OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
7th Edition
ISBN: 9780077835439
Author: Roger G Schroeder, M. Johnny Rungtusanatham, Susan Meyer Goldstein
Publisher: McGraw-Hill Education
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 12, Problem 3P

Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is on” hour. Sequence” the jobs in priority order 1, 2, 3, 4.

JobWork Center/Machine Hours Due Date (days)
1 A/3, B/2, C/2 3
2 C/2, A/4 2
3 B/6, A/1, C/3 4
4 C/4, A/1, B/2  3
  1. a. What is the make span?
  2. b. How much machine idle time is there?
  3. c. When is each job delivered compared with its due date?
  4. d. How much idle time (waiting time) is there for each job?
  5. e. Devise a better job sequence for processing.

a)

Expert Solution
Check Mark
Summary Introduction

To determine: The makespan.

Introduction:

Gantt chart is the tool used to allocate the resources and schedule the tasks of projects.

Answer to Problem 3P

The makespan is 18 hours.

Explanation of Solution

Given information:

Moving time between the machines is one hour and sequence is given as 1, 2, 3, and 4. In addition to this, the information is given below:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  1

Construct the Gantt chart:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  2

Hence, the total makespan is 18 hours (refer the Gantt chart).

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The machine idle time.

Introduction:

Gantt chart is the tool used to allocate the resources and schedule the tasks of projects.

Answer to Problem 3P

The machine idle time is 24 hours.

Explanation of Solution

Given information:

Moving time between the machines is one hour and sequence is given as 1, 2, 3, and 4. In addition to this, the information is given below:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  3

Construct Gantt chart:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  4

Determine the idle time for Machine A:

It can be determined that subtracting the sum of machine hours from the total makespan.

Idle time=Total makespanTotal machine hours=18(3+4+1+1)=189=9 hours

Determine the idle time for Machine B:

It can be determined that subtracting the sum of machine hours from the total makespan.

Idle time=Total makespanTotal machine hours=18(2+6+2)=1810=8 hours

Determine the idle time for Machine C:

It can be determined that the subtracting the sum of machine hours from the total makespan.

Idle time=Total makespanTotal machine hours=18(2+2+3+4)=1811=7 hours

Determine the machine idle time:

It can be calculated by adding the idle time of Machine A, Machine B, and Machine C.

Machine idle time=Idle time of Machine A+Idle time of Machine B+Idle time of Machine C=9+8+7=24 hours

Hence, the total machine idle time is 24 hours.

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The delivery time of each job compared to due dates.

Introduction:

Gantt chart is the tool used to allocate the resources and schedule the tasks of projects.

Answer to Problem 3P

The delivery time does not exist due date.

Explanation of Solution

Given information:

Moving time between the machines is one hour and sequence is given as 1, 2, 3, and 4. In addition to this, the information is given below:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  5

Construct Gantt chart:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  6

Determine the delivery time:

Due date is given in days. It must be converted to hours by considering working hours per day is 8 hours.

Job Due date (hours) Delivery time (hours)
1 24 9
2 16 7
3 32 18
4 24 14

Delivery time is taken from the Gantt chart. Example: Job 1 is on its 9th hour at last. After that there is no Job 1.

d)

Expert Solution
Check Mark
Summary Introduction

To determine: The idle time of the jobs.

Introduction:

Gantt chart is the tool used to allocate the resources and schedule the tasks of projects.

Answer to Problem 3P

The job idle time is 11 hours.

Explanation of Solution

Given information:

Moving time between the machines is one hour and sequence is given as 1, 2, 3, and 4. In addition to this, the information is given below:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  7

Construct Gantt chart:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  8

Determine the idle time of the jobs

There is no idle time for Job 1 and Job 2. However, Job 3 has the idle time of 6 hours in Machine C from 9th hour to 15th hour (Refer Gantt chart). Job 4 has the idle time of 5 hours in Machine A from 8th hour to 13th hour (Refer Gantt chart).

Hence, the total idle time is 11 hours.

e)

Expert Solution
Check Mark
Summary Introduction

To determine: The better sequence for processing.

Introduction:

Gantt chart is the tool used to allocate the resources and schedule the tasks of projects.

Answer to Problem 3P

The makespan is 14 hours and the better sequence is 3, 2, 4, and 1.

Explanation of Solution

Given information:

Moving time between the machines is one hour and sequence is given as 1, 2, 3, and 4. In addition to this, the information is given below:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  9

Construct the Gantt chart:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  10

Hence, the total makespan is 14 hours (refer the Gantt chart).

Determine the idle time for Machine A:

It can be determined that subtracting the sum of machine hours from the total makespan.

Idle time=Total makespanTotal machine hours=14(3+4+1+1)=149=5 hours

Determine the idle time for Machine B:

It can be determined that subtracting the sum of machine hours from the total makespan.

Idle time=Total makespanTotal machine hours=14(2+6+2)=1410=4 hours

Determine the idle time for Machine C:

It can be determined that subtracting the sum of machine hours from the total makespan.

Idle time=Total makespanTotal machine hours=14(2+2+3+4)=1411=3 hours

Determine the machine idle time:

It can be calculated by adding the idle time of Machine A, Machine B, and Machine C.

Machine idle time=Idle time of Machine A+Idle time of Machine B+Idle time of Machine C=5+4+3=12 hours

Hence, the total machine idle time is 12 hours.

Determine the delivery time:

Due date is given in days. It must be converted to hours by considering the working hours per day as 8 hours.

Job Due date (hours) Delivery time (hours)
1 24 14
2 16 7
3 32 12
4 24 12

Delivery time is taken from the Gantt chart. Example: Job 2 is on its 7th hour at last. After that there is no Job 2.

Hence, the sequence 3, 2, 4, and 1 is better in makespan and idle time.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
What is Bitcoin? How important is it to businesses and individuals? How does it cause environmental damage and is that damage worth continued uses of Bitcoin? Read the following articles to help answer these questions: United Nations University. (2023, October 24). UN study reveals the hidden environmental impacts of bitcoin: Carbon is not the only harmful by-product. https://unu.edu/press-release/un-study-reveals-hidden-environmental-impacts-bitcoin-carbon-not-only-harmful-product#:~:text=Bitcoin%2C%20the%20most%20popular%20cryptocurrency,the%20worldwide%20Bitcoin%20mining%20network. Salam, E. (2023, April 26). Bitcoin is terrible for the environment – can it ever go green? The Guardian. https://www.theguardian.com/technology/2023/apr/26/bitcoin-mining-climate-crisis-environmental-impact
419 X .com/courses/1546/assignments/49499?module_item_id=111573 Unlimited Attempts Allowed ✓ Details Directions: Record a video of yourself giving a business presentation. Imagine you are tasked with researching a professional development topic on business communication for 40 coworkers. You are then expected to give a 4 - 5 minute presentation on the topic. Choose any topic related to business communication, such as intercultural communication, effective leadership, professional writing, etc. Research the topic and prepare a 4 - 5 minute presentation that could be given over video conference call (such as Zoom). You may use visual aids if you choose. Upload a video file of your presentation. Provide all needed citations. Requirements: 4-5 minutes long Contains visual and audio Create your own work; do not plagiarize Cite your sources using APA citations Choose a submission type T
acts Container chips (s 150 cussion: Conflict X + e.com/courses/1546/discussion_topics/15722?module_item_id=111559 24 Winter > Discussions > Week 8 Discussion: Conflict 时☆ 26 Replies, 26 Unread Week 8 Discussion: Conflict Write a 200 - 300 word discussion post based on the prompt below. Reply to at least one other student in 50 - 100 words. Can you think of a time when a conflict led to a new opportunity, better understanding, or other positive result? If not, think of a past conflict and imagine a positive outcome. Discuss the impact of this conflict on your workplace relationships, productivity, and innovation. Source: Business Communication for Success. (2015). University of Minnesota Libraries Publishing. Attribution-NonCommerical-ShareAlike. Edit View Insert Format Tools Table 12ptv Paragraph BIUA T2
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Understanding Management (MindTap Course List)
Management
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Cengage Learning
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY