Concept explainers
A.
Interpretation: A network diagram representing the activities of the project is to be constructed.
Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the work flow and is used to compute the total duration of the project.
A.
Explanation of Solution
Given information: Theactivities to be taken up for the construction of a gas station and the time duration for each are given in the table.
Activity | Time |
A | 4 |
B | 2 |
C | 3 |
D | 1 |
E | 1 |
F | 2 |
G | 3 |
H | 1 |
I | 5 |
J | 3 |
K | 4 |
L | 2 |
M | 1 |
The activity times and the precedence relationship are shown in the table:
Activity | Time | Predecessors |
A | 4 | |
B | 2 | A |
C | 3 | B |
D | 1 | C |
E | 1 | D |
F | 2 | B |
G | 3 | F |
H | 1 | G |
I | 5 | B |
J | 3 | I |
K | 4 | C, F, I |
L | 2 | K |
M | 1 | L |
The network diagram showing the work flows is as follows:
B.
Interpretation: The critical path is to be identified by computing the earliest and the latest start and finish times.
Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the work flow and is used to compute the total duration of the project.
B.
Answer to Problem 26AP
The critical path is A − B − I − K − L − M with completion time as 18 weeks
Explanation of Solution
Given information:
Activity | Time |
A | 4 |
B | 2 |
C | 3 |
D | 1 |
E | 1 |
F | 2 |
G | 3 |
H | 1 |
I | 5 |
J | 3 |
K | 4 |
L | 2 |
M | 1 |
The earliest and latest start and finish times are calculated using the formulae:
Earliest Start (EST) = Maximum EFT of the predecessor activity
Latest Start (LST) = LFT - Duration
Earliest Finish (EFT) = EST + Duration
Latest Finish (LFT) = Minimum LST of the immediate successor
Slack = LFT − EFT (or) LST − EST
Activity | Time | EST | EFT | LST | LFT | Slack |
A | 4 | 0 | 4 | 0 | 4 | 0 |
B | 2 | 4 | 6 | 4 | 6 | 0 |
C | 3 | 6 | 9 | 8 | 11 | 2 |
D | 1 | 9 | 10 | 16 | 17 | 7 |
E | 1 | 10 | 11 | 17 | 18 | 7 |
F | 2 | 6 | 8 | 9 | 11 | 3 |
G | 3 | 8 | 11 | 14 | 17 | 6 |
H | 1 | 11 | 12 | 17 | 18 | 6 |
I | 5 | 6 | 11 | 6 | 11 | 0 |
J | 3 | 11 | 14 | 15 | 18 | 4 |
K | 4 | 11 | 15 | 11 | 15 | 0 |
L | 2 | 15 | 17 | 15 | 17 | 0 |
M | 1 | 17 | 18 | 17 | 18 | 0 |
The critical path includes the activities with zero slack. So, here the critical path is A − B− I − K − L − M. The total time taken to complete the project is 18 weeks.
C.
Interpretation: A Gantt chart of the
Concept Introduction: Gantt chart is a project management tool that is a type of bar chart. It depicts the project schedule and is used for resource allocation.
C.
Answer to Problem 26AP
A Gantt chart for the project has been drawn.
Explanation of Solution
Given information:
Activity | Time |
A | 4 |
B | 2 |
C | 3 |
D | 1 |
E | 1 |
F | 2 |
G | 3 |
H | 1 |
I | 5 |
J | 3 |
K | 4 |
L | 2 |
M | 1 |
Activity times and early start times:
Activity | EST | Time |
A | 0 | 4 |
B | 4 | 2 |
C | 6 | 3 |
D | 9 | 1 |
E | 10 | 1 |
F | 6 | 2 |
G | 8 | 3 |
H | 11 | 1 |
I | 6 | 5 |
J | 11 | 3 |
K | 11 | 4 |
L | 15 | 2 |
M | 17 | 1 |
The Gantt chart depicting the project based on the EST:
D.
Interpretation: The impact of replacement of the air compressor which takes two weeks on the completion of the project is to be determined.
Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the work flow and is used to compute the total duration of the project.
D.
Explanation of Solution
Given information:
Activity | Time |
A | 4 |
B | 2 |
C | 3 |
D | 1 |
E | 1 |
F | 2 |
G | 3 |
H | 1 |
I | 5 |
J | 3 |
K | 4 |
L | 2 |
M | 1 |
Installing the air compressor is represented by activity G.
Activity | Time | EST | EFT | LST | LFT | Slack |
A | 4 | 0 | 4 | 0 | 4 | 0 |
B | 2 | 4 | 6 | 4 | 6 | 0 |
C | 3 | 6 | 9 | 8 | 11 | 2 |
D | 1 | 9 | 10 | 16 | 17 | 7 |
E | 1 | 10 | 11 | 17 | 18 | 7 |
F | 2 | 6 | 8 | 9 | 11 | 3 |
G | 3 | 8 | 11 | 14 | 17 | 6 |
H | 1 | 11 | 12 | 17 | 18 | 6 |
I | 5 | 6 | 11 | 6 | 11 | 0 |
J | 3 | 11 | 14 | 15 | 18 | 4 |
K | 4 | 11 | 15 | 11 | 15 | 0 |
L | 2 | 15 | 17 | 15 | 17 | 0 |
M | 1 | 17 | 18 | 17 | 18 | 0 |
The latest start time of the activity G is 14th week. If the failure is identified before installation, the project will not be delayed as the replacement time (2 weeks) is less than the slack (6 weeks).
If the failure is found during testing of the air compressor, represented by activity H, still the project would not be delayed, as again there is a slack of 6 weeks.
E.
Interpretation: The activities that can be completed by the end of the 15th week without delaying the project completion are to be determined.
Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the work flow and is used to compute the total duration of the project.
E.
Answer to Problem 26AP
The activities A, B, C, F and I have to be completed by the end of the 15th week to guarantee project completion without delay.
Explanation of Solution
Given information:
Activity | Time |
A | 4 |
B | 2 |
C | 3 |
D | 1 |
E | 1 |
F | 2 |
G | 3 |
H | 1 |
I | 5 |
J | 3 |
K | 4 |
L | 2 |
M | 1 |
The table shows the Earliest and Latest times of the activities
Activity | Time | EST | EFT | LST | LFT | Slack |
A | 4 | 0 | 4 | 0 | 4 | 0 |
B | 2 | 4 | 6 | 4 | 6 | 0 |
C | 3 | 6 | 9 | 8 | 11 | 2 |
D | 1 | 9 | 10 | 16 | 17 | 7 |
E | 1 | 10 | 11 | 17 | 18 | 7 |
F | 2 | 6 | 8 | 9 | 11 | 3 |
G | 3 | 8 | 11 | 14 | 17 | 6 |
H | 1 | 11 | 12 | 17 | 18 | 6 |
I | 5 | 6 | 11 | 6 | 11 | 0 |
J | 3 | 11 | 14 | 15 | 18 | 4 |
K | 4 | 11 | 15 | 11 | 15 | 0 |
L | 2 | 15 | 17 | 15 | 17 | 0 |
M | 1 | 17 | 18 | 17 | 18 | 0 |
The latest finish times of the activities A, B, C, F and Iam less than 15 weeks. Therefore, these activities have to be completed by the end of the 15th weeks to guarantee project completion without any delay.
F.
Interpretation: The optimal solution for the problem is to be determined using linear programming.
Concept Introduction: Linear programming is a mathematical technique used to achieve the best outcome, given a list of parameters usually restrictions on the resources.
F.
Answer to Problem 26AP
The optimal solution for the problem is obtained using linear programming.
Explanation of Solution
Given information:
Activity | Time |
A | 4 |
B | 2 |
C | 3 |
D | 1 |
E | 1 |
F | 2 |
G | 3 |
H | 1 |
I | 5 |
J | 3 |
K | 4 |
L | 2 |
M | 1 |
The various paths of the project and the durations are:
The critical path is A − B − I − K − L − M with the completion time of 18 weeks.
Using linear programming, the EST is calculated.
Objective function = =SUM (B2:M2)
Nodes | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
EST |
The constraints
Activity | Time | ||
A | 0 | > | 4 |
B | 0 | > | 2 |
C | 0 | > | 3 |
D | 0 | > | 1 |
E | 0 | > | 1 |
F | 0 | > | 2 |
G | 0 | > | 3 |
H | 0 | > | 1 |
I | 0 | > | 5 |
J | 0 | > | 3 |
K | 0 | > | 4 |
L | 0 | > | 2 |
M | 0 | > | 1 |
P1 | 0 | > | 0 |
P2 | 0 | > | 0 |
P3 | 0 | > | 0 |
Solver Solution:
Objective Function |
120 |
EST for the nodes:
Nodes | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
EST | 0 | 4 | 6 | 9 | 8 | 11 | 11 | 11 | 10 | 15 | 17 | 18 |
Want to see more full solutions like this?
