Concept explainers
A.
Interpretation: A network diagram representing the activities of the project is to be constructed.
Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the work flow and is used to compute the total duration of the project.
A.
Explanation of Solution
Given information: Theactivities to be taken up for the construction of a gas station and the time duration for each are given in the table.
Activity | Time |
A | 4 |
B | 2 |
C | 3 |
D | 1 |
E | 1 |
F | 2 |
G | 3 |
H | 1 |
I | 5 |
J | 3 |
K | 4 |
L | 2 |
M | 1 |
The activity times and the precedence relationship are shown in the table:
Activity | Time | Predecessors |
A | 4 | |
B | 2 | A |
C | 3 | B |
D | 1 | C |
E | 1 | D |
F | 2 | B |
G | 3 | F |
H | 1 | G |
I | 5 | B |
J | 3 | I |
K | 4 | C, F, I |
L | 2 | K |
M | 1 | L |
The network diagram showing the work flows is as follows:
B.
Interpretation: The critical path is to be identified by computing the earliest and the latest start and finish times.
Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the work flow and is used to compute the total duration of the project.
B.
Answer to Problem 26AP
The critical path is A − B − I − K − L − M with completion time as 18 weeks
Explanation of Solution
Given information:
Activity | Time |
A | 4 |
B | 2 |
C | 3 |
D | 1 |
E | 1 |
F | 2 |
G | 3 |
H | 1 |
I | 5 |
J | 3 |
K | 4 |
L | 2 |
M | 1 |
The earliest and latest start and finish times are calculated using the formulae:
Earliest Start (EST) = Maximum EFT of the predecessor activity
Latest Start (LST) = LFT - Duration
Earliest Finish (EFT) = EST + Duration
Latest Finish (LFT) = Minimum LST of the immediate successor
Slack = LFT − EFT (or) LST − EST
Activity | Time | EST | EFT | LST | LFT | Slack |
A | 4 | 0 | 4 | 0 | 4 | 0 |
B | 2 | 4 | 6 | 4 | 6 | 0 |
C | 3 | 6 | 9 | 8 | 11 | 2 |
D | 1 | 9 | 10 | 16 | 17 | 7 |
E | 1 | 10 | 11 | 17 | 18 | 7 |
F | 2 | 6 | 8 | 9 | 11 | 3 |
G | 3 | 8 | 11 | 14 | 17 | 6 |
H | 1 | 11 | 12 | 17 | 18 | 6 |
I | 5 | 6 | 11 | 6 | 11 | 0 |
J | 3 | 11 | 14 | 15 | 18 | 4 |
K | 4 | 11 | 15 | 11 | 15 | 0 |
L | 2 | 15 | 17 | 15 | 17 | 0 |
M | 1 | 17 | 18 | 17 | 18 | 0 |
The critical path includes the activities with zero slack. So, here the critical path is A − B− I − K − L − M. The total time taken to complete the project is 18 weeks.
C.
Interpretation: A Gantt chart of the
Concept Introduction: Gantt chart is a project management tool that is a type of bar chart. It depicts the project schedule and is used for resource allocation.
C.
Answer to Problem 26AP
A Gantt chart for the project has been drawn.
Explanation of Solution
Given information:
Activity | Time |
A | 4 |
B | 2 |
C | 3 |
D | 1 |
E | 1 |
F | 2 |
G | 3 |
H | 1 |
I | 5 |
J | 3 |
K | 4 |
L | 2 |
M | 1 |
Activity times and early start times:
Activity | EST | Time |
A | 0 | 4 |
B | 4 | 2 |
C | 6 | 3 |
D | 9 | 1 |
E | 10 | 1 |
F | 6 | 2 |
G | 8 | 3 |
H | 11 | 1 |
I | 6 | 5 |
J | 11 | 3 |
K | 11 | 4 |
L | 15 | 2 |
M | 17 | 1 |
The Gantt chart depicting the project based on the EST:
D.
Interpretation: The impact of replacement of the air compressor which takes two weeks on the completion of the project is to be determined.
Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the work flow and is used to compute the total duration of the project.
D.
Explanation of Solution
Given information:
Activity | Time |
A | 4 |
B | 2 |
C | 3 |
D | 1 |
E | 1 |
F | 2 |
G | 3 |
H | 1 |
I | 5 |
J | 3 |
K | 4 |
L | 2 |
M | 1 |
Installing the air compressor is represented by activity G.
Activity | Time | EST | EFT | LST | LFT | Slack |
A | 4 | 0 | 4 | 0 | 4 | 0 |
B | 2 | 4 | 6 | 4 | 6 | 0 |
C | 3 | 6 | 9 | 8 | 11 | 2 |
D | 1 | 9 | 10 | 16 | 17 | 7 |
E | 1 | 10 | 11 | 17 | 18 | 7 |
F | 2 | 6 | 8 | 9 | 11 | 3 |
G | 3 | 8 | 11 | 14 | 17 | 6 |
H | 1 | 11 | 12 | 17 | 18 | 6 |
I | 5 | 6 | 11 | 6 | 11 | 0 |
J | 3 | 11 | 14 | 15 | 18 | 4 |
K | 4 | 11 | 15 | 11 | 15 | 0 |
L | 2 | 15 | 17 | 15 | 17 | 0 |
M | 1 | 17 | 18 | 17 | 18 | 0 |
The latest start time of the activity G is 14th week. If the failure is identified before installation, the project will not be delayed as the replacement time (2 weeks) is less than the slack (6 weeks).
If the failure is found during testing of the air compressor, represented by activity H, still the project would not be delayed, as again there is a slack of 6 weeks.
E.
Interpretation: The activities that can be completed by the end of the 15th week without delaying the project completion are to be determined.
Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the work flow and is used to compute the total duration of the project.
E.
Answer to Problem 26AP
The activities A, B, C, F and I have to be completed by the end of the 15th week to guarantee project completion without delay.
Explanation of Solution
Given information:
Activity | Time |
A | 4 |
B | 2 |
C | 3 |
D | 1 |
E | 1 |
F | 2 |
G | 3 |
H | 1 |
I | 5 |
J | 3 |
K | 4 |
L | 2 |
M | 1 |
The table shows the Earliest and Latest times of the activities
Activity | Time | EST | EFT | LST | LFT | Slack |
A | 4 | 0 | 4 | 0 | 4 | 0 |
B | 2 | 4 | 6 | 4 | 6 | 0 |
C | 3 | 6 | 9 | 8 | 11 | 2 |
D | 1 | 9 | 10 | 16 | 17 | 7 |
E | 1 | 10 | 11 | 17 | 18 | 7 |
F | 2 | 6 | 8 | 9 | 11 | 3 |
G | 3 | 8 | 11 | 14 | 17 | 6 |
H | 1 | 11 | 12 | 17 | 18 | 6 |
I | 5 | 6 | 11 | 6 | 11 | 0 |
J | 3 | 11 | 14 | 15 | 18 | 4 |
K | 4 | 11 | 15 | 11 | 15 | 0 |
L | 2 | 15 | 17 | 15 | 17 | 0 |
M | 1 | 17 | 18 | 17 | 18 | 0 |
The latest finish times of the activities A, B, C, F and Iam less than 15 weeks. Therefore, these activities have to be completed by the end of the 15th weeks to guarantee project completion without any delay.
F.
Interpretation: The optimal solution for the problem is to be determined using linear programming.
Concept Introduction: Linear programming is a mathematical technique used to achieve the best outcome, given a list of parameters usually restrictions on the resources.
F.
Answer to Problem 26AP
The optimal solution for the problem is obtained using linear programming.
Explanation of Solution
Given information:
Activity | Time |
A | 4 |
B | 2 |
C | 3 |
D | 1 |
E | 1 |
F | 2 |
G | 3 |
H | 1 |
I | 5 |
J | 3 |
K | 4 |
L | 2 |
M | 1 |
The various paths of the project and the durations are:
The critical path is A − B − I − K − L − M with the completion time of 18 weeks.
Using linear programming, the EST is calculated.
Objective function = =SUM (B2:M2)
Nodes | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
EST |
The constraints
Activity | Time | ||
A | 0 | > | 4 |
B | 0 | > | 2 |
C | 0 | > | 3 |
D | 0 | > | 1 |
E | 0 | > | 1 |
F | 0 | > | 2 |
G | 0 | > | 3 |
H | 0 | > | 1 |
I | 0 | > | 5 |
J | 0 | > | 3 |
K | 0 | > | 4 |
L | 0 | > | 2 |
M | 0 | > | 1 |
P1 | 0 | > | 0 |
P2 | 0 | > | 0 |
P3 | 0 | > | 0 |
Solver Solution:
Objective Function |
120 |
EST for the nodes:
Nodes | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
EST | 0 | 4 | 6 | 9 | 8 | 11 | 11 | 11 | 10 | 15 | 17 | 18 |
Want to see more full solutions like this?
