Tabard Industries forecasted the following demand for one of its most profitable products for the next 8 weeks: 120, 120, 120, 100, 100, 100, 80, and 80 units. The booked customer orders for this product, starting in week 1 are: 100, 80, 60, 40, 10, 10, 0, and 0 units. The current on-hand inventory is 150 units, the order quantity is 200 units, and the lead time is 1 week.

  1. Develop a MPS for this product.
  2. The marketing department revised its forecast. Starting with week 1, the new forecasts are: 120, 120, 120, 150, 150, 150, 100, and 100 units. Assuming that the prospective MPS you developed in part (a) does not change, prepare a revised MPS record. Comment on the situation that Tabard now faces.
  3. Returning to the original forecasted demand level and the MPS record you developed in part (a), assume that marketing accepted a new customer order for 200 units in week 2, and thereby booked orders in week 2 is now 280 units. Assuming that the prospective MPS you developed in part (a) does not change, prepare a revised MPS record. Comment on the situation that Tabard now faces.

Blurred answer
Students have asked these similar questions
The schedular at ZamTech uses MPS time-phased records for planning and item production. The planner is currently working on a schedule for a strut assembly, one of ZamTechs top-selling spare parts.The planner uses a production lot size of 170 and a safety stock of 15 for the strut assembly. The planner has the following forecasts (Ft) and orders (Dt) for the next 8 weeks, as shown in Table 1. Table 1 Week 1 2 3 4 5 6 7 8 Ft 130 130 130 140 140 140 145 145 Dt 45 38 18           Required: a) Help the master production scheduler to fill in the MPS time-phased record shown in Table 2 for the strut assembly. There are 120 units on hand. Table 2   1 2 3 4 5 6 7 8 Ft                 Dt                 EIt-1                 Pt                 EIt                 ATPt                 b) Can the planner accept the following orders? Update the MPS time-phased record for accepted orders, in Table 3. Table 3 Order Quantity Desired week 1 120 4 2 144 6 3 100 2…
minco inc is a small manufaturer of fused magnesia and silica. Minco's continuous improvement efforts led to a capacity and production planning software. to prepare for the use of software, a spreadsheet was first used to determine the capacity requirements for the main equipment (the fusion furnances) and the production schedule for the main products. A major product had the following forecast and committed orders (all in thousand dollars):                                      January                                              Feburary Week 2 3 4 1 2 3 4   Forecast 56 56 56 66 66 66 66   Committed order 44 0 18           The initial inventory was 119,000 pounds and the minimum stock at the end week was to be 83,000 pounds. Calculate the economic production quantity (EPQ) if the annual demand is 3,000,000 pounds, setup cost is $350 per setup, inventory holding cost rate is 20 percent per year, unit cost is $2 per pound, demand rate is 500 pounds per hour, and production…
Product A is an assemble-to-order product. It has a lot size of 150, and currentlyhas an on-hand inventory of 110 units. There is a 2-week demand time fence and a12-week planning time fence. The following table gives the original forecast and theactual customer orders for the next 12 weeks:Week 1 2 3 4 5 6 7 8 9 10 11 12Forecast 80 80 80 70 70 70 70 70 70 70 70 70Demand 83 78 65 61 49 51 34 17 11 7 0 0a. Given this information, develop a realistic master schedule, complete with ATPlogic.b. Tell how you would respond to each of the following customer order requests.Assume these are independent requests, and do not have cumulative effects.■ 20 units in week 3■ 40 units in week 5■ 120 units in week 7

Chapter 11 Solutions

Operations Management: Processes and Supply Chains (11th Edition)

Ch. 11 - A forecast of 240 units in January, 320 units in...Ch. 11 - An end items demand forecasts for the next 6 weeks...Ch. 11 - An end items demand forecasts for the next 10...Ch. 11 - Consider the bill of materials (BOM) in Figure...Ch. 11 - Product A is made from components B, C, and D....Ch. 11 - What is the lead time (in weeks) to respond to a...Ch. 11 - Product A is made from components B and C. Item B,...Ch. 11 - Refer to Figure 11.23 and Solved Problem 1. If...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - Figure 11.38 shows a partially completed inventory...Ch. 11 - A partially completed inventory record for the...Ch. 11 - The BOM for product A is shown in Figure 11.40,...Ch. 11 - The BOMs for products A & B and data from the...Ch. 11 - Figure 11.42 illustrates the BOM for product A....Ch. 11 - The following information is available for three...Ch. 11 - Figure 11.44 shows the BOMs for two products, A...Ch. 11 - The BOM for product A is shown in Figure 11.45....Ch. 11 - Refer to Solved Problem 1 (Figure 11.23) for the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The McDuff Credit Union advertises their ability...Ch. 11 - Suppose that the POQ for item B is changed from 3...Ch. 11 - As the on-hand inventory for item C increases from...Ch. 11 - As the fixed order quantity (FOQ) for item D...Ch. 11 - As the lead time for item C changes, what happens...

Additional Business Textbook Solutions

Find more solutions based on key concepts
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY