Operations Management
Operations Management
13th Edition
ISBN: 9781259667473
Author: William J Stevenson
Publisher: McGraw-Hill Education
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 12, Problem 5P

a. One hundred twenty units of end item Z are needed at the beginning of week 7. Prepare a material requirements plan for component C. Take into account that on hand there are 40 units of Z, 70 units of A, 100 units of B, and 30 units of C. Also, there is a scheduled receipt of 20 units of component C in week 4. Lead times are two weeks for Z and B, and one week for the other components. Lot-for-lot ordering will be used for all items.

Chapter 12, Problem 5P, a. One hundred twenty units of end item Z are needed at the beginning of week 7. Prepare a material , example  1

b. Ninety-five units of end item E are needed at the beginning of week 7. Prepare a material requirements plan for component D. Take into account that 5 units of E are currently on hand, as well as 50 units of B, 100 units of C, and 80 units of D. Also, 30 units of C have been outsourced and are expected to arrive in week 4. Lead times are two weeks for E and C. and one week for the other components. Assume lot-for-lot ordering except for D. where multiples of 40 must be used.

Chapter 12, Problem 5P, a. One hundred twenty units of end item Z are needed at the beginning of week 7. Prepare a material , example  2

a)

Expert Solution
Check Mark
Summary Introduction

To prepare: A material requirements plan for Component C.

Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item)

Explanation of Solution

Given information:

120 units of end item (Z) are required at the beginning of Week 7. It is given that 40 units of Component Z, 100 units of Component B, 70 units of Component A, and 30 units of Component C are available on hand. Scheduled receipt is 20 units of Component C in Week 4. Lead-time is given as 2 weeks for Component Z and Component B and 1 week for other components. Lot size is lot-for-lot.

In addition to the above information, the following diagram is given:

Operations Management, Chapter 12, Problem 5P , additional homework tip  1

Prepare a Material Requirement Plan (MRP) for Component Z:

Operations Management, Chapter 12, Problem 5P , additional homework tip  2

  • Gross requirement is given as 120 units at the beginning of Week 7.
  • On-hand inventory is 40 units. It remains same until Week 6, as there is no demand.
  • Net requirement can be calculated by subtracting the projected on hand inventory of previous week from the gross requirement of current week.

Net requirement=Gross requirementOn-hand units of previous week=12040=80

  • 80 units are required at the beginning of Week 7. Hence, they need to order for 80 units (as the lot size is lot-for-lot) before two weeks (as the lead-time is 2 weeks), which means on Week 5.
  • Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.

Projected on-hand=(Projected on-hand of Week 6+Planned order receipt of Week 6Gross requirement of Week 6)+Scheduled receipt of current week=(40+00)+0=40

Prepare a Material Requirement Plan (MRP) for Component A (2):

Operations Management, Chapter 12, Problem 5P , additional homework tip  3

  • Component Z is the parent item of Component A (2). As the number of Component A is 2, the planned order release should be multiplied with 2 to determine the gross requirement of Component A.
  • On-hand inventory is 70 units. It remains same until Week 4, as there is no demand.
  • Net requirement can be calculated by subtracting the projected on hand inventory of previous week from the gross requirement of current week.

Net requirement=Gross requirementOn-hand units of previous week=16070=90

  • 90 units are required at the beginning of Week 5. Hence, they need to order for 90 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 weeks), which means on Week 4.
  • Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.

Projected on-hand on Week 6}=(Projected on-hand of Week 5+Planned order receipt of Week 5Gross requirement of Week 5)+Scheduled receipt of current week=(70+90160)+0=0

Prepare a Material Requirement Plan (MRP) for Component B (4):

Operations Management, Chapter 12, Problem 5P , additional homework tip  4

  • Component Z is the parent item of Component B (4). As the number of Component B is 4, the planned order release should be multiplied with 4 to determine the gross requirement of Component B.
  • On-hand inventory is 100 units. It remains same until Week 4, as there is no demand.
  • Net requirement can be calculated by subtracting the projected on hand inventory of previous week from the gross requirement of current week.

Net requirement=Gross requirementOn-hand units of previous week=320100=220

  • 220 units are required at the beginning of Week 5. Hence, they need to order for 220 units (as the lot size is lot-for-lot) on two weeks before (as the lead-time is 2 weeks), which means on Week 3.
  • Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.

Projected on-hand on Week 6}=(Projected on-hand of Week 5+Planned order receipt of Week 5Gross requirement of Week 5)+Scheduled receipt of current week=(100+220320)+0=0

Prepare a Material Requirement Plan (MRP) for Component C (3) and C (2):

Operations Management, Chapter 12, Problem 5P , additional homework tip  5

  • Component A (2) is the parent item of Component C (3) and Component B (4) is the parent item of Component C (2). As the number of Component C is 3, the planned order release of Component A should be multiplied with 3 to determine the gross requirement of Component C. The same should be followed for Component C (2) with its parent item B (4).
  • On-hand inventory is 30 units. It remains same until Week 3, as there is no demand.
  • Net requirement can be calculated by subtracting the projected on hand inventory of previous week from the gross requirement of current week.

