a)

Summary Introduction

To determine: The time required for the given operations.

a)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Person X plans for six tellers and the tellers would take 15 minutes per customers. Standard deviation is given as 7 minutes. arrival time of customers is three minutes according to the exponential distribution.

Determine the arrival and service rate using waiting line approximation:

X¯a=3Sa=3X¯s=15Ss=7S=6

Determine interarrival time:

Ca=SaX¯a=33=1

Determine service time:

Cs=SsX¯s=715=0.4667

Determine arrival and service time:

λ=1X¯a=13=0.3333

μ=1X¯s=115=0.06667

ρ=λSμ=0.33336(0.06667)=0.8332

Determine the number of customers waiting in the line:

Lq=ρ2(S+1)1ρ×Ca2+Cs22=0.83322(6+1)10.8332×12+0.466722=0.505770.1668×1.21782=1.8443

Hence, the number of customers waiting in the line is 1.8443.

b)

Summary Introduction

To determine: The time spent by the customers in the bank.

b)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Person X plans for six tellers and the tellers would take 15 minutes per customers. Standard deviation is given as 7 minutes. arrival time of customers is three minutes according to the exponential distribution.

Determine the arrival and service rate using waiting line approximation:

X¯a=3Sa=3X¯s=15Ss=7S=6

Determine interarrival time:

Ca=SaX¯a=33=1

Determine service time:

Cs=SsX¯s=715=0.4667

Determine arrival and service time:

λ=1X¯a=13=0.3333

μ=1X¯s=115=0.06667

ρ=λSμ=0.33336(0.06667)=0.8332

Determine the time spent by the customers in the line:

Lq=ρ2(S+1)1ρ×Ca2+Cs22=0.83322(6+1)10.8332×12+0.466722=0.505770.1668×1.21782=1.8443

Ls=Lq+Sρ=1.8443+(6)(0.8332)=1.8443+4.9992=6.8435

Ws=Lsλ=6.84350.3333=20.5325

Hence, the time spent by the customers in the bank is 20.5325.

c)

Summary Introduction

To determine: The term for the given information.

c)

Expert Solution
Check Mark

Explanation of Solution

Determine the term for the given information:

When the customer arrived at the place, saw the queue and decided to leave before getting into line is said to be balked.

d)

Summary Introduction

To determine: The term for the given information.

d)

Expert Solution
Check Mark

Explanation of Solution

Determine the term for the given information:

Here, the customer arrives at the place, saw the queue and stand in line. However, he decides to leave before getting service is said to be reneged.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
وبة واضافة هذه القيمة الى القيم Ex: Assign each job for each worker at minimum total Cost عمل لكل عامل وبأقل كلفة ممكنة obs الأعمال Workors العمال J1 J2 J3 J4 W₁ 15 13 14 12 W2 11 12 15 13 W3 13 12 10 11 W4 15 17 14 16
The average completion time (flow time) for the sequence developed using the FCFS rule = 11.75 days (round your response to two decimal places). The percentage utilization for the sequence developed using the FCFS rule = 42.55 % (enter your response as a percentage rounded to two decimal places). b) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: Job Due Date A 212 B 209 C 208 D 210 Duration (days) 6 3 3 8 Sequence 1 Job B 2 3 4 A D The average tardiness (job lateness) for the sequence developed using the SPT rule = 5.00 days (round your response to two decimal places). The average completion time (flow time) for the sequence developed using the SPT rule = 10.25 days…
With the aid of examples, fully discuss any five (5) political tactics used in organisations.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.