Interest capitalization; specific interest method
• LO10–7
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows:
January 1, 2018 | $1,000,000 |
March 1, 2018 | 600,000 |
June 30, 2018 | 800,000 |
October 1, 2018 | 600,000 |
January 31, 2019 | 270,000 |
April 30, 2019 | 585,000 |
August 31, 2019 | 900,000 |
On January 1, 2018, the company obtained a $3 million construction loan with a 10% interest rate. The loan was outstanding all of 2018 and 2019. The company’s other interest-bearing debt included two long-term notes of $4,000,000 and $6,000,000 with interest rates of 6% and 8%, respectively. Both notes were outstanding during all of 2018 and 2019. Interest is paid annually on all debt. The company’s fiscal year-end is December 31.
Required:
- 1. Calculate the amount of interest that Mason should capitalize in 2018 and 2019 using the specific interest method.
- 2. What is the total cost of the building?
- 3. Calculate the amount of interest expense that will appear in the 2018 and 2019 income statements.
1.
Interest Capitalization:
Interest capitalization refers to the interest amount that is added to the cost of the long-term asset. Such interest capitalization amount includes the interest amount of the debt which was financed for acquiring the asset.
To Calculate: The amount of interest that Company M should capitalize in 2018 and 2019 using the specific interest method.
Explanation of Solution
Calculate the amount of interest capitalized in the year 2018.
Month | Construction Expenditure ($) | Interest Outstanding (Number of months) | Accumulated Expenditure ($) | ||
January 1, 2018 | 100,000 | = | 1,000,000 | ||
March 1, 2018 | 600,000 | = | 500,000 | ||
June 30, 2018 | 800,000 | = | 400,000 | ||
October 1, 2018 | 600,000 | = | 150,000 | ||
Accumulated expenditures (before interest) | $3,000,000 | ||||
Average accumulated expenditures | $2,050,000 |
Table (1)
Determine the capitalized interest.
Calculate the amount of interest capitalized in the year 2019.
Month | Construction Expenditure | Interest Outstanding | Accumulated Expenditure | ||
January 1, 2019 | 3,205,000 | = | 3,205,000 | ||
January 31, 2019 | 270,000 | = | 240,000 | ||
April 30, 2019 | 585,000 | = | 325,000 | ||
August 31, 2019 | 900,000 | = | 100,000 | ||
Accumulated expenditures (before interest) | 4,960,000 | ||||
Average accumulated expenditure | 3,870,000 |
Table (2)
Determine the weighted average rate of all other debt.
Amount ($) | Interest rate | Interest Amount ($) | |||
Long-term note 6% | $4,000,000 | 6% | = | 240,000 | |
Long-term note 8% | $6,000,000 | 8% | = | 480,000 | |
Total | $10,000,000 | 720,000 |
Table (3)
Working Note:
Determine the weighted-average interest rate.
Determine the amount of difference.
Determine the interest on amount of difference.
Determine the interest on amount on the construction loan.
Determine the capitalized interest.
Hence, the amount of interest capitalized in the year 2018, and 2019 are $205,000, and $271,980 respectively.
2.
Explanation of Solution
Determine the total cost of the building.
Particulars | Amount ($) |
Accumulated expenditures as on September 30, 2019 before interest capitalization |
4,960,000 |
Add: Interest capitalization as on 2019 | 271,980 |
Total cost of building | 5,231,980 |
Table (4)
Hence, the total cost of the building is $5,231,980.
3.
To Calculate: The amount of interest expense that will appear in the 2018 and 2019 income statements.
Explanation of Solution
Calculate the amount of interest expense for 2018 and 2019.
2018 | 2019 | |
Amount ($) | Amount ($) | |
300,000 | 300,000 | |
240,000 | 240,000 | |
480,000 | 480,000 | |
Total interest capitalized | 1,020,000 | 1,020,000 |
Less: Interest capitalized | (205,000) | (271,980) |
Interest expense | 815,000 | 748,020 |
Table (5)
Hence, the amount of interest expense that will appear in the income statement for the years 2018 and 2019 are $815,000 and $748,020 respectively.
Want to see more full solutions like this?
Chapter 10 Solutions
Intermediate Accounting
- 10arrow_forwardH1.arrow_forward21 Beck Construction Company began work on a new building project on January 1, 2023. The project is to be completed by December 31, 2025, for a fixed price of $131 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff: Years Actual costs incurred in each year Estimated remaining costs to complete the project (measured atDecember 31 of each year) 2023 $ 36 million $ 72 million 2024 $ 57 million $ 57 million 2025 $ 41 million $ 0 million Required: What amount of gross profit (or loss) would Beck record on this project in each year, assuming that Beck recognizes revenue for this project upon completion of the project?arrow_forward
- Problem 10-9 (Algo) Interest capitalization; specific interest method [LO10-7]On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows:January 1, 2021$1,280,000March 1, 2021720,000June 30, 2021920,000October 1, 2021720,000January 31, 2022288,000April 30, 2022621,000August 31, 2022918,000 On January 1, 2021, the company obtained a $3,200,000 construction loan with a 15% interest rate. The loan was outstanding all of 2021 and 2022. The company’s other interest-bearing debt included two long-term notes of $3,000,000 and $7,000,000 with interest rates of 11% and 13%, respectively. Both notes were outstanding during all of 2021 and 2022. Interest is paid annually on all debt. The company’s fiscal year-end is December 31. Required:1. Calculate the amount of interest that Mason should capitalize in 2021 and 2022 using the specific…arrow_forwardSM3arrow_forwardQ 9 – A company constructs a building for its own use. Construction began on January 1, 2020 and ended on December 31,2020. In 2020, the company made the following expenditures related to this building: January 1, $480,000; March 31, $900,000; June 30, $1,600,000; and October 30, $1,800,000. To help finance construction, the company arranged a 15% construction loan on January 1 for $1,000,000. The company’s other borrowings, outstanding for the whole year, consisted of a $2 million loan and a $4 million note with interest rates of 8% and 6%, respectively. Determine the amount of interest to be capitalized in 2020 in relation to the construction of the building. Q 10 –Eshaq Company’s record of transactions concerning part X for the month of February was as follows.arrow_forward
- View Policies Current Attempt in Progress On December 31, 2024, Blue Inc. borrowed $4,320,000 at 13% payable annually to finance the construction of a new building. In 2025, the company made the following expenditures related to this building: March 1, $518,400; June 1, $864,000; July 1, $2,160,000; December 1, $2,160,000. The building was completed in February 2026. Additional information is provided as follows. 1. 2. 3. (a) Other debt outstanding: 10-year, 14% bond, December 31, 2018, interest payable annually 6-year, 11% note, dated December 31, 2022, interest payable annually March 1, 2025, expenditure included land costs of $216,000. Interest revenue of $70,560 earned in 2025. The amount of interest Determine the amount of interest to be capitalized in 2025 in relation to the construction of the building. eTextbook and Media List of Accounts $ $5,760,000 EMBLY 2,304,000 DOLLarrow_forwardacc1arrow_forwardh2arrow_forward
- Dineshbhaiarrow_forwardPlease help me to solve this problemarrow_forwardChapter 10 Problem Set A Problem 10-1 On January 1, 2019 Crampton Company acquired land on which to construct a new distribution warehouse. During 2019, the company made expenditures as follows: Contract price of the land $600,000 Closing costs $23,000 Hoerr Excavating for clearing and grading $65,000 Sparks Concrete Construction for sidewalk and parking lot $158,500 Touchstone Lighting for parking lot lighting $21,500 J Hacker and Associates, Architects $71,000 Town of Normal for building permits $9,500 Lewis General Contractors $4,100,000 Crampton also purchased $1,450,000 of warehousing equipment and conveyors. The entire facility was placed in service before December 31, 2019. Prepare Crampton Company’s PPE section of their balance sheet dated December 31, 2019 before the adjusting entries for depreciationarrow_forward