Net requirement=Gross requirementOn-hand units of previous week=44030=410

  • 410 units are required at the beginning of Week 3. Hence, they need to order for 410 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week), which means on Week 2.
  • Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.

Projected on-hand on Week 4}=(Projected on-hand of Week 3+Planned order receipt of Week 3Gross requirement of Week 3)+Scheduled receipt of current week=(30+410440)+20=20

  • Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.

Projected on-hand on Week 5}=(Projected on-hand of Week 4+Planned order receipt of Week 4Gross requirement of Week 4)+Scheduled receipt of current week=(20+250270)+0=0

b)

Expert Solution
Check Mark
Summary Introduction

To prepare: A material requirements plan for Component D.

Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item)

Explanation of Solution

Given information:

95 units of end item (E) are required at the beginning of Week 7. It is given that 5 units of Component E, 50 units of Component B, 80 units of Component D, and 100 units of Component C are available on hand. Scheduled receipt is 30 units of Component C in Week 4. Lead-time is given as 2 weeks for Component E and Component C and 1 week for other components. Lot size is lot-for-lot for all the components except Component D. Lot size for Component C is multiples of 40.

In addition to the above information, the following diagram is given:

Operations Management, Chapter 12, Problem 5P , additional homework tip  6

Prepare a Material Requirement Plan (MRP) for Component E:

Operations Management, Chapter 12, Problem 5P , additional homework tip  7

  • Gross requirement is given as 95 units at the beginning of Week 7.
  • On-hand inventory is 5 units. It remains same until Week 6, as there is no demand.
  • Net requirement can be calculated by subtracting the projected on hand inventory of previous week from the gross requirement of current week.

Net requirement=Gross requirementOn-hand units of previous week=955=90

  • 90 units are required at the beginning of Week 7. Hence, they need to order for 90 units (as the lot size is lot-for-lot) before two weeks (as the lead-time is 2 weeks), which means on Week 5.
  • Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.

Projected on-hand=(Projected on-hand of Week 6+Planned order receipt of Week 6Gross requirement of Week 6)+Scheduled receipt of current week=(5+00)+0=5

Prepare a Material Requirement Plan (MRP) for Component B (3):

Operations Management, Chapter 12, Problem 5P , additional homework tip  8

  • Component E is the parent item of Component B (3). As the number of Component B is 3, the planned order release should be multiplied with 3 to determine the gross requirement of Component 3.
  • On-hand inventory is 50 units. It remains same until Week 4, as there is no demand.
  • Net requirement can be calculated by subtracting the projected on hand inventory of previous week from the gross requirement of current week.

Net requirement=Gross requirementOn-hand units of previous week=27050=220

  • 220 units are required at the beginning of Week 5. Hence, they need to order for 220 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 weeks), which means on Week 4.
  • Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.

Projected on-hand on Week 6}=(Projected on-hand of Week 5+Planned order receipt of Week 5Gross requirement of Week 5)+Scheduled receipt of current week=(50+220270)+0=0

Prepare a Material Requirement Plan (MRP) for Component C (2):

Operations Management, Chapter 12, Problem 5P , additional homework tip  9

  • Component E is the parent item of Component C (2). As the number of Component C is 2, the planned order release should be multiplied with 2 to determine the gross requirement of Component C.
  • On-hand inventory is 100 units. It remains same until Week 3, as there is no demand. Scheduled receipts of 30 units arrived on Week 4. Hence, the on-hand inventory is 130 units on Week 4.
  • Net requirement can be calculated by subtracting the projected on hand inventory of previous week from the gross requirement of current week.

Net requirement=Gross requirementOn-hand units of previous week=180130=50

  • 50 units are required at the beginning of Week 5. Hence, they need to order for 50 units (as the lot size is lot-for-lot) on two weeks before (as the lead-time is 2 weeks), which means on Week 3.
  • Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.

Projected on-hand on Week 5}=(Projected on-hand of Week 4+Planned order receipt of Week 4Gross requirement of Week 4)+Scheduled receipt of current week=(130+00)+0=130

  • Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.

Projected on-hand on Week 6}=(Projected on-hand of Week 5+Planned order receipt of Week 5Gross requirement of Week 5)+Scheduled receipt of current week=(130+50180)+0=0

Prepare a Material Requirement Plan (MRP) for Component D (2) and D (2):

Operations Management, Chapter 12, Problem 5P , additional homework tip  10

  • Component B (3) is the parent item of Component D (2) and Component C (2) is the parent item of Component D (2). As the number of Component D is 2, the planned order release of Component B should be multiplied with 2 to determine the gross requirement of Component D. The same should be followed for Component D (2) with its parent item C (2).
  • On-hand inventory is 80 units. It remains same until Week 3, as there is no demand.
  • Net requirement can be calculated by subtracting the projected on hand inventory of previous week from the gross requirement of current week.

Net requirement=Gross requirementOn-hand units of previous week=10080=20

  • 20 units are required at the beginning of Week 3. Hence, they need to order for 40 units (as the lot size is multiples of 40) on previous week (as the lead-time is 1 week), which means on Week 2.
  • Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.

Projected on-hand on Week 4}=(Projected on-hand of Week 3+Planned order receipt of Week 3Gross requirement of Week 3)+Scheduled receipt of current week=(80+40100)+0=20

  • Projected on-hand inventory is calculated by adding the scheduled receipts and the value attained by subtracting gross requirements from the sum of projected on-hand of previous week and planned order receipt of previous week.

Projected on-hand on Week 5}=(Projected on-hand of Week 4+Planned order receipt of Week 4Gross requirement of Week 4)+Scheduled receipt of current week=(20+440440)+0=20

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
a. One hundred twenty units of end item Z are needed at the beginning of week 7. Prepare a material requirements plan for component C. Take into account that on hand there are 40 units of Z,70 units of A, 100 units of B, and 30 units of C. Also, there is a scheduled receipt of 20 units ofcomponent C in week 4. Lead times are two weeks for Z and B, and one week for the other components. Lot-for-lot ordering will be used for all items b. Ninety-five units of end item E are needed at the beginning of week 7. Prepare a material requirements plan for component D. Take into account that 5 units of E are currently on hand, as well as50 units of B, 100 units of C, and 80 units of D. Also, 30 units of C have been outsourced and areexpected to arrive in week 4. Lead times are two weeks for E and C, and one week for the othercomponents. Assume lot-for-lot ordering except for D, where multiples of 40 must be used.
Develop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the startof week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are inproduction and will be completed by the start of week 2. Lot-for-lot ordering will be used for all items.
3. Item Z has a lead time of two weeks; A, B, C and D take one week each and E takes 3 weeks. Fifty units of Z are required in period 10. Assume that there is currently no inventory on hand of any of these items. Consider the following Bill of material and develop an MRP schedule for A, B, C, D and E showing gross and net requirements and order releases and order receipt dates. Assume Lot-for-lot ordering. C(3) A(2) Z D(4) E(2) B(4) Level 0 1 2 3

Chapter 12 Solutions

Operations Management

Ch. 12 - Prob. 7DRQCh. 12 - Briefly discuss the requirements for effective...Ch. 12 - Prob. 9DRQCh. 12 - How can the use of MRP contribute to productivity?Ch. 12 - Prob. 11DRQCh. 12 - What is lot sizing. what is its goal, and why is...Ch. 12 - Contrast planned-order receipts and scheduled...Ch. 12 - If seasonal variations are present, is their...Ch. 12 - Prob. 15DRQCh. 12 - What are some unforeseen costs of ERP?Ch. 12 - What trade-offs are involved in the decision to...Ch. 12 - Who in the organization needs to be involved in...Ch. 12 - Prob. 3TSCh. 12 - Prob. 1CTECh. 12 - Give one example of unethical behavior involving...Ch. 12 - a. Given the following diagram for a product,...Ch. 12 - Prob. 2PCh. 12 - Prob. 3PCh. 12 - Eighty units of end item E are needed at the...Ch. 12 - a. One hundred twenty units of end item Z are...Ch. 12 - A table is assembled using three components, as...Ch. 12 - Eighty units of end item X are needed at the...Ch. 12 - Oh No!, Inc., sells three models of radar detector...Ch. 12 - Assume that you are the manager of a shop that...Ch. 12 - Assume that you are the manager of Assembly, Inc....Ch. 12 - Determine material requirements plans for pans N...Ch. 12 - A firm that produces electric golf carts has just...Ch. 12 - Refer to Problem 12. Assume that unusually mild...Ch. 12 - Using the accompanying diagram, do the following:...Ch. 12 - A company that manufactures paving material for...Ch. 12 - Prob. 16PCh. 12 - The MRP Department has a problem. Its computer...Ch. 12 - Develop a material requirements plan for component...Ch. 12 - How many wheels sets should the manager order?Ch. 12 - When should the wheel sets be ordered?Ch. 12 - Prob. 2.1CQCh. 12 - Prob. 1OTQCh. 12 - Prob. 2OTQCh. 12 - Suppose the company has just received an order for...Ch. 12 - Prob. 4OTQCh. 12 - Prob. 5OTQ

Additional Business Textbook Solutions

Find more solutions based on key concepts
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY