Interpretation: A network diagram depicting the work flow of the project is to be drawn.
Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the work flow and is used to compute the total duration of the project.
B.
Interpretation: The critical path is to be identified by computing the earliest and the latest start and finish times.
Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the work flow and is used to compute the total duration of the project.
C.
Interpretation: A Gantt chart of the
Concept Introduction:Gantt chart is a project management tool that is a type of bar chart. It depicts the project schedule and is used for resource allocation.
D.
Interpretation: The group of activities that have to be completed by day 60 so as to ensure that the project will be completed without any delay is to be identified.
Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the workflow and is used to compute the total duration of the project.
![Check Mark](/static/check-mark.png)
Want to see the full answer?
Check out a sample textbook solution![Blurred answer](/static/blurred-answer.jpg)
Chapter 10 Solutions
Production and Operations Analysis, Seventh Edition
- Suppose you are the project manager for the following project: First, draw a network diagram for the project. Determine the critical path and slack times for all of the tasks. This completes your plan for the project schedule. During project execution, you become aware of the need to change the duration of Task 4 to five days. Meanwhile, Task 3 has been finished one day early, so it only took one day to do. What, if any, effects do these changes have on your project? What would have happened if you had not been monitoring the status of the project?arrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Dave's earliest start (ES) and earliest finish (EF) are: Dave's latest start (LS) and latest finish (LF) are: Activity A B C D Time (weeks) 7 6 2 2 Immediate Predecessor(s) A A Activity A C D F G H Activity H Time Activity (weeks) E 4 F 6 G 10 H 6 ES 0 0 7 7 6 6 10 12 LS 14 EF 7 9 1228 10 20 LF Immediate Predecessor(s) B B C, E D, F 27arrow_forwardThe following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Duration (weeks) Precedes B, C F E F This exercise contains only parts b, c, and d. b) The activities on the critical path are c) The total project completion time for Rafay Ishfaq's software firm is d) Determine the slack time for each of the activities. (Enter your responses as whole numbers.) Activity A (start) BOE C F (end) weeks. (Enter your response as a whole number.) Activity A B ош 2 9 2 6 3 F Slack Time (weeks) What is the total slack for the non critical path(s) in the project? week(s) (Enter your response as a whole number.)arrow_forward
- A project's activities must be completed in the sequence indicated below. Activity Immediately Preceding Activity Duration in Weeks A - 3 B - 20 C - 15 D - 10 E - 5 F A 4 G D 3 H D, E 10 I F 3 J B 10 K G, H 7 L B, I 5 The project ends with the intersection of activities: C, J, K and L 1- Use CPM to construct (Draw) the project Network and find the critical path. 2- How long is the project expected to takearrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Dave's earliest start (ES) and earliest finish (EF) are: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A B C D 7 2 A Activity A F G H ES | FF 5 6 9 7 B B C. E D, Farrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Dave's earliest start (ES) and earliest finish (EF) are: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A B C D 7 6 3 2 A A Activity A ES EFGH EF 7 3 6 11 6 B B C, E D, Farrow_forward
- In a project network, the critical path is the sequence of activities which has the Multiple Choice greatest variance. longest duration. most events. most activities.arrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Time Activity (weeks) Dave's earliest start (ES) and earliest finish (EF) are: Dave's latest start (LS) and latest finish (LF) are: The slack times are: The activities on the critical path are The total project completion time for Dave = weeks. ▼ Time Immediate Activity (weeks) Predecessor(s) A 6 8 3 3 B C D A A Activity A B C D E F G H Activity H G F E D C B A Activity A B C D E F G H | E F 6 G ES □ 0 H 8 T П LS 15 14 8 9 12 11 0 5 Slack || EF 6 13 22 23 5 7 9 8 LF | | L | | Immediate Predecessor(s) B B C, E D,Farrow_forwardA project schedule has the following characteristics: explain all the step to construct the network and find critical patharrow_forward
- A project consists of the activities in the following table. Times are given in weeks Draw the network diagram Calculate the ES, EF, LS, LF, and slack for each activity What is this project completion time?arrow_forwardWhen developing a schedule network diagram, the project manager must take into account the dependencies between activities as well as the start and finish relationships between activities. List and describe the four types of schedule activity relationships List and describe the four types of schedule activity dependencies Include examples of each item above, that do not come from the PMBOK.arrow_forwardA project consists of eight activities. The activity completion times and the precedence relationships are as follows: Activity Completion Immediate predecessor activities time (weeks) A 50 70 C 60 D 30 A E 40 B,C F 20 G 60 A.D E,F H 50 I G,H Draw the project network diagram using the Activity-On-Node (AON) method for this project and calculate the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and Slack (SL) for each activity.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)