Question
Book Icon
Chapter 1, Problem 5P
Summary Introduction

To determine: The productivity of Person GK and to know whether the organization is maintaining a manufacturing average of 3% increase in productivity every year.

Introduction: Productivity is a measure of the effectiveness of an individual, systems, machinery and other equipment that are used in converting inputs into outputs. In all organizations, productivity is an important determinant to know the cost efficiency.

Expert Solution & Answer
Check Mark

Answer to Problem 5P

Person GK is maintaining the manufacturing average of a 3% increase in productivity per year in all the resources except capital.

Explanation of Solution

Given information: Person GK is producing bowling balls. The amount of resources used last year and in the current year is given as follows:

Last year Now
Units produced 1,000 1,000
Labor (hours) 300 275
Resin (pounds) 50 45
Capital invested ($) 10,000 11,000
Energy (BTU) 3,000 2,850

Formula to calculate productivity for last year and the current year:

Productivity=Total outputTotal input

The productivity is calculated by dividing the total number of units produced by the total input used to produce the overall output.

Formula to calculate the change in the production units:

Change in production units=New productivityIntital productivity

The change in production units are calculated by subtracting the current year’s productivity from the previous year’s productivity value.

Formula to calculate the percentage of productivity change:

Percentage change=Change in productivityIntital productivity

The percentage change in productivity is calculated by dividing the change in productivity units by the initial productivity.

Substitution:

Resource Last-year productivity Current year productivity Change in production units Percentage of productivity change
Labor 3.33 3.64 0.30 9.01%
Resin 20.00 22.22 2.22 11.1%
Capital 0.10 0.09 -0.01 -10%
Energy 0.33 0.35 0.02 6.06%

Working note:

Calculate last-year productivity for labor:

The productivity is calculated by dividing the total number of units produced by the total input used to produce the overall output.

Productivity=Total outputTotal input=1,000300=3.33

Calculate last-year productivity for resin:

The productivity is calculated by dividing the total number of units produced by the total input used to produce the overall output.

Productivity=Total outputTotal input=1,00050=20

Note: The calculation continues for capital and energy.

Calculate current year productivity for labor:

The productivity is calculated by dividing the total number of units produced by the total input used to produce the overall output.

Productivity=Total outputTotal input=1,000275=3.64

Calculate current year productivity for resin:

The productivity is calculated by dividing the total number of units produced by the total input used to produce the overall output.

Productivity=Total outputTotal input=1,00045=22.22

Note: The calculation continues for capital and energy.

Calculate the change in the production units for labor:

The change in production units are calculated by subtracting the current year’s productivity from the previous year’s productivity value.

Change in production units=Current year productivitylast-year productivity=3.643.33=0.30

Calculate the change in the production units for resin:

The change in production units are calculated by subtracting the current year’s productivity from the previous year’s productivity value.

Change in production units=Current year productivitylast-year productivity=22.2220=2.22

Note: The calculation continues for capital and energy.

Calculate the percentage of productivity change for labor:

The percentage change in productivity is calculated by dividing the change in productivity units by the initial productivity.

Percentage change=Change in productivityLast-year productivity=0.303.33×100=9.01%

Calculate the percentage of productivity change for resin:

The percentage change in productivity is calculated by dividing the change in productivity units by the initial productivity.

Percentage change=Change in productivityLast-year productivity=2.2220×100=11.1%

Note: The calculation continues for capital and energy.

Hence, Person GKis maintaining the manufacturing average of a 3% increase in productivity per year in all the resources except capital.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Communication Tips (2015) Tactful bragging Respond to the question "So, what do you do?" Whether you are student or have a job/internship, how can you tactfully brag in your answer to this question? Use the three elements from the video (listed below) when crafting your brag statement:  Focus on results vs title Process vs job description Loop back to listener Example of an instructor's brag statement: "I help hundreds of students each semester to connect with one another, develop communication skills and prepare for upcoming interviews. Through improv games we explore presence, flexibility, and storytelling. How have your networking experiences on campus been so far?"
Accounting problem
Government's new plan to shift cargo from roads back to rail 26TH JANUARY 2024 Government is seeking to finalise a plan aimed at improving its rail network and move cargo away from a billion rand per day to its logistics crises, government has said an urgentturnaround is needed to improve its 31 000km locomotive network as more and more cargo moves from rail to trucks. The Department of Transport (DoT) hosted a discussion with industry stakeholders regarding the Freight Road to Rail Migration Plan on Thursday - the latest development in the wake of President Cyril Ramphosa forming the National Logistics Crisis Committee last year. Transnet, the South African National Roads Agency (Sanral) and private sector companies were all in attendance. The Freight Road to Rail Migration Plan is part of government's strategies to improve the country's ongoing logistics crises. In October last year, the government unveiled its Freight Logistics Roadmap to improve the ports and rail networks and…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Management, Loose-Leaf Version
Management
ISBN:9781305969308
Author:Richard L. Daft
Publisher:South-Western College Pub
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Foundations of Business (MindTap Course List)
Marketing
ISBN:9781337386920
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College