Chapter 10 Solutions
Production and Operations Analysis, Seventh Edition
- وبة واضافة هذه القيمة الى القيم Ex: Assign each job for each worker at minimum total Cost عمل لكل عامل وبأقل كلفة ممكنة obs الأعمال Workors العمال J1 J2 J3 J4 W₁ 15 13 14 12 W2 11 12 15 13 W3 13 12 10 11 W4 15 17 14 16arrow_forwardThe average completion time (flow time) for the sequence developed using the FCFS rule = 11.75 days (round your response to two decimal places). The percentage utilization for the sequence developed using the FCFS rule = 42.55 % (enter your response as a percentage rounded to two decimal places). b) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: Job Due Date A 212 B 209 C 208 D 210 Duration (days) 6 3 3 8 Sequence 1 Job B 2 3 4 A D The average tardiness (job lateness) for the sequence developed using the SPT rule = 5.00 days (round your response to two decimal places). The average completion time (flow time) for the sequence developed using the SPT rule = 10.25 days…arrow_forwardWith the aid of examples, fully discuss any five (5) political tactics used in organisations.arrow_forward
- a. With the aid of examples, define discrimination. b. Fully discuss any four (4) types of discrimination in the workplacearrow_forwardRead the Following Extract and Answer the Questions that Follows:The word politics has a somewhat negative connotation. It suggests that someone is attempting touse means or to gain ends that are not sanctioned by the organisation. Political behaviour, as we’vedefined it is quite neutral. Similarly, power is not inherently negative. Whether a person viewspower and politics as unsavoury topics depends on several considerations, most important perhapsbeing where the individual stands on a specific issue in each situation. Nonetheless, most managersare reluctant to admit to political character of their own work settings.Discuss any Five (5) Political tactics you know.arrow_forwardDescribe current features of Cigna Accredo pharmacy own appraisal forms and compare the system used against the textbook’s description of desirable features of appraisal forms. What improvements would you recommend and why?arrow_forward
- Provide a recommendation of a combination of different methods of performance data that could be used to arrive at an overall score for each person being rated in cigna Accredo pharmacy. Explain the comprehensive system you have recommended and why you have chosen this combination of tools. Support your answer with research.arrow_forwardAlready got wrong answer Plz Don't use chatgptarrow_forwardThe RTY calculation for the following process steps would be: A ➡ ○ A.YA+YB+YC+YD OB. (YA)(YB)(YCYD) OC. ((YA+YB+YC+YD)/4)*4 ○ D. (1/YA)+(1/YB)+(1/YC)+YD B C Darrow_forward
- Can you guys help me with this? 1. What did you learn about the case, the concepts of transformational leadership; transactional leadership; Herzberg's Two Factors; Maslow's Hierarchy of needs theories that been applied through the case? Here is the case: Theranos (2003-2018):Overview: Theranos promised to revolutionize blood testing but was exposed formisleading claims about its technology, leading to its collapse 2. What did you learn about the case between Elon Musk and Twitter, the concepts of transformational leadership; transactional leadership; Herzberg's Two Factors Theory; Maslow's Hierarchy of needs theories that been applied through the case? 3. What did you learn about the case of Blockbuster's decline and their failure to adapt with digital streaming, the concepts of autocratic leadership; transactional leadership; Herzberg's Two Factors; Maslow's Hierarchy of needs theories that been applied through the case?arrow_forwardCan you guys help me with this? 1. What did you learn about the case, the concepts of transformational leadership; transactional leadership; Herzberg's Two Factors; and Maslow's Hierarchy of needs theories that have been applied through the case? Here is the case: The COVID-19 Pandemic Response (2020-Present): Overview: Global leaders had to navigate an unprecedented health crisis, balancingpublic health needs with economic pressures. 2. What did you learn about the case, the concepts of transformational leadership; transactional leadership; Herzberg's Two Factors Theory; and Maslow's Hierarchy of Needs theories that have been applied through the case? Here's the case: Google Glass (2013):Overview: Google launched its augmented reality glasses with high expectations, butprivacy concerns and limited functionality led to poor adoption 3. What did you learn about the case of Kodak's failure to keep up with digital photography, the concepts of autocratic leadership; transformational…arrow_forwardWith the above information do the following:1. Based on the From-To chart presented develop an ActivityRelationship Chart for this operation.2. Develop a Space-Relationship Diagram for this operation.3. Evaluate the actual layout using the “Distance Traveled byProduct” technique discussed in class (use rectilinear distance inall calculations).4. Develop two layout improvement alternatives.5. Evaluate alternatives using the “Distance Traveled by Product”technique discussed in class (use rectilinear distance in allcalculations).6. Make a layout recommendation based on alternatives evaluatedarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.