
Concept explainers
Compute the total cost for each aggregate plan using these unit costs:
Regular output = $40
Overtime = $50
Subcontract = $60
Average Balance Inventory = $10
a.
b.
c. (Refer to part b) After complaints from some workers about working overtime every month during the first half of the year, the manager is now considering adding some temporary workers for the second half of the year, which would increase regular output to a steady 350 units a month, not using any overtime, and using subcontracting to make up needed output. Determine the total cost of that plan.
a)

To compute: The total cost for each aggregate plan
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Answer to Problem 1P
Explanation of Solution
Given information:
Regular output is $40, overtime is $50, subcontract is $60, and average balance inventory is $10.
In addition to this, the following information is given:
Month | January | February | March | April | May | June |
Forecast | 300 | 320 | 320 | 340 | 320 | 320 |
Regular | 300 | 300 | 300 | 300 | 300 | 300 |
Overtime | 20 | 20 | 20 | 20 | 20 | 20 |
Subcontract | 0 | 0 | 0 | 0 | 0 | 0 |
Determine the aggregate plan to compute total cost:
Month | January | February | March | April | May | June | Total | |
Forecast | 300 | 320 | 320 | 340 | 320 | 320 | 1,920 | |
Output | ||||||||
Regular | 300 | 300 | 300 | 300 | 300 | 300 | 1,800 | |
Part-time | ||||||||
Overtime | 20 | 20 | 20 | 20 | 20 | 20 | 120 | |
Subcontract | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Difference | 20 | 0 | 0 | -20 | 0 | 0 | 0 | |
Inventory | ||||||||
Beginning | 0 | 20 | 20 | 20 | 0 | 0 | 60 | |
Ending | 20 | 20 | 20 | 0 | 0 | 0 | 60 | |
Average | 10 | 20 | 20 | 10 | 0 | 0 | 60 | |
Backlog | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Costs | ||||||||
Regular | 40 | $12,000 | $12,000 | $12,000 | $12,000 | $12,000 | $12,000 | $72,000 |
Part-time | ||||||||
Overtime | 50 | $1,000 | $1,000 | $1,000 | $1,000 | $1,000 | $1,000 | $6,000 |
Subcontract | 60 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
Hire/Layoff | ||||||||
Inventory | 10 | $100 | $200 | $200 | $100 | $0 | $0 | $600 |
Backorders | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
$13,100 | $13,200 | $13,200 | $13,100 | $13,000 | $13,000 | $78,600 |
Supporting calculation:
Forecast, regular time units, overtime, and subcontract units were given.
Calculate the difference of month January:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 20 units.
Difference=Output−Forecast=(Regular+Overtime+Subcontract)−Forecast=(300+20+0)−300=20
Calculate the difference of month February:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 0 units.
Difference=Output−Forecast=(Regular+Overtime+Subcontract)−Forecast=(300+20+0)−320=0
Calculate the difference of month March:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 0 units.
Difference=Output−Forecast=(Regular+Overtime+Subcontract)−Forecast=(300+20+0)−320=0
Note: The calculation repeats for all the months.
Beginning inventory:
The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.
Ending inventory for the month of January:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.
Ending inventory=[Beginning inventory of January+Difference between output and forecast]=0+20=20
Ending inventory for the month of February:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.
Ending inventory=[Beginning inventory of February+Difference between output and forecast]=20+0=20
Ending inventory for the month of March:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.
Ending inventory=Beginning inventory of March+Difference between output and forecast=20+0=20
Note: The calculation repeats for all the months.
Average inventory for the month of January:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 10 units.
Average inventory=Beginning inventory+Ending inventory2=0+202=10
Average inventory for the month of February:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 20 units.
Average inventory=Beginning inventory+Ending inventory2=20+202=20
Average inventory for the month of March:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 20 units.
Average inventory=Beginning inventory+Ending inventory2=20+202=20
Note: The calculation repeats for all the months.
Calculate the regular time cost for the month of January:
Regular time cost per unit is given as $40 and regular time unit is given as 300. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $12,000.
Regular time cost=Regular time cost per unit×Regular time units=$40×300=$12,000
Calculate the regular time cost for the month of February:
Regular time cost per unit is given as $40 and regular time unit is given as 300. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $12,000.
Regular time cost=Regular time cost per unit×Regular time units=$40×300=$12,000
Calculate the regular time cost for the month of March:
Regular time cost per unit is given as $40 and regular time unit is given as 300. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $12,000.
Regular time cost=Regular time cost per unit×Regular time units=$40×300=$12,000
Note: The calculation repeats for all the months.
Calculate the total regular time cost:
It is calculated by adding the regular time cost of all the months.
Total regular time cost=Regular time of all the months=$12,000+$12,000+$12,000+$12,000+$12,000+$12,000=$72,000
Hence, the total regular time cost is $72,000.
Calculate the overtime cost for the month of January:
Overtime cost per unit is given as $50 and overtime unit is given as 20. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $1,000.
Overtime cost=Overtime cost per unit×Overtime units=$50×20=$1,000
Calculate the overtime cost for the month of February:
Overtime cost per unit is given as $50 and overtime unit is given as 20. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $1,000.
Overtime cost=Overtime cost per unit×Overtime units=$50×20=$1,000
Calculate the overtime cost for the month of March:
Overtime cost per unit is given as $50 and overtime unit is given as 20. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $1,000.
Overtime cost=Overtime cost per unit×Overtime units=$50×20=$1,000
Note: The calculation repeats for all the months.
Calculate the total overtime cost:
It is calculated by adding the overtime cost of all the months.
Total overtime cost=Overtime of all the months=$1,000+$1,000+$1,000+$1,000+$1,000+$1,000=$6,000
Hence, the total overtime cost is $6,000.
Calculate the subcontract cost for the month of January:
Subcontract cost per unit is given as $60 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Subcontract cost=Subcontract cost per unit×Subcontract units=$60×0=$0
Calculate the subcontract cost for the month of February:
Subcontract cost per unit is given as $60 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Subcontract cost=Subcontract cost per unit×Subcontract units=$60×0=$0
Calculate the subcontract cost for the month of March:
Subcontract cost per unit is given as $60 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Subcontract cost=Subcontract cost per unit×Subcontract units=$60×0=$0
Note: The calculation repeats for all the months.
Calculate the total subcontract cost:
It is calculated by adding the subcontract cost of all the months.
Total subcontract cost=Subcontract of all the months=$0+$0+$0+$0+$0+$0=$0
Hence, the total subcontract cost is $0.
Calculate the inventory cost for the month of January:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $100.
Inventory cost=Inventory cost per unit×Average inventory=$10×10=$100
Calculate the inventory cost for the month of February:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $200.
Inventory cost=Inventory cost per unit×Average inventory=$10×20=$200
Calculate the inventory cost for the month of March:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $200.
Inventory cost=Inventory cost per unit×Average inventory=$10×20=$200
Note: The calculation repeats for all the months.
Calculate the total inventory cost:
It is calculated by adding the inventory cost of all the months.
Total inventory cost=Inventory cost of all the months=$100+$200+$200+$100+$0+$0=$600
Hence, the total inventory cost is $600.
Calculate the total cost of the plan:
It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.
Total cost of the plan=(Total regular time cost+Total overtime cost+Total subcontract cost+Total inventory cost)=$72,000+$6,000+$0+$600=$78,600
Hence, the total cost of the plan is $78,600.
b)

To compute: The total cost for each aggregate plan.
Introduction:The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Answer to Problem 1P
Explanation of Solution
Given information:
Regular output is $40, overtime is $50, subcontract is $60, and average balance inventory is $10.
In addition to this, the following information is given:
Month | July | August | September | October | November | December |
Forecast | 320 | 340 | 360 | 380 | 400 | 400 |
Regular | 300 | 300 | 300 | 300 | 300 | 300 |
Overtime | 20 | 20 | 20 | 20 | 30 | 30 |
Subcontract | 20 | 30 | 40 | 40 | 60 | 70 |
Determine the aggregate plan to compute total cost:
Month | July | August | September | October | November | December | Total | |
Forecast | 320 | 340 | 360 | 380 | 400 | 400 | 2,200 | |
Output | ||||||||
Regular | 300 | 300 | 300 | 300 | 300 | 300 | 1,800 | |
Part-time | ||||||||
Overtime | 20 | 20 | 20 | 20 | 30 | 30 | 140 | |
Subcontract | 20 | 30 | 40 | 40 | 60 | 70 | 260 | |
Difference | 20 | 10 | 0 | -20 | -10 | 0 | 0 | |
Inventory | ||||||||
Beginning | 0 | 20 | 30 | 30 | 10 | 0 | 90 | |
Ending | 20 | 30 | 30 | 10 | 0 | 0 | 90 | |
Average | 10 | 25 | 30 | 20 | 5 | 0 | 90 | |
Backlog | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Costs | ||||||||
Regular | 40 | $12,000 | $12,000 | $12,000 | $12,000 | $12,000 | $12,000 | $72,000 |
Part-time | ||||||||
Overtime | 50 | $1,000 | $1,000 | $1,000 | $1,000 | $1,500 | $1,500 | $7,000 |
Subcontract | 60 | $1,200 | $1,800 | $2,400 | $2,400 | $3,600 | $4,200 | $15,600 |
Hire/Layoff | ||||||||
Inventory | 10 | $100 | $250 | $300 | $200 | $50 | $0 | $900 |
Backorders | ||||||||
$14,300 | $15,050 | $15,700 | $15,600 | $17,150 | $17,700 | $95,500 |
Supporting calculation:
Forecast, regular time units, overtime, and subcontract units were given.
Calculate the difference of month July:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 20 units.
Difference=Output−Forecast=(Regular+Overtime+Subcontract)−Forecast=(300+20+20)−320=20
Calculate the difference of month August:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 10 units.
Difference=Output−Forecast=(Regular+Overtime+Subcontract)−Forecast=(300+20+30)−340=10
Calculate the difference of month September:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 0 units.
Difference=Output−Forecast=(Regular+Overtime+Subcontract)−Forecast=(300+20+40)−360=0
Note: The calculation repeats for all the months.
Beginning inventory:
The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.
Ending inventory for the month of July:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.
Ending inventory=Beginning inventory of July+Difference between output and forecast=0+20=20
Ending inventory for the month of August:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.
Ending inventory=Beginning inventory of August+Difference between output and forecast=20+10=30
Ending inventory for the month of September:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.
Ending inventory=Beginning inventory of September+Difference between output and forecast=30+0=30
Note: The calculation repeats for all the months.
Average inventory for the month of July:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 10 units.
Average inventory=Beginning inventory+Ending inventory2=0+202=10
Average inventory for the month of August:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 25 units.
Average inventory=Beginning inventory+Ending inventory2=20+302=25
Average inventory for the month of September:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 30 units.
Average inventory=Beginning inventory+Ending inventory2=30+302=30
Note: The calculation repeats for all the months.
Calculate the regular time cost for the month of July:
Regular time cost per unit is given as $40 and regular time unit is given as 300. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $12,000.
Regular time cost=Regular time cost per unit×Regular time units=$40×300=$12,000
Calculate the regular time cost for the month of August:
Regular time cost per unit is given as $40 and regular time unit is given as 300. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $12,000.
Regular time cost=Regular time cost per unit×Regular time units=$40×300=$12,000
Calculate the regular time cost for the month of September:
Regular time cost per unit is given as $40 and regular time unit is given as 300. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $12,000.
Regular time cost=Regular time cost per unit×Regular time units=$40×300=$12,000
Note: The calculation repeats for all the months.
Calculate the total regular time cost:
It is calculated by adding the regular time cost of all the months.
Total regular time cost=Regular time of all the months=$12,000+$12,000+$12,000+$12,000+$12,000+$12,000=$72,000
Hence, the total regular time cost is $72,000.
Calculate the overtime cost for the month of July:
Overtime cost per unit is given as $50 and overtime unit is given as 20. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $1,000.
Overtime cost=Overtime cost per unit×Overtime units=$50×20=$1,000
Calculate the overtime cost for the month of August:
Overtime cost per unit is given as $50 and overtime unit is given as 20. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $1,000.
Overtime cost=Overtime cost per unit×Overtime units=$50×20=$1,000
Calculate the overtime cost for the month of September:
Overtime cost per unit is given as $50 and overtime unit is given as 20. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $1,000.
Overtime cost=Overtime cost per unit×Overtime units=$50×20=$1,000
Note: The calculation repeats for all the months.
Calculate the total overtime cost:
It is calculated by adding the overtime cost of all the months.
Total overtime cost=Overtime of all the months=$1,000+$1,000+$1,000+$1,000+$1,000+$1,000=$6,000
Hence, the total overtime cost is $6,000.
Calculate the subcontract cost for the month of July:
Subcontract cost per unit is given as $60 and subcontract unit is given as 20. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $1,200.
Subcontract cost=Subcontract cost per unit×Subcontract units=$60×20=$1,200
Calculate the subcontract cost for the month of August:
Subcontract cost per unit is given as $60 and subcontract unit is given as 30. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $1,800.
Subcontract cost=Subcontract cost per unit×Subcontract units=$60×30=$1,800
Calculate the subcontract cost for the month of September:
Subcontract cost per unit is given as $60 and subcontract unit is given as 40. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $2,400.
Subcontract cost=Subcontract cost per unit×Subcontract units=$60×40=$2,400
Note: The calculation repeats for all the months.
Calculate the total subcontract cost:
It is calculated by adding the subcontract cost of all the months.
Total subcontract cost=Subcontract of all the months=$1,200+$1,800+$2,400+$2,400+$3,600+$4,200=$15,600
Hence, the total subcontract cost is $15,600.
Calculate the inventory cost for the month of July:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $100.
Inventory cost=Inventory cost per unit×Average inventory=$10×10=$100
Calculate the inventory cost for the month of August:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $250.
Inventory cost=Inventory cost per unit×Average inventory=$10×25=$250
Calculate the inventory cost for the month of September:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $300.
Inventory cost=Inventory cost per unit×Average inventory=$10×30=$300
Note: The calculation repeats for all the months.
Calculate the total inventory cost:
It is calculated by adding the inventory cost of all the months.
Total inventory cost=Inventory cost of all the months=$100+$250+$300+$200+$50+$0=$900
Hence, the total inventory cost is $900.
Calculate the total cost of the plan:
It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.
Total cost of the plan=(Total regular time cost+Total overtime cost+Total subcontract cost+Total inventory cost)=$72,000+$6,000+$15,600+$900=$95,500
Hence, the total cost of the plan is $95,500.
c)

To compute: The total cost for each aggregate plan.
Introduction:The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Answer to Problem 1P
Explanation of Solution
Given information:
Regular output is $40, overtime is $50, subcontract is $60, and average balance inventory is $10.
In addition to this, the following information is given:
Month | July | August | September | October | November | December |
Forecast | 320 | 340 | 360 | 380 | 400 | 400 |
Regular | 350 | 350 | 350 | 350 | 350 | 350 |
Overtime | 0 | 0 | 0 | 0 | 0 | 0 |
It is given that subcontract can be used whenever necessary.
Determine the aggregate plan to compute total cost:
Month | July | August | September | October | November | December | Total | |
Forecast | 320 | 340 | 360 | 380 | 400 | 400 | 2,200 | |
Output | ||||||||
Regular | 350 | 350 | 350 | 350 | 350 | 350 | 2,100 | |
Part-time | ||||||||
Overtime | ||||||||
Subcontract | 50 | 50 | ||||||
Difference | 30 | 10 | -10 | -30 | 0 | 0 | 0 | |
Inventory | ||||||||
Beginning | 0 | 30 | 40 | 30 | 0 | 0 | 100 | |
Ending | 30 | 40 | 30 | 0 | 0 | 0 | 100 | |
Average | 15 | 35 | 35 | 15 | 0 | 0 | 100 | |
Backlog | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Costs | ||||||||
Regular | 40 | $14,000 | $14,000 | $14,000 | $14,000 | $14,000 | $14,000 | $84,000 |
Part-time | ||||||||
Overtime | 50 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
Subcontract | 60 | $0 | $0 | $0 | $0 | $3,000 | $3,000 | $6,000 |
Hire/Layoff | ||||||||
Inventory | 10 | $150 | $350 | $350 | $150 | $0 | $0 | $1,000 |
Backorders | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
$14,150 | $14,350 | $14,350 | $14,150 | $17,000 | $17,000 | $91,000 |
Supporting calculation:
Forecast, regular time units, overtime, and subcontract units were given.
Calculate the difference of month July:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 30 units.
Difference=Output−Forecast=(Regular+Overtime+Subcontract)−Forecast=(350+0+0)−320=30
Calculate the difference of month August:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 10 units.
Difference=Output−Forecast=(Regular+Overtime+Subcontract)−Forecast=(350+0+0)−340=10
Calculate the difference of month September:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is -10 units.
Difference=Output−Forecast=(Regular+Overtime+Subcontract)−Forecast=(350+0+0)−360=−10
Note: The calculation repeats for all the months.
Beginning inventory:
The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.
Ending inventory for the month of July:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 30 units.
Ending inventory=Beginning inventory of July+Difference between output and forecast=0+30=30
Ending inventory for the month of August:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 40 units.
Ending inventory=Beginning inventory of August+Difference between output and forecast=30+10=40
Ending inventory for the month of September:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.
Ending inventory=Beginning inventory of September+Difference between output and forecast=40+(−10)=30
Note: The calculation repeats for all the months.
Average inventory for the month of July:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 15 units.
Average inventory=Beginning inventory+Ending inventory2=0+302=15
Average inventory for the month of August:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 35 units.
Average inventory=Beginning inventory+Ending inventory2=30+402=35
Average inventory for the month of September:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 35 units.
Average inventory=Beginning inventory+Ending inventory2=40+302=35
Note: The calculation repeats for all the months.
Calculate the regular time cost for the month of July:
Regular time cost per unit is given as $40 and regular time unit is given as 350. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $14,000.
Regular time cost=Regular time cost per unit×Regular time units=$40×350=$14,000
Calculate the regular time cost for the month of August:
Regular time cost per unit is given as $40 and regular time unit is given as 350. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $14,000.
Regular time cost=Regular time cost per unit×Regular time units=$40×350=$14,000
Calculate the regular time cost for the month of September:
Regular time cost per unit is given as $40 and regular time unit is given as 350. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $14,000.
Regular time cost=Regular time cost per unit×Regular time units=$40×350=$14,000
Note: The calculation repeats for all the months.
Calculate the total regular time cost:
It is calculated by adding the regular time cost of all the months.
Total regular time cost=Regular time of all the months=$14,000+$14,000+$14,000+$14,000+$14,000+$14,000=$84,000
Hence, the total regular time cost is $84,000.
Calculate the overtime cost for the month of July:
Overtime cost per unit is given as $50 and overtime unit is given as 0. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $0.
Overtime cost=Overtime cost per unit×Overtime units=$50×20=$0
Calculate the overtime cost for the month of August:
Overtime cost per unit is given as $50 and overtime unit is given as 0. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $0.
Overtime cost=Overtime cost per unit×Overtime units=$50×20=$0
Calculate the overtime cost for the month of September:
Overtime cost per unit is given as $50 and overtime unit is given as 0. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $0.
Overtime cost=Overtime cost per unit×Overtime units=$50×20=$0
Note: The calculation repeats for all the months.
Calculate the total overtime cost:
It is calculated by adding the overtime cost of all the months.
Total overtime cost=Overtime of all the months=$0+$0+$0+$0+$0+$0=$0
Hence, the total overtime cost is $0.
Calculate the subcontract cost for the month of July:
Subcontract cost per unit is given as $60 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Subcontract cost=Subcontract cost per unit×Subcontract units=$60×0=$0
Calculate the subcontract cost for the month of August:
Subcontract cost per unit is given as $60 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Subcontract cost=Subcontract cost per unit×Subcontract units=$60×0=$0
Calculate the subcontract cost for the month of September:
Subcontract cost per unit is given as $60 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Subcontract cost=Subcontract cost per unit×Subcontract units=$60×0=$0
Note: The calculation repeats for all the months. As there are backlogs in the month of November and December, there would be 50 units of subcontracting in those months.
Calculate the total subcontract cost:
It is calculated by adding the subcontract cost of all the months.
Total subcontract cost=Subcontract of all the months=$0+$0+$0+$0+$3,000+$3,000=$6,000
Hence, the total subcontract cost is $15,600.
Calculate the inventory cost for the month of July:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $150.
Inventory cost=Inventory cost per unit×Average inventory=$10×15=$150
Calculate the inventory cost for the month of August:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $350.
Inventory cost=Inventory cost per unit×Average inventory=$10×35=$350
Calculate the inventory cost for the month of September:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $350.
Inventory cost=Inventory cost per unit×Average inventory=$10×35=$350
Note: The calculation repeats for all the months.
Calculate the total inventory cost:
It is calculated by adding the inventory cost of all the months.
Total inventory cost=Inventory cost of all the months=$150+$350+$350+$150+$50+$0=$1,000
Hence, the total inventory cost is $1,000.
Calculate the total cost of the plan:
It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.
Total cost of the plan=(Total regular time cost+Total overtime cost+Total subcontract cost+Total inventory cost)=$84,000+$0+$6,000+$1,000=$91,000
Hence, the total cost of the plan is $91,000.
Want to see more full solutions like this?
Chapter 11 Solutions
OPERATIONS MANAGEMENT W/ CNCT+
- Communication Tips (2015) Tactful bragging Respond to the question "So, what do you do?" Whether you are student or have a job/internship, how can you tactfully brag in your answer to this question? Use the three elements from the video (listed below) when crafting your brag statement: Focus on results vs title Process vs job description Loop back to listener Example of an instructor's brag statement: "I help hundreds of students each semester to connect with one another, develop communication skills and prepare for upcoming interviews. Through improv games we explore presence, flexibility, and storytelling. How have your networking experiences on campus been so far?"arrow_forwardAccounting problemarrow_forwardGovernment's new plan to shift cargo from roads back to rail 26TH JANUARY 2024 Government is seeking to finalise a plan aimed at improving its rail network and move cargo away from a billion rand per day to its logistics crises, government has said an urgentturnaround is needed to improve its 31 000km locomotive network as more and more cargo moves from rail to trucks. The Department of Transport (DoT) hosted a discussion with industry stakeholders regarding the Freight Road to Rail Migration Plan on Thursday - the latest development in the wake of President Cyril Ramphosa forming the National Logistics Crisis Committee last year. Transnet, the South African National Roads Agency (Sanral) and private sector companies were all in attendance. The Freight Road to Rail Migration Plan is part of government's strategies to improve the country's ongoing logistics crises. In October last year, the government unveiled its Freight Logistics Roadmap to improve the ports and rail networks and…arrow_forward
- Assess what led to such logistical inefficiencies / collapse of a previously world class freight networkarrow_forwardWhich of the following statements concerning the evaluation of training programs is true? Most companies thoroughly evaluate the return on investment of their training programs It is relatively easy to establish a control group and a treatment group for evaluation Results level of evaluation measures how well participants liked the program Behavior level criteria measure whether skills learned in training result in behavior changes back on the jobarrow_forwardEligibility testing is an disparate impact validation method none of the above a method to validate promotions and progressive discipline activity a test an employee administers to ensure that the potential employee is capable and qualified to perform the requirements of the positionarrow_forward
- A no-strike pledge by a union in a collective bargaining agreement is given in return for management’s agreement to: a grievance procedure a union shop a wage increase a fringe benefit increase binding arbitration of grievancesarrow_forwardWhich is the major OD technique that is used for increasing the communication, cooperation, and cohesiveness of work units? Leadership analysis Developing objectives Groupthink Strategic Planning team Buildingarrow_forwardAn American multinational firm usually is less than fully successful in adapting itself to local practices in each country because: American managers are often ignorant of local conditions None of the above management direction may be centralized in the home office All of the above Foreign subsidiaries often have American managersarrow_forward
- When salary increases are based on inputs, or performance, companies are following: agency theory equality theory equity theory compliance theory need theoryarrow_forwardThe most frequently used techniques for measuring job satisfaction involves Direct observation Questionnaires Interviews Psychological testsarrow_forwardWhich of the following is not an advantage of on-the-job training? Transfer is less difficult Transfer is less difficult The training is inexpensive Any organizational member can be the trainer without preparation It is relatively easy to use this methodarrow_forward
- MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPractical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning

