Concept explainers
To determine: The productivity of Person GK and to know whether the organization is maintaining a manufacturing average of 3% increase in productivity every year.
Introduction: Productivity is a measure of the effectiveness of an individual, systems, machinery and other equipment that are used in converting inputs into outputs. In all organizations, productivity is an important determinant to know the cost efficiency.
Answer to Problem 5P
Person GK is maintaining the manufacturing average of a 3% increase in productivity per year in all the resources except capital.
Explanation of Solution
Given information: Person GK is producing bowling balls. The amount of resources used last year and in the current year is given as follows:
Last year | Now | |
Units produced | 1,000 | 1,000 |
Labor (hours) | 300 | 275 |
Resin (pounds) | 50 | 45 |
Capital invested ($) | 10,000 | 11,000 |
Energy (BTU) | 3,000 | 2,850 |
Formula to calculate productivity for last year and the current year:
The productivity is calculated by dividing the total number of units produced by the total input used to produce the overall output.
Formula to calculate the change in the production units:
The change in production units are calculated by subtracting the current year’s productivity from the previous year’s productivity value.
Formula to calculate the percentage of productivity change:
The percentage change in productivity is calculated by dividing the change in productivity units by the initial productivity.
Substitution:
Resource | Last-year productivity | Current year productivity | Change in production units | Percentage of productivity change |
Labor | 3.33 | 3.64 | 0.30 | 9.01% |
Resin | 20.00 | 22.22 | 2.22 | 11.1% |
Capital | 0.10 | 0.09 | -0.01 | -10% |
Energy | 0.33 | 0.35 | 0.02 | 6.06% |
Working note:
Calculate last-year productivity for labor:
The productivity is calculated by dividing the total number of units produced by the total input used to produce the overall output.
Calculate last-year productivity for resin:
The productivity is calculated by dividing the total number of units produced by the total input used to produce the overall output.
Note: The calculation continues for capital and energy.
Calculate current year productivity for labor:
The productivity is calculated by dividing the total number of units produced by the total input used to produce the overall output.
Calculate current year productivity for resin:
The productivity is calculated by dividing the total number of units produced by the total input used to produce the overall output.
Note: The calculation continues for capital and energy.
Calculate the change in the production units for labor:
The change in production units are calculated by subtracting the current year’s productivity from the previous year’s productivity value.
Calculate the change in the production units for resin:
The change in production units are calculated by subtracting the current year’s productivity from the previous year’s productivity value.
Note: The calculation continues for capital and energy.
Calculate the percentage of productivity change for labor:
The percentage change in productivity is calculated by dividing the change in productivity units by the initial productivity.
Calculate the percentage of productivity change for resin:
The percentage change in productivity is calculated by dividing the change in productivity units by the initial productivity.
Note: The calculation continues for capital and energy.
Hence, Person GKis maintaining the manufacturing average of a 3% increase in productivity per year in all the resources except capital.
Want to see more full solutions like this?
Chapter 1 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
- Solve the following Question 1. How do volume and variety affect the process selection and layout types? Discuss 2. How is the human resource aspect important to operation function? Discuss 3. Discuss the supply network design and its impact on the overall performance of the organization.arrow_forwardHelp with question?arrow_forwardWhat are some good examples of bullet points on a resume for a Christian Elementary School?arrow_forward
- What is an example of a cover letter for a Christian School Long-Term Substitute Teaching position?arrow_forwardThe supply chain is a conventional notion, but organizations are only really interested in making products that they can sell to customers. Provided they have reliable supplies of materials and reasonable transport for finished products, logistics is irrelevant. Do you think this is true? If yes, explain, and if no, clearly explain as well.arrow_forwardworking as a program operations managerarrow_forward
- 12 X1, X230 1 x =0x2 write the Following linear Programming model by 1- general Form Canonical Forms Canonical formY 2- Standard Form Max Z=35X+ 4 X 2 +6 X3 ST. X+2X2-5x3 = 40 3X, + 6X2 + 7x 3 = 30 7x, +lox2 x3 = 50 X3 X 2 X 3 <0arrow_forwarda/ a Minimum cost assign each worker for one job at Jobs J1 12 33 WI 2 4 6 W2 5 W3 5 33 6 7arrow_forwardوبة واضافة هذه القيمة الى القيم Ex: Assign each job for each worker at minimum total Cost عمل لكل عامل وبأقل كلفة ممكنة obs الأعمال Workors العمال J1 J2 J3 J4 W₁ 15 13 14 12 W2 11 12 15 13 W3 13 12 10 11 W4 15 17 14 16arrow_forward
- The average completion time (flow time) for the sequence developed using the FCFS rule = 11.75 days (round your response to two decimal places). The percentage utilization for the sequence developed using the FCFS rule = 42.55 % (enter your response as a percentage rounded to two decimal places). b) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: Job Due Date A 212 B 209 C 208 D 210 Duration (days) 6 3 3 8 Sequence 1 Job B 2 3 4 A D The average tardiness (job lateness) for the sequence developed using the SPT rule = 5.00 days (round your response to two decimal places). The average completion time (flow time) for the sequence developed using the SPT rule = 10.25 days…arrow_forwardWith the aid of examples, fully discuss any five (5) political tactics used in organisations.arrow_forwarda. With the aid of examples, define discrimination. b. Fully discuss any four (4) types of discrimination in the workplacearrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,