Chapter 10 Solutions
Production and Operations Analysis, Seventh Edition
- Information Security Innovation within a Contemporary Business Environment All organisations using computers need to consider the security of information they keep. Many organisations utilise Websites for their core business functions and this results in monetary transactions being carried out on the Websites.arrow_forwardPlease help with a complete research report on the topic below: "Information Security Innovation within a Contemporary Business Environment " The format of the report should follow this below.arrow_forward7. Wireless Infrastructure in the Cloud Wireless devices have changed the way organisations and their customers interact. Wireless enabled devices have driven the mindset that wireless networks must be ubiquitous, fast, and constantly available. These are demands that have traditionally put organisations and their user communities in direct conflict with their IT departments, as constructing and maintaining wireless infrastructures are typically time-consuming, complex, and costly endeavours.arrow_forward
- IM.54 A growing online retailer sells thousands of items yet has has one specialty product category with just 30 items. They want to classify these thirty items according to the annual dollar volume (revenue) generated by each item. The table below lists each item number, Annual Sales (in units), and Price per unit: Item # Annual Sales Price 1 221 $25.85 2 446 $14.15 3 8,940 $168.19 4 2,965 $15.99 5 1,322 $29.37 6 2,575 $12.77 7 767 $28.43 8 5,803 $163.01 9 2,673 $20.51 10 642 $14.71 11 4,168 $54.53 12 1,881 $22.55 13 2,417 $29.63 14 5,207 $36.41 15 1,381 $20.55 16 9,635 $173.69 17 17,406 $27.07 18 1,573 $25.99 19 6,471 $64.99 20 6,047 $29.83 21 433 $20.89 22 2,279 $53.59 23 15,532 $106.91 24 1,585 $4.09 25 5,376 $65.23 26 2,965 $37.93 27 2,048 $28.51 28 1,174 $22.99 29 381 $5.57 30 2,930 $3.43 Which item in the table above has the highest annual dollar volume? In the answer field below, write the ITEM # that…arrow_forwardIM.84 An outdoor equipment manufacturer sells a rugged water bottle to complement its product line. They sell this item to a variety of sporting goods stores and other retailers. The manufacturer offers quantity discounts per the following discount schedule: Option Plan Quantity Price A 1 - 2,199 $5.00 B 2,200 - 3,699 $4.55 C 3,700+ $3.90 A large big-box retailer expects to sell 9,200 units this year. This retailer estimates that it incurs an internal administrative cost of $235 each time it places an order with the manufacturer. Holding cost for the retailer is $60 per case per year. (There are 52 units or water bottles per case.)Based on this information, and not taking into account any quantity discount offers, what is the calculated EOQ (in units)? (Display your answer to the nearest whole number.) Based on this information, sort each quantity discount plan from left to right by dragging the MOST preferred option plan to the left, and the LEAST preferred option…arrow_forwardPlease provide detailed solutions to the following problems/exercises (4 problems/exercises x 9 points each): 1) View the video ON Unveils ‘Lightspray’ Technology (4.55 mins, Ctrl+Click in the link), and The Secret of Lightspray (8.27 mins, Ctrl+Click in the link), answer the following questions: https://www.youtube.com/watch?v=wjmeaC-wlZs a) What is new about the design of ON’s shoes? b) How will ON’s new manufacturing technique affect location planning for footwear firms? c) How does ON focus on it sustainability strategy? Note: As a rough guideline, please try to keep the written submission to one or two paragraphs for each of the questions. 2) Unimed Hospital currently processes patient admissions through three admitting clerks who are set up to work in series, with respective reliabilities of 0.96, 0.95, and 0.90 (see figure below). a) Find the reliability of the current admission process. Due to rising patient complaints, the hospital administrator, Chimeg…arrow_forward
- 3) A startup firm, Pocket International, has come up with a tiny programmable computer, NerdCom Mini Air, that sells for $49.99. The firm estimates that the programmable computers have an expected life that is exponential, with a mean of 24 months. The firm wants to estimate the probability that the NerdCom Mini Air will have a life that ends: a) after the initial 24 months of service. b) before the 24 months of service is completed. c) not before 48 months of service. Note: You could work out the problem by hand or use excel; in chapter 4S, section 4S.2 of the Stevenson text, reliability (finding the probability of functioning for a specified length of time) is covered with examples; chapters 4 & 4S Stevenson lecture power point slides 33 to 38 (chapters 4 & 4S lecture: 32.30 mins to 38.56 mins) cover reliability over time with examples.arrow_forwardDiscuss how training and development programs can be best presented to ultimately change the behavior of employees, often without their knowledge or awareness.arrow_forwardDoctor Earrow_forward
- Considering contemporary challenges in business, analyze a real-world case where a company successfully navigated a major shift in its marketing strategy to adapt to changing market dynamics. Discussion Question and Prompt: Identify the key factors that contributed to the success of their marketing strategy in the face of contemporary issues. How can businesses draw insights from this case to inform their own marketing strategies amid current business challenges?arrow_forward1) View the video Service Processing at BuyCostumes (10.41 minutes, Ctrl+Click on the link); what are your key takeaways (tie to one or more of the topics discussed in Chapter 3) after watching this video. (viddler.com/embed/a6b7054c) Note: As a rough guideline, please try to keep the written submission to one or two paragraphs. 2) Orkhon Foods makes hand-held pies (among other products). The firm’s weekly sales of hand-held pies over the past seven weeks are given in the table. The firm’s operations manager, Amarjargal, wants to forecast sales for week 8. Weeks Sales of hand-held pies(000s) 1 19 2 18 3 17 4 20 5 18 6 22 7 20 Forecast the week 8 sales using the following approaches: a) Naïve approach b) 5-month moving average c) 3-month weighted moving average using the following weights: 0.50 for week 7, 0.30 for week 6, and 0.20 for week 5. d) Exponential smoothing using a smoothing constant of 0.30, assume a…arrow_forwardAnswer all parts to question 4 and show all workingarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning