
Concept explainers
Interpretation: A real estate firm wishes to open four new offices in Boston area and they are having six potential sites available. Based on the number of employees in each office and the location of the properties that each employee will manage, the firm estimated the total travel time in hours per day for each office and each location. The optimal assignment of offices to sites to minimize employee travel time needs to be determined.
Offices | |||||
A | B | C | D | ||
1 | 10 | 3 | 3 | 8 | |
2 | 13 | 5 | 2 | 6 | |
Sites | 3 | 12 | 9 | 9 | 4 |
4 | 14 | 2 | 7 | 7 | |
5 | 17 | 7 | 4 | 3 | |
6 | 12 | 8 | 5 | 5 |
Concept Introduction: A discrete facility location problem is considered, when a balance has to be achieved between the minimum and maximum number of customers, wherein there is a difference that arises between the allocation of these customers made to every plant.

Answer to Problem 46AP
The optimal travel time has been derived as 17.
Explanation of Solution
Given information:
Offices | |||||
A | B | C | D | ||
1 | 10 | 3 | 3 | 8 | |
2 | 13 | 5 | 2 | 6 | |
Sites | 3 | 12 | 9 | 9 | 4 |
4 | 14 | 2 | 7 | 7 | |
5 | 17 | 7 | 4 | 3 | |
6 | 12 | 8 | 5 | 5 |
When there are no inter-departmental interactions and a discrete set of alternative locations could be considered, then assignment problems can be considered to be appropriate. Following are the procedure for solution for assignment problems:
- The smallest number in row 1 needs to be identified and it should be subtracted from all the entries in that row. This procedure needs to be repeated for all the rows in cost matrix.
- Similarly, the smallest number in column 1 needs to be identified and it should be subtracted from all the entries in column 1. This procedure needs to be repeated for all the columns in cost matrix.
- At a certain point, each column and each row will have at least a zero. If there is possibility for making a zero assignment, then the same can be done, which in turn will be the optimal solution, and if not, then proceed to the next step.
- The maximum number of zero cost assignments needs to be determined, which will be equal to smallest number of lines adequate to cover all zeros. These lines are not necessarily unique and are found by inspection. The number of lines drawn should be less than the maximum number of zero cost assignments.
- The smallest uncovered number should be identified and proceed with the following steps:
- Subtract smallest uncovered number from all the other uncovered numbers.
- Add this to the step at the point where the line crosses.
- Return back to step 3
Step 1: The below shown matrix, not being a square matrix, dummy rows to balance the sites and offices are added.
Offices | ||||
Sites | A | B | C | D |
1 | 10 | 3 | 3 | 8 |
2 | 13 | 5 | 2 | 6 |
3 | 12 | 9 | 9 | 4 |
4 | 14 | 2 | 7 | 7 |
5 | 17 | 7 | 4 | 3 |
6 | 12 | 8 | 5 | 5 |
By adding the dummy rows the matrix has been modified as shown below:
Offices | ||||||
Sites | A | B | C | D | E | F |
1 | 10 | 3 | 3 | 8 | 0 | 0 |
2 | 13 | 5 | 2 | 6 | 0 | 0 |
3 | 12 | 9 | 9 | 4 | 0 | 0 |
4 | 14 | 2 | 7 | 7 | 0 | 0 |
5 | 17 | 7 | 4 | 3 | 0 | 0 |
6 | 12 | 8 | 5 | 5 | 0 | 0 |
Step 2: The row reducing matrix needs to be performed by subtracting the smallest number from each row. Since in this case, the resultant zero assignment has been achieved for each office, further column reduction matrix is not performed.
Offices | ||||||
Sites | A | B | C | D | E | F |
1 | 0 | 1 | 1 | 5 | 0 | 0 |
2 | 3 | 3 | 0 | 3 | 0 | 0 |
3 | 2 | 7 | 7 | 1 | 0 | 0 |
4 | 4 | 0 | 5 | 4 | 0 | 0 |
5 | 7 | 5 | 2 | 0 | 0 | 0 |
6 | 2 | 6 | 3 | 2 | 0 | 0 |
Step 3: From each site identifying of the zero assignment gives the following matrix
Offices | ||||||
Sites | A | B | C | D | E | F |
1 | 1 | 1 | 5 | 0 | 0 | |
2 | 3 | 3 | 3 | 0 | 0 | |
3 | 2 | 7 | 7 | 1 | ![]() | 0 |
4 | 4 | ![]() | 5 | 4 | 0 | 0 |
5 | 7 | 5 | 2 | ![]() | 0 | 0 |
6 | 2 | 6 | 3 | 2 | 0 | ![]() |
Thus the optimal solution for travel time will be
Want to see more full solutions like this?
Chapter 11 Solutions
EBK PRODUCTION AND OPERATIONS ANALYSIS
- The Harvey Motorcycle Company produces three models: the Tiger, a sure-footed dirt bike; the LX2000, a nimble cafe racer; and the Golden, a large interstate tourer. The month's master production schedule calls for the production of 32 Goldens, 31 LX2000s, and 38 Tigers per 10-hour shift. What average cycle time is required for the assembly line to achieve the production quota in 10 hours? 0.099 hours per motorcycle. (Enter your response rounded to three decimal places.) If mixed-model scheduling is used, how many of each model will be produced before the production cycle is repeated? The greatest common divisor of the production requirements is Therefore, the Harvey Motorcycle Company will produce Goldens, LX2000s, and Tigers. (Enter your responses as integers.)arrow_forwardThe Harvey Motorcycle Company produces three models: the Tiger, a sure-footed dirt bike; the LX2000, a nimble cafe racer; and the Golden, a large interstate tourer. The month's master production schedule calls for the production of 32 Goldens, 31 LX2000s, and 38 Tigers per 10-hour shift. What average cycle time is required for the assembly line to achieve the production quota in 10 hours? hours per motorcycle. (Enter your response rounded to three decimal places.)arrow_forwardThe binding constraints for this problem are the second and third constraints are binding. Min x1 + 2x2 s.t. x1 + x2 ≤ 300 2x1 + x2 ≥ 400 2x1 + 5x2 ≥750 X1, X220 (a) Keeping the second objective function coefficient fixed at 2, over what range can the first objective function coefficient vary before there is a change in the optimal solution point? The first objective coefficient can from a low of to a high of (b) Keeping the first objective function coefficient fixed at 1, over what range can the second objective function coefficient vary before there is a change in the optimal solution point? The second objective coefficient can from a low of to a high of (c) If the objective function becomes Min 1.5x₁ + 2x2, what will be the optimal values of x1 and x2? x1 = X2 = What is the value of the objective function at the minimum? (d) If the objective function becomes Min 7x₁ + 6x2, what constraints will be binding? (Select all that apply.) First Constraint Second Constraint Third Constraint…arrow_forward
- [-16.66 Points] DETAILS MY NOTES CAMMIMS16 4.E.008. 0/1 Submissions Used A linear programming computer package is needed. ASK YOUR TEACHER PRACTICE ANOTHER The Clark County Sheriff's Department schedules police officers for 8-hour shifts. The beginning times for the shifts are 8:00 a.m., noon, 4:00 p.m., 8:00 p.m., midnight, and 4:00 a.m. An officer beginning a shift at one of these times works for the next 8 hours. During normal weekday operations, the number of officers needed varies depending on the time of day. The department staffing guidelines require the following minimum number of officers on duty: Time of Day 8:00 A.M. Noon Noon - 4:00 P.M. Minimum Officers Time of Day on Duty 4 7 4:00 P.M. - 8:00 P.M. 11 8:00 P.M. Midnight 6 Midnight 4:00 A.M. 4:00 A.M. -8:00 A.M. 3 7 Determine the number of police officers that should be scheduled to begin the 8-hour shifts at each of the six times (8:00 a.m., noon, 4:00 p.m., 8:00 p.m., midnight, and 4:00 a.m.) to minimize the total number…arrow_forwarddiscuss in detail the benefits of working in a teamarrow_forwardExplain why some people resist working in a team.arrow_forward
- Discuss the Open Systems Approach to Teamworkarrow_forwarddiscuss team development stagesarrow_forwardLearning Activity 6: Canadian Business This Year Read the following webpage: The Business Development Bank of Canada. (2023). Canadian economic outlook for 2024: Shifting into neutral. https://www.bdc.ca/en/articles- tools/blog/canadian-economic-outlook-for-2024- shifting-into-neutral "Despite persistently high inflation and rising. interest rates, the news was generally better than expected for the Canadian economy in 2023" (BDC Blog 2024). Discussion Question: In your view, what are the most pressing problems for Canadian companies or consumers in 2024? Explain your answer using current examples of companies or consumer concerns.arrow_forward
- Travelling and working internationally can lead to a life of adventure and unique career experiences. For businesses, selecting the right candidates to take on foreign assignments can propel, delay, or deny the success of the international ventures. As an international manager, identify key competencies you would look for in choosing expatriates. What might be some of their concerns in taking on overseas assignments? What are some best practices in supporting expats during and after their assignments?arrow_forwardResearch proposal: The Investigation of Career Development and Job satisfaction atEskom Rotek Industries 1. Introduction (250 words) 2. Research Context: Background (Research Context: Background (250 words) 3. The Research Problem (The Research Problem) 4. Aim of the study (Maximum 50 words) 5. Research Objectives (3 in total) 6. Research Questions (3 in total) 7. Justification or rationale of the study (150 words) 8. Literature Review (2-3 pages / 1000-1500 words) 9. Research Design and Methodology (1 - 2 page in total, from 9.1 to 9.6) 9.1 Research Philosophy 9.2 Research Methodology 9.3 Target Population and Sampling strategy 9.4 Data Collection 9.5 Data Analysis (100 words) 9.6 Pilot Study 10. Ethical considerations 11. Referencearrow_forwardWith your experience and research, discuss;(a) what type of “Leadership Style” is used in communications services (Digicel Group Limited)?(b) whether the style used is successful or not and why. Justify your position with relevant citation and references ( Rubic is attached to guide the essay ) NOTE: NO AI RESPONSES PLEASEarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningManagement, Loose-Leaf VersionManagementISBN:9781305969308Author:Richard L. DaftPublisher:South-Western College Pub


