EBK PRODUCTION AND OPERATIONS ANALYSIS
EBK PRODUCTION AND OPERATIONS ANALYSIS
7th Edition
ISBN: 9781478628385
Author: Olsen
Publisher: WAVELAND PRESS (ECONTENT)
bartleby

Concept explainers

Question
Book Icon
Chapter 11, Problem 46AP
Summary Introduction

Interpretation: A real estate firm wishes to open four new offices in Boston area and they are having six potential sites available. Based on the number of employees in each office and the location of the properties that each employee will manage, the firm estimated the total travel time in hours per day for each office and each location. The optimal assignment of offices to sites to minimize employee travel time needs to be determined.

    Offices
    ABCD
    110338
    213526
    Sites312994
    414277
    517743
    612855

Concept Introduction: A discrete facility location problem is considered, when a balance has to be achieved between the minimum and maximum number of customers, wherein there is a difference that arises between the allocation of these customers made to every plant.

Expert Solution & Answer
Check Mark

Answer to Problem 46AP

The optimal travel time has been derived as 17.

Explanation of Solution

Given information:

    Offices
    ABCD
    110338
    213526
    Sites312994
    414277
    517743
    612855

When there are no inter-departmental interactions and a discrete set of alternative locations could be considered, then assignment problems can be considered to be appropriate. Following are the procedure for solution for assignment problems:

  1. The smallest number in row 1 needs to be identified and it should be subtracted from all the entries in that row. This procedure needs to be repeated for all the rows in cost matrix.
  2. Similarly, the smallest number in column 1 needs to be identified and it should be subtracted from all the entries in column 1. This procedure needs to be repeated for all the columns in cost matrix.
  3. At a certain point, each column and each row will have at least a zero. If there is possibility for making a zero assignment, then the same can be done, which in turn will be the optimal solution, and if not, then proceed to the next step.
  4. The maximum number of zero cost assignments needs to be determined, which will be equal to smallest number of lines adequate to cover all zeros. These lines are not necessarily unique and are found by inspection. The number of lines drawn should be less than the maximum number of zero cost assignments.
  5. The smallest uncovered number should be identified and proceed with the following steps:
    1. Subtract smallest uncovered number from all the other uncovered numbers.
    2. Add this to the step at the point where the line crosses.
    3. Return back to step 3

Step 1: The below shown matrix, not being a square matrix, dummy rows to balance the sites and offices are added.

    Offices
    SitesABCD
    110338
    213526
    312994
    414277
    517743
    612855

By adding the dummy rows the matrix has been modified as shown below:

    Offices
    SitesABCDEF
    11033800
    21352600
    31299400
    41427700
    51774300
    61285500

Step 2: The row reducing matrix needs to be performed by subtracting the smallest number from each row. Since in this case, the resultant zero assignment has been achieved for each office, further column reduction matrix is not performed.

    Offices
    SitesABCDEF
    1011500
    2330300
    3277100
    4405400
    5752000
    6263200

Step 3: From each site identifying of the zero assignment gives the following matrix

    Offices
    SitesABCDEF
    1 11500
    233 300
    32771EBK PRODUCTION AND OPERATIONS ANALYSIS, Chapter 11, Problem 46AP , additional homework tip  10
    44EBK PRODUCTION AND OPERATIONS ANALYSIS, Chapter 11, Problem 46AP , additional homework tip  25400
    5752 EBK PRODUCTION AND OPERATIONS ANALYSIS, Chapter 11, Problem 46AP , additional homework tip  300
    626320EBK PRODUCTION AND OPERATIONS ANALYSIS, Chapter 11, Problem 46AP , additional homework tip  4

Thus the optimal solution for travel time will be 10+2+2+3+0+0=17

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
working as a program operations manager
12 X1, X230 1 x =0x2 write the Following linear Programming model by 1- general Form Canonical Forms Canonical formY 2- Standard Form Max Z=35X+ 4 X 2 +6 X3 ST. X+2X2-5x3 = 40 3X, + 6X2 + 7x 3 = 30 7x, +lox2 x3 = 50 X3 X 2 X 3 <0
a/ a Minimum cost assign each worker for one job at Jobs J1 12 33 WI 2 4 6 W2 5 W3 5 33 6 7
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,