a lead time of three weeks. Lot-for-lot (L4L) lot sizing is used for items C, E, and F; lots of size 20, 40, and 160 are used for items A, B, and D, respectively. Items A, B, D, and E have on-hand (beginning) inventories of 5, 10, 100, and 100, respectively; all other items have zero beginning inventories. We are scheduled to receive 10 units of A in week 3, 20 units of B in week 7, 40 units of F in week 5, and 60 units of E in week 2; there are no other scheduled receipts. If 20 units of A are required in week 10, use the low-level-coded bill-of-materials (product structure tree) to find thenecessary planned order releases for all components.arrow_forwardOne unit of A is made of two units of B and one unit of C. B is made of three units of Dand one unit of F. C is composed of three units of B, one unit of D, and four units of E.D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F havetwo-week lead times; and Item D has a lead time of three weeks. Lot-for-lot (L4L) lot sizingis used for Items C, E, and F; lots of size 20, 40, and 160 are used for Items A, B, andD, respectively. Items A, B, D, and E have on-hand (beginning) inventories of 5, 10, 100,and 100, respectively; all other items have zero beginning inventories. We are scheduledto receive 10 units of A in Week 3, 20 units of B in Week 7, 40 units of F in Week 5, and60 units of E in Week 2; there are no other scheduled receipts. If 20 units of A are requiredin Week 10, use the low-level-coded bill-of-materials (product structure tree) to i nd thenecessary planned order releases for all components.arrow_forwardThe assembly department started the month with 468,000 units in its beginning work in process inventory. An additional 1,524,000 units were transferred in from the prior department during the month to begin processing in the Assembly Department. There were 126,000 units in the ending work in process inventory of the Assembly Department. How many units were transferred to the next processing department during the month? a. 1,992,000 b. 1,992,000 c. 2,118,000 d. 1,866,000 e. 1,398,000 f. 1,182,000arrow_forward
- One unit of A is composed of two units of B and three units of C. Each B is composed of one unit of F. C is made of one unit of D, one unit of E, and two units of F. Items A, B, C, and D have 20, 50, 60, and 25 units of on-hand inventory, respectively. Items A, B, and C use lot-for-lot (L4L) as their lot-sizing technique, while D, E, and F require multiples of 50, 100, and 100, respectively, to be purchased. B has scheduled receipts of 30 units inperiod 1. No other scheduled receipts exist. Lead times are one period for items A, B, and D, and two periods for items C, E, and F. Gross requirements for A are 20 units in period 1, 20 units in period 2, 60 units in period 6, and 50 units in period 8. Find the planned order releases for all items.arrow_forwardA product (A) consists of a base (B) and a casting (C). The base consists of a plate(P) and three fasteners (F). The lead time, current on-hand inventory and scheduledreceipts are given in the table below. All components are lot for lot. The MasterSchedule requires 100 units of product A be available in week 4 and 150 in week 6. Part Lead time On - Hand inventory Scheduled receipts A 1 20 None B 1 100 50 in Week 1 C 3 30 20 in Week 1, 30 in Week 2 P 2 0 50 in Week 1 F 3 0 30 in Week 1, 40 in Week 3 Required:A. Draw the product structure tree. B. Develop the MRP for Parts A, B, C, P, and F in order to meet the demand. Therows for MRP tables are Gross Requirement (GR), Scheduled Receipt (SR),On-Hand Inventory (OHI), Net Requirement (NR), and Planned Production (PP).arrow_forwardOne unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of three weeks. Lot-for-lot (L4L) lot sizing is used for Items A, D, and E; lots of size 50, 100, and 50 are used for Items B, C, and F, respectively. Items A, C, D, and E have on-hand (beginning) inventories of 15, 55, 100, and 10, respectively; all other items have zero beginning inventory. We are scheduled to receive 10 units of A in Week 1, 100 units of C in Week 1, and 100 units of D in Week 3; there are no other scheduled receipts.If 50 units of A are required in week 10, use the low-level-coded bill-of-materials (product structure tree) to find the necessary planned-order releases for all components. (Leave the cells blank, whenever zero (0) is required.)arrow_forward
- One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; items A, B, E, and F have two-week lead times; and item D has a lead time of three weeks. Lot-for-lot (L4L) lot sizing is used for items A, D, and E; lots of sizes 50, 100, and 50 are used for items B, C, and F, respectively. Items A, C, D, and E have on-hand (beginning) inventories of 20, 50, 100, and 10, respectively; all other items have zero beginning inventory. We are scheduled to receive 10 units of A in week 1, 100 units of C in week 1, and 100 units of D in week 3; there are no other scheduled receipts. If 50 units of A are required in week 10, use the low-level-coded bill-of-materials (product structure tree) to find the necessary planned-order releases for all components.arrow_forwardEach unit of A is composed of one unit of B, two units of C, and one unit of D. C is composed of two units of D and three units of E. Items A, C, D, and E have on-hand inventories of 20, 10, 20, and 10 units, respectively. Item B has a scheduled receipt of 10 units in Period 1, and C has a scheduled receipt of 50 units in Period 1. Lot-for-lot (L4L) lot sizing is used for Items A and B. Item C requires a minimum lot size of 50 units. D and E are required to be purchased in multiples of 100 and 50, respectively. Lead times are one period for Items A, B, and C, and two periods for Items D and E. The gross requirements for A are 30 in Period 2, 30 in Period 5, and 40 in Period 8. Find the planned-order releases for all itemsarrow_forwardOne unit of Part C is used in item A and in item B. Currently, we have 10 As, 20 Bs, and 100 Cs in inventory. We want to ship 60 As and 70 Bs. How many additional Cs do we need to purchase?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,