Case Study
SMT’s Negotiation with IBM
SMT and one other, much larger company were asked by IBM to bid on 80 more units of a particular computer product. The RFQ (request for quote) asked that the overall bid be broken down to show the hourly rate, the parts and materials component in the price, and any charges for subcontracted services. SMT quoted $1.62 million and supplied the cost breakdown as requested. The second company submitted only one total figure, $5 million, with no cost breakdown. The decision was made to negotiate with SMT.
The IBM negotiating team included two purchasing managers and two cost engineers. One cost engineer had developed
In the negotiations, SMT was represented by one of the two owners of the business, two engineers, and one cost estimator. The sessions opened with a discussion of learning curves. The IBM cost estimator demonstrated that SMT had in fact been operating on a 90% learning curve. But, he argued, it should be possible to move to an 85% curve, given the longer runs, reduced setup time, and increased continuity of workers on the job that would be possible with an order for 80 units. The owner agreed with this analysis and was willing to reduce his price by 4%.
However, as each operation in the manufacturing process was discussed, it became clear that some IBM cost estimates were too low because certain crating and shipping expenses had been overlooked. These oversights were minor, however, and in the following discussions, the two parties arrived at a common understanding of specifications and reached agreements on the costs of each manufacturing operation.
At this point, SMT representatives expressed great concern about the possibility of inflation in material costs. The IBM negotiators volunteered to include a form of price escalation in the contract, as previously agreed among themselves. IBM representatives suggested that if overall material costs changed by more than 10%, the price could be adjusted accordingly. However, if one party took the initiative to have the price revised, the other could require an analysis of all parts and materials invoices in arriving at the new price.
Another concern of the SMT representatives was that a large amount of overtime and subcontracting would be required to meet IBM’s specified delivery