Concept explainers
Keller Construction is considering two new investments. Project E calls for the purchase of earthmoving equipment. Project H represents an investment in a hydraulic lift. Keller wishes to use a
a. Determine the net present value of the projects based on a zero percent discount rate.
b. Determine the net present value of the projects based on a 9 percent discount rate.
c. The
d. If the two projects are not mutually exclusive, what would your acceptance or rejection decision be if the cost of capital (discount rate) is 8 percent? (Use the net present value profile for your decision; no actual numbers are necessary.)
e. If the two projects are mutually exclusive (the selection of one precludes the selection of the other), what would be your decision if the cost of capital is (1) 6 percent, (2) 13 percent, (3) 18 percent? Once again, use the net present value profile for your answer.
a.
To calculate: The NPV of the projects by using zero discount rate for Keller Construction Company.
Introduction:
Net present value (NPV):
It is the difference between the PV (present value) of cash inflows and the PV of cash outflows. It is used in capital budgeting and planning of investment to assess the benefits and losses of any project or investment.
Answer to Problem 23P
The NPV of the project E is $8,000 and project H is $5,000 based on zero discount rate for Keller Construction Company.
Explanation of Solution
The calculation of NPV of project E:
The calculation of NPV of project H:
Working Notes:
The calculation of inflows for project E:
The calculation of inflows for project H:
b.
To calculate: The NPV of the projects by using 9% discount rate for Keller Construction Company.
Introduction:
Net present value (NPV):
It is the difference between the PV (present value) of cash inflows and the PV of cash outflows. It is used in capital budgeting and planning of investment to assess the benefits and losses of any project or investment.
Present value (PV):
The current value of an investment or an asset is termed as its present value. It is calculated by discounting the future value of the investment or asset.
Answer to Problem 23P
The calculation of PV of inflows for Project E at 9%:
The calculation of PV of inflows for Project H at 9%:
Thus, the NPV of project E is $2,127 and project H is $1,976.
Explanation of Solution
The calculation of NPV of project E:
The calculation of NPV of project H:
The formulae used for the calculation of PV of inflows for Project E:
The formulae used for the calculation of PV of inflows for Project E:
c.
To plot: The graph for the NPV of the project according to the Fig. 12-3 for the Keller Construction Company.
Introduction:
Internal rate of return (IRR):
A method of capital budgeting that is used to measure the profitability of potential projects or investments. It is a discount that makes the NPV equals to zero for a specific project.
Answer to Problem 23P
The graph for the NPV of the project according to the Fig. 12-3 for the Keller Construction Company:
Explanation of Solution
Calculation of IRR:
Working Note:
The formulae used in the calculation of IRR:
d.
To determine: The decision regarding the acceptance or the rejection of the projects, if the projects are mutually exclusive and discount rate of the cost of capital is 8% for the Keller Construction Company.
Introduction:
Net present value (NPV):
It is the difference between the PV (present value) of cash inflows and the PV of cash outflows. It is used in capital budgeting and planning of investment to assess the benefits and losses of any project or investment.
Present value (PV):
The current value of an investment or an asset is termed as its present value. It is calculated by discounting the future value of the investment or asset.
Answer to Problem 23P
The calculation of PV of project E and project H at 8%:
The NPV of project E is $2,681 and project H is $2,277. Thus, the NPV of project E is higher than the project H. Therefore, project E must be accepted as it is more profitable than the project H.
Explanation of Solution
The calculation of NPV of project E:
The calculation of NPV of project H:
The formulae used in the calculation of PV of project E and H at 8% are shown below:
e.
To determine: The decision regarding the acceptance or rejection of the projects, if the projects are mutually exclusive and discount rates of cost of capital are 6%, 13%, and 18% for the Keller Construction Company.
Introduction:
Net present value (NPV):
It is the difference between the PV (present value) of cash inflows and the PV of cash outflows. It is used in capital budgeting and planning of investment to assess the benefits and losses of any project or investment.
Present value (PV):
The current value of an investment or an asset is termed as its present value. It is calculated by discounting the future value of the investment or asset.
Answer to Problem 23P
The calculation of PV of project E and project H at 6%:
The NPV of project E is $3,855 and project H is $2,903. Thus, the NPV of project E is higher than the project H, So, project E must be accepted at 6% discount rate as it is superior to the project H.
The calculation of PV of project E and project H at 13%:
The NPV of project E is $108 and project H is $847. Thus, the NPV of project H is higher than the project E, So, project H must be accepted at 13% discount rate as it is superior to the project E.
The calculation of PV of project E and project H at 18%:
The NPV of project E is ($2,035) and project H is ($415). Thus, both projects must be rejected at 18% discount rate as NPV of both projects are negative.
Explanation of Solution
The calculation of NPV of project E at 6%:
The calculation of NPV of project H at 6%:
The calculation of NPV of project E at 13%:
The calculation of NPV of project H at 13%:
The calculation of NPV of project E at 18%:
The calculation of NPV of project H at 18%:
The formulae used in the calculation of PV of project E and H at 6% are shown below:
The formulae used in the calculation of PV of project E and H at 13% are shown below:
The formulae used in the calculation of PV of project E and H at 18% are shown below:
Want to see more full solutions like this?
Chapter 12 Solutions
FOUND.OF FINANCIAL MANAGEMENT-ACCESS
- Please help me with this question (picture below) 1. Calculate the payback period, accounting rate of return, net present value of each project. Based on your calculations, discuss whether the projects should go ahead. Assume that the target value for payback is 3 years for project A and 2 years for project B.2. List advantages and disadvantages of payback period, accounting rate of return, net present value of each project.arrow_forwardi) Calculate the payback period for each project. ii) Calculate the net present value (NPV) for each project.arrow_forwardYokam Company is considering two alternative projects. Project 1 requires an initial investment of $400,000 and has a present value of cash flows of $1,100,000. Project 2 requires an initial investment of $4,000,000 and has a present value of cash flows of $6,000,000. 1. Compute the profitability index for each project. 2. Based on the profitability index, which project should the company prefer? Complete this question by entering your answers in the tabs below. Required 1 Required 2 Compute the profitability index for each project. Project 1 Project 2 Choose Numerator: Profitability Index T 7 Choose Denominator: 4 of 5 180 # Next > G Oarrow_forward
- Pound Industries is attempting to select the best of three mutually exclusive projects. The initial investment and subsequent cash inflows associated with these projects are shown in the following table attached: a. Calculate the payback period for each project. b. Calcuate the net present value (NPV) of each project, assuming that the firm has a cost of capital equal to 13%. c. Calculate the internal rate of return (IRR) for each project. d. Indicate which project you would recommend.arrow_forwardYokam Company is considering two alternative projects. Project 1 requires an initial investment of $400,000 and has a present value of cash flows of $1,100,000. Project 2 requires an initial investment of $4 million and has a present value of cash flows of $6 million. Compute the profitability index for each project. Based on the profitability index, which project should the company prefer? Explain.arrow_forwardConsider the following sets of investment projects: (a) Classify each project as either simple or nonsimple.(b) Compute the i* for Project A, using the quadratic equation.(c) Obtain the rate(s) of return for each project by plotting the PW as a function of interest rate.arrow_forward
- A. Calculate the payback period for each project and identify the project in which the company should invest, giving one reason for your choice. B. Calculate the accounting rate of return on initial capital for each project.arrow_forwardWhat are the correct free cash flows for evaluating this project? Start from the correct net income which has already been given.arrow_forwardSan Lucas Corporation is considering investment in robotic machinery based upon the following estimates: a. Determine the net present value of the equipment, assuming a desired rate of return of 10% and annual net cash flows of 700,000. Use the present value tables appearing in Exhibits 2 and 5 of this chapter. b. Determine the net present value of the equipment, assuming a desired rate of return of 10% and annual net cash flows of 500,000, 700,000, and 900,000. Use the present value tables (Exhibits 2 and 5) provided in the chapter in determining your answer. c. Determine the minimum annual net cash flow necessary to generate a positive net present value, assuming a desired rate of return of 10%. Round to the nearest dollar. d. Interpret the results of parts (a), (b), and (c).arrow_forward
- There are two projects under consideration by the Rainbow factory. Each of the projects will require an initial investment of $35,000 and is expected to generate the following cash flows: Use the information from the previous exercise to calculate the internal rate of return on both projects and make a recommendation on which one to accept. For further instructions on internal rate of return in Excel, see Appendix C.arrow_forwardThe management of Kawneer North America is considering investing in a new facility and the following cash flows are expected to result from the investment: A. What is the payback period of this uneven cash flow? B. Does your answer change if year 10s cash inflow changes to $500,000?arrow_forwardCalculate the cash flows for each year. Based on these cash flows and the average project cost of capital, what are the projects NPV, IRR, MIRR, PI, payback, and discounted payback? Do these indicators suggest that the project should be undertaken?arrow_forward
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubEBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENTManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage Learning
- Financial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Intermediate Financial Management (MindTap Course...FinanceISBN:9781337395083Author:Eugene F. Brigham, Phillip R. DavesPublisher:Cengage LearningPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College