With the data attached: 1. Draw a project network. 2. What is the critical path 3. What is the normal project cost? 4. What would be the total cost of this project if need to crash it by 1 week?
With the data attached: 1. Draw a project network. 2. What is the critical path 3. What is the normal project cost? 4. What would be the total cost of this project if need to crash it by 1 week?
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
With the data attached:
1. Draw a project network.
2. What is the critical path
3. What is the normal project cost?
4. What would be the total cost of this project if need to crash it by 1 week?

Transcribed Image Text:Activity
A
B
C
D
E
F
G
H
I
Predecessor(s)
---
A
A
--
B,D,C
D
D
E
F,G,H
Normal Time
(Wks)
5
8
7
6
8
3
3
4
6
Crash Time (Wks)
4
6
6
5
6
2
2
3
5
Normal Cost
$400
1600
800
600
1200
800
500
400
900
C
Crash Cost
$750
2200
1100
1000
2200
1000
650
600
1300
I
ZOOM
Expert Solution

Step 1
The critical path can be defined as the longest path in the project and should be completed for the project to be completed and Normal Duration and Cost mean the amount of absolute cost of the normal duration activities in the project changed by the year in accordance with the appropriate penalty or reward associated with the completion of the project.
Step by step
Solved in 2 steps with 1 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.