To determine: The productivity of Person GK and to know whether the organization is maintaining a manufacturing average of 3% increase in productivity every year.
Introduction: Productivity is a measure of the effectiveness of an individual, systems, machinery and other equipment that are used in converting inputs into outputs. In all organizations, productivity is an important determinant to know the cost efficiency.

Answer to Problem 5P
Person GK is maintaining the manufacturing average of a 3% increase in productivity per year in all the resources except capital.
Explanation of Solution
Given information: Person GK is producing bowling balls. The amount of resources used last year and in the current year is given as follows:
Last year | Now | |
Units produced | 1,000 | 1,000 |
Labor (hours) | 300 | 275 |
Resin (pounds) | 50 | 45 |
Capital invested ($) | 10,000 | 11,000 |
Energy (BTU) | 3,000 | 2,850 |
Formula to calculate productivity for last year and the current year:
The productivity is calculated by dividing the total number of units produced by the total input used to produce the overall output.
Formula to calculate the change in the production units:
The change in production units are calculated by subtracting the current year’s productivity from the previous year’s productivity value.
Formula to calculate the percentage of productivity change:
The percentage change in productivity is calculated by dividing the change in productivity units by the initial productivity.
Substitution:
Resource | Last-year productivity | Current year productivity | Change in production units | Percentage of productivity change |
Labor | 3.33 | 3.64 | 0.30 | 9.01% |
Resin | 20.00 | 22.22 | 2.22 | 11.1% |
Capital | 0.10 | 0.09 | -0.01 | -10% |
Energy | 0.33 | 0.35 | 0.02 | 6.06% |
Working note:
Calculate last-year productivity for labor:
The productivity is calculated by dividing the total number of units produced by the total input used to produce the overall output.
Calculate last-year productivity for resin:
The productivity is calculated by dividing the total number of units produced by the total input used to produce the overall output.
Note: The calculation continues for capital and energy.
Calculate current year productivity for labor:
The productivity is calculated by dividing the total number of units produced by the total input used to produce the overall output.
Calculate current year productivity for resin:
The productivity is calculated by dividing the total number of units produced by the total input used to produce the overall output.
Note: The calculation continues for capital and energy.
Calculate the change in the production units for labor:
The change in production units are calculated by subtracting the current year’s productivity from the previous year’s productivity value.
Calculate the change in the production units for resin:
The change in production units are calculated by subtracting the current year’s productivity from the previous year’s productivity value.
Note: The calculation continues for capital and energy.
Calculate the percentage of productivity change for labor:
The percentage change in productivity is calculated by dividing the change in productivity units by the initial productivity.
Calculate the percentage of productivity change for resin:
The percentage change in productivity is calculated by dividing the change in productivity units by the initial productivity.
Note: The calculation continues for capital and energy.
Hence, Person GKis maintaining the manufacturing average of a 3% increase in productivity per year in all the resources except capital.
Want to see more full solutions like this?
Chapter 1 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
- What do you think is more effective in the long run, bringing in more staff during peak times or investing in cross-training and process redesign to manage demand variability better? With a Referencearrow_forward5. Glenn Dental Clinic provides general dental care to residents of Philadelphia on a walk-in basis. The clinic has started receiving complaints from patients that the waiting time is too long and has asked you to investigate whether this problem can be solved. Upon arrival, customers first receive a series of paperwork from the receptionist and fill out relevant information such as personal health records and insurance provider. The form is then handed back to the receptionist who enters the information into the computer system for the dentist to see. A dental assistant then takes an X-ray from the patient. A dentist then performs the checkup and discusses any issues with the patient. Based on conversations with staff members at the clinic, you have obtained the following information on the process: a. It takes about 5 minutes for a customer to fill out the paperwork. b. Entry of information on the paperwork into the system and verification with past records takes another 5 minutes…arrow_forwardWhy should businesses not set efficiency as the only goal? • Note: Include a reference with supportive citations in the discussion reply in your post.arrow_forward
- Do you think there are other methods to achieve efficiency, such as specialization or using technology to alleviate the bottleneck, like patient wait time?arrow_forwardIs it hard to improve efficiency in a process? Why or why not? Give an example of how to improve the efficiency of a process. Please provide a reference in APA formarrow_forwardSimplex Method Three types of paints are manufactured in one machine; Interior paint, Exterior paint and Paint for metal structures. The preparation time for each type of paint is 2, 3 and 4 minutes respectively and the processing time is 3, 2 and 1 minute. The profit contributed by each product is 12, 10 and 15 dollars respectively. The machine availability is 100 minutes and 200 minutes for machine setup. 1. Determine the optimum number of types of paints to be manufactured. 2. Determine the optimal utility value.arrow_forward
- The company LED S.A DE C.V. produces 2 devices for lamps, devices 1 and 2 that require metal parts and electrical parts. The manager wants to determine how many units of each product should be manufactured to maximize the profit for each unit, device 1 requires 2 metal parts and 4 electrical parts, device 2 requires 4 metal parts and 2 electrical parts, the company has 24 units of each material available for batch production, device 1 generates $4 profit and device 2 generates $6 profit. a) Formulate PL model. b) Solve by the graphical method and determine what is the resulting maximum profit. Translated with DeepL.com (free version)arrow_forwardQuestion 3 i. Using the Center of Gravity method, determine the optimal location (X, Y) for the new distribution center. [7 marks] [TOTAL 25 MARKS] Time (sec.) Power steering assembly firm wants to set up an assembly line which must have an output of 60 units per hour. The work elements, task times and their precedence relationships are shown in Table 2: Table 1 Work Element Immediate Predecessor(s) A 30 NONE B 26 A C 50 A D 44 B E 10 с F 20 с G 15 D.E H 30 E,G,F Required: a. Draw the precedence diagram showing the task precedence and their times b. Determine the cycle time associated with the rate of output required. [3 marks] c. What is the theoretical number of work stations required to satisfy this output rate? [3 marks] [4 marks] d. Allocate the tasks to work stations taking into consideration the precedence requirements and using the LOT rule to break ties between feasible tasks. e. Calculate the total idle time [8 marks] [3 marks] f. What is the efficiency of the line and the…arrow_forwardHyundai Motors is considering three sites-A, B, and C-at which to locate a factory to build its new electric car batteries. The goal is to locate at a minimum-cost site, where cost is measured by the annual fixed plus variable costs of production. Hyundai Motors has gathered the following data: Site Annualized Fixed Cost Variable Cost per Battery Produced A $11,000,000 $2,600 B C $2,000 $1,100 $20,000,000 $25,000,000 The firm knows it will produce between 0 and 60,000 batteries at the new plant each year, but, thus far, that is the extent of its knowledge about production plans. a) The value of volume, V, of production above which site C is recommended = batteries (round your response up to the next whole number).arrow_forward
- Hyundai Motors is considering three sites-A, B, and C-at which to locate a factory to build its new electric car batteries. The goal is to locate at a minimum-cost site, where cost is measured by the annual fixed plus variable costs of production. Hyundai Motors has gathered the following data: Site Annualized Fixed Cost Variable Cost per Battery Produced A $11,000,000 $2,500 B C $2,100 $1,050 $20,000,000 $25,000,000 The firm knows it will produce between 0 and 60,000 batteries at the new plant each year, but, thus far, that is the extent of its knowledge about production plans. a) The value of volume, V, of production above which site C is recommended = batteries (round your response up to the next whole number).arrow_forwardThe importance of keeping track of invoices and budgeting in a nursing home kitchen and how can a nutritionist utilize this in their career? Please not just a short explanation.arrow_forwardThe importance of interviewing potential food service aides and how can a nutritionist utilize this in their career? Please not just a short explanation.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Management, Loose-Leaf VersionManagementISBN:9781305969308Author:Richard L. DaftPublisher:South-Western College PubPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning
- Foundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage Learning