Using the LPT (longest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): Sequence 1 Job 2 3 4 5 The total flow time for the sequence developed using the LPT rule = response to two decimal places). days (round your The percentage utilization for the sequence developed using the LPT rule = your response as a percentage rounded to two decimal places). % (enter The average number of jobs in the system for the sequence developed using the LPT rule jobs (round your response to two decimal places). = The average tardiness (job lateness) for the sequence developed using the LPT rule = days (round your response to two decimal places). Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): Sequence 1 Job The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. 2 3 4 5 ... The total flow time for the sequence developed using the SPT rule = days (round your response to two decimal places). The percentage utilization for the sequence developed using the SPT rule = ☐ % (enter your response as a percentage rounded to two decimal places). The average number of jobs in the system for the sequence developed using the SPT rule = jobs (round your response to two decimal places). The average tardiness (job lateness) for the sequence developed using the SPT rule = days (round your response to two decimal places). Job Date Job Received Due Date Duration (days) BR-02 225 270 25 CX-01 230 320 35 DE-06 235 360 40 RG-05 231 310 30 SY-11 228 300 15

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Using the LPT (longest processing time) decision rule for sequencing the jobs, the order
is (to resolve a tie, use the order in which the jobs were received):
Sequence
1
Job
2
3
4
5
The total flow time for the sequence developed using the LPT rule =
response to two decimal places).
days (round your
The percentage utilization for the sequence developed using the LPT rule =
your response as a percentage rounded to two decimal places).
% (enter
The average number of jobs in the system for the sequence developed using the LPT rule
jobs (round your response to two decimal places).
=
The average tardiness (job lateness) for the sequence developed using the LPT rule =
days (round your response to two decimal places).
Transcribed Image Text:Using the LPT (longest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): Sequence 1 Job 2 3 4 5 The total flow time for the sequence developed using the LPT rule = response to two decimal places). days (round your The percentage utilization for the sequence developed using the LPT rule = your response as a percentage rounded to two decimal places). % (enter The average number of jobs in the system for the sequence developed using the LPT rule jobs (round your response to two decimal places). = The average tardiness (job lateness) for the sequence developed using the LPT rule = days (round your response to two decimal places).
Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order
is (to resolve a tie, use the order in which the jobs were received):
Sequence
1