Interpretation: Contour lines for the problem of locating a machine shop described in Problem 28, needs to be drawn.

Concept Introduction: The line that passes through or drawn through points having the same value is called a contour line.

Expert Solution & Answer
Check Mark

Answer to Problem 33P

Contour lines have been drawn along the plotted points.

Explanation of Solution

Given information: Contour lines for locating the machine shop is drawn from the values of points derived.

The procedure for drawing contour lines is as follows:

  1. The points need to be plotted on a graph paper, and horizontal and vertical lines need to be drawn along their respective axis.
  2. The horizontal and vertical lines, needs to be clearly numbered from left to right.
  3. It is being assumed, Di to be the sum of weights of points along the horizontal line i and Ci be the sum of weights of points along the vertical line j .
  4. Following is the method for computing numbers:

  M1=M0+2C1         N0=N0+2D1M2=M1+2C2         N1=N1+2D2

Where Ci represents the total of the weights added up along the vertical line and Di represents the total of the weights added up along the horizontal line.

A region (i,j) can be defined as bounded by the ith vertical line and the (i+1)th vertical line and horizontally by the jth horizontal line and (j+1)th horizontal line. The area below the first horizontal line is represented by (i,0) , and that towards the left of the first vertical line is represented by (0,j) . The contour line’s slope is given by the formula:

  Sij=MiNj

After calculating the slopes of the contour lines, it is drawn by starting from any point, moves forward along the predetermined slopes, as calculated from the above mentioned formula and at an angle

The weights and coordinates of the locations of machines are being tabulated as follows:

    Location of machinesWeight
    (3,3)18
    (3,7)18
    (8,4)14
    (12,3)1
    (14,6)16

Let us assume the following:

  (a1,b1)=(3,3); (a2,b2)=(3,7); (a3,b3)=(8,4); (a4,b4)=(12,3); (a5,b5)=(14,6)

and w1=18; w2=18; w3=14; w5=16  . With these points the horizontal and vertical lines are drawn along the axis and the values of M0,M1,M2,M3,M4 and N0,N1,N2,N3,N4 are calculated.

  M0=(18+18+14+1+16)=56M1=53+12=76M2=76+12=23M3=23+2=43M4=43+26=53

  N0=(18+18+14+1+16)=56N1=53+94=712N2=712+12=1312N3=1312+13=1712M4=1712+14=53

Further, in order to find the slope, the ratios are calculated:

  S0,0=1S1,0=(76)/(53)=0.7S2,0=(23)/(53)=0.4S3,0=(43)/(53)=0.8S4,0=(53)/(53)=0.1 S0,1=(53)/(712)=2.8S1,1=(76)/(712)=12S2,1=(23)/(712)=1.1S3,1=(43)/(712)=2.2S4,1=(53)/(712)=2.8

  S0,2=(53)/(1312)=1.5S1,2=(76)/(1312)=1.07S2,2=(23)/(1312)=0.61S3,2=(43)/(1312)=1.2S4,2=(53)/(1312)=1.5S0,3=(53)/(1712)=1.17S1,3=(76)/(1712)=0.82S2,3=(23)/(1712)=0.47S3,3=(43)/(1712)=0.94S4,3=(53)/(1712)=1.17

  S0,4=(53)/(53)=1S1,4=(76)/(53)=0.7S2,4=(23)/(53)=0.4S3,4=(43)/(53)=0.8S4,4=(53)/(53)=1

From the derived points, the contour lines has been plotted as shown in the figure below: EBK PRODUCTION AND OPERATIONS ANALYSIS, Chapter 11.9, Problem 33P

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
وبة واضافة هذه القيمة الى القيم Ex: Assign each job for each worker at minimum total Cost عمل لكل عامل وبأقل كلفة ممكنة obs الأعمال Workors العمال J1 J2 J3 J4 W₁ 15 13 14 12 W2 11 12 15 13 W3 13 12 10 11 W4 15 17 14 16
The average completion time (flow time) for the sequence developed using the FCFS rule = 11.75 days (round your response to two decimal places). The percentage utilization for the sequence developed using the FCFS rule = 42.55 % (enter your response as a percentage rounded to two decimal places). b) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: Job Due Date A 212 B 209 C 208 D 210 Duration (days) 6 3 3 8 Sequence 1 Job B 2 3 4 A D The average tardiness (job lateness) for the sequence developed using the SPT rule = 5.00 days (round your response to two decimal places). The average completion time (flow time) for the sequence developed using the SPT rule = 10.25 days…
With the aid of examples, fully discuss any five (5) political tactics used in organisations.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,