Assume that you are the manager of Assembly, Inc. You have just received an order for 40 units of an industrial robot, which is to be delivered at the start of week 7 of your
Want to see the full answer?
Check out a sample textbook solutionChapter 12 Solutions
Operations Management
Additional Business Textbook Solutions
Operations Management
Operations Management, Binder Ready Version: An Integrated Approach
Operations Management: Processes and Supply Chains (11th Edition)
Business in Action (8th Edition)
Principles Of Operations Management
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
- Assume that you are the manager of Assembly, Inc. You have just received an order for 25 units of an industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine how many units of subassembly G to order and the timing of those orders, given that subassembly G must be ordered in multiples of 80 units and all other components are ordered lot-for-lot. Assume that the components are used only for this particular robot. Item Lead Time (weeks) On Hand Components Robot 2 10 B, G, C(3) B 1 5 E, F C 1 20 G(2), H E 2 4 — F 3 8 — G 2 15 — H 1 10 — Subassembly G order quantity (in units) Subassembly G should start at beginning of Week (Click to select) 1 2 3 4arrow_forwardAssume you are the manager of Assembly Inc., you have just received an order for 40 units of an industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine the timing of subassembly G, given the subassembly G must be ordered in multiples of 80 units & all other components are ordered lot for lot. Assume that the components are used only for this particular robot. Item Lead time (ks) On Hand | Components Robot 2 10 B, G, C(3) 1 E, F 1 G(2), H 2 3 B C E F G H 2 1 5 20 4 8 15 10arrow_forwardAssume that you are the manager of Assembly, Inc. You have just received an order for 40 units ofan industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine how many units of subassembly G to order and the timing of thoseorders, given that subassembly G must be ordered in multiples of 80 units and all other componentsare ordered lot-for-lot. Assume that the components are used only for this particular robot.Item Lead Time (weeks) On Hand ComponentsRobot 2 10 B, G, C(3)B 1 5 E, FC 1 20 G(2), HE 2 4 —F 3 8 —G 2 15 —H 1 10 —arrow_forward
- Assume you are the manager of Assembly Inc., you have just received an order for 40 units of an industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine how many units of subassembly G to order, given the subassembly G must be ordered in multiples of 80 units & all other components are ordered lot for lot. Assume that the components are used only for this particular robot. Item Lead time (ks) On Hand Components B, G, C(3) Robot 2 10 1 E, F G(2), H C E F G H 1 2 3 2 1 5 20 4 8 15 10arrow_forwardEach unit of A is composed of one unit of B, two units of C, and one unit of D. C is composed of two units of D and three units of E. Items A, C, D, and E have on-hand inventories of 20, 10, 20, and 10 units, respectively. Item B has a scheduled receipt of 10 units in Period 1, and C has a scheduled receipt of 50 units in Period 1. Lot-for-lot (L4L) lot sizing is used for Items A and B. Item C requires a minimum lot size of 50 units. D and E are required to be purchased in multiples of 100 and 50, respectively. Lead times are one period for Items A, B, and C, and two periods for Items D and E. The gross requirements for A are 30 in Period 2, 30 in Period 5, and 40 in Period 8. Find the planned-order releases for all itemsarrow_forwardEach unit of A is composed of one unit of B, two units of C, and one unit of D. C is composed of two units of D and three units of E. Items A, C, D, and E have on-hand inventories of 20, 10, 20, and 15 units, respectively. Item B has a scheduled receipt of 10 units in Period 1, and C has a scheduled receipt of 50 units in Period 1. Lot-for-lot (L4L) is used for Items A and B. Item C requires a minimum lot size of 50 units. D and E are required to be purchased in multiples of 95 and 55, respectively. Lead times are one period for Items A, B, and C, and two periods for Items D and E. The gross requirements for A are 30 in Period 2, 30 in Period 5, and 40 in Period 8.arrow_forward
- aw 11 Assume you are the manager of Assembly, Inc. You have just received an order for 29 units of an industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine how many units of subassembly G to order and the timing of those orders, given that subassembly G must be ordered in multiples of 80 units and all other components are ordered lot-for-lot. Assume that the components are used only for this particular robot. Item Robot B C E F G H Lead Time (weeks) On Hand 2 1 1 NM NA 2 2 Click here for the Excel Data File 5 20 4 8 15 10 Subassembly G order quantity (in units) Order subassembly G at start of week Search Components B, G, C(3) E, F G(2), H کا < Prev 19 of 19 Next W 9arrow_forwardMontague Composite makes a unit A, which consists of two units of B, three units of C, and four units of D. C is composed of three units of D and two units of E. Items A, C, D and E have on-hand inventories of 10, 20, 30 and 40 units respectively. Item B has a scheduled receipt of 50 units in period 1, and C has a scheduled receipt of 90 units in period 1. Lot-for-lot sizing is used for items A and B. Item C requires a minimum lot size of 60 units. D and E must be purchased in multiples of 35 and 55 respectively. Lead times are one period for items A, B and C, and two periods for items D and E. The gross requirements for A are 180 in period 5, and 220 in period 8. Determine the planned-order releases for all items using template 2 (provided at the end of the paper)arrow_forwardOne unit of A is composed of two units of B and three units of C. Each B is composed of one unit of F. C is made of one unit of D, one unit of E, and two units of F. Items A, B, C, and D have 20, 50, 60, and 25 units of on-hand inventory, respectively. Items A, B, and C use lot-for-lot (L4L) as their lot-sizing technique, while D, E, and F require multiples of 50, 100, and 100, respectively, to be purchased. B has scheduled receipts of 30 units inperiod 1. No other scheduled receipts exist. Lead times are one period for items A, B, and D, and two periods for items C, E, and F. Gross requirements for A are 20 units in period 1, 20 units in period 2, 60 units in period 6, and 50 units in period 8. Find the planned order releases for all items.arrow_forward
- One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; items A, B, E, and F have two-week lead times; and item D has a lead time of three weeks. Lot-for-lot (L4L) lot sizing is used for items C, E, and F; lots of size 20, 40, and 160 are used for items A, B, and D, respectively. Items A, B, D, and E have on-hand (beginning) inventories of 5, 10, 100, and 100, respectively; all other items have zero beginning inventories. We are scheduled to receive 10 units of A in week 3, 20 units of B in week 7, 40 units of F in week 5, and 60 units of E in week 2; there are no other scheduled receipts. If 20 units of A are required in week 10, use the low-level-coded bill-of-materials (product structure tree) to find thenecessary planned order releases for all components.arrow_forwardConsider the bill of materials (BOM) shown to the right. Part 2 If inventory consists of 33 units of B, 11 unitunit of F, and 33 units of G, how many units of G, E, and D must be purchased to produce 55 units of product A? enter your response here unit(s) of item G, enter your response here units of item E, and enter your response here units of item D. (Enter your responses as integers.)arrow_forwardThese are orders that have already been released and are to arrive in the future.arrow_forward