You are the project manager of the software installation project in the table below. You would like to find the minimum-cost schedule for your project. There is a $500-per-week penalty for each week the project is delayed beyond week 25. In addition, your project team determined that indirect project costs are $2,000 per week. 9 Activity Immediate Predecessor(s) A B C D E F G H I A A, B B D E, F G C. F Normal Time (weeks) 3 10 5 8 a. What would be your target completion week? The target completion week is week (Enter your response as an integer.) 2 8 4 7 9 Normal Cost (S) 5,000 4,000 7,000 7,000 2,000 4,000 2,000 2,000 3,000 Crash Time (weeks) 3 7 4 7 1 6 2 5 8 Crash Cost ($) 5,000 10,000 12.000 12,000 5,000 7.000 8,000 4,000 7,000

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

 

Give typed explanation not a single word hand written otherwise leave it

The answer is not 17 week. Thanks!

You are the project manager of the software installation project in the table below. You would like to find the minimum-cost schedule for your project. There is a
$500-per-week penalty for each week the project is delayed beyond week 25. addition, your project team determined that indirect project costs are 2,000 per week.
9
Crash
Cost ($)
5,000
10,000
12,000
Activity Immediate Predecessor(s)
A
B
с
D
E
F
G
H
|
A
A. B
B
D
E, F
G
C, F
Normal
Time (weeks)
a. What would be your target completion week?
The target completion week is week. (Enter your response as an integer.)
3
10
5
8
2
8
4
7
9
Normal
Cost (S)
5,000
4,000
7,000
7,000
2,000
4,000
2,000
2,000
3,000
Crash
Time (weeks)
3
7
4
7
1
6
2
5
8
12,000
5,000
7,000
8,000
4,000
7,000
Transcribed Image Text:You are the project manager of the software installation project in the table below. You would like to find the minimum-cost schedule for your project. There is a $500-per-week penalty for each week the project is delayed beyond week 25. addition, your project team determined that indirect project costs are 2,000 per week. 9 Crash Cost ($) 5,000 10,000 12,000 Activity Immediate Predecessor(s) A B с D E F G H | A A. B B D E, F G C, F Normal Time (weeks) a. What would be your target completion week? The target completion week is week. (Enter your response as an integer.) 3 10 5 8 2 8 4 7 9 Normal Cost (S) 5,000 4,000 7,000 7,000 2,000 4,000 2,000 2,000 3,000 Crash Time (weeks) 3 7 4 7 1 6 2 5 8 12,000 5,000 7,000 8,000 4,000 7,000
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 3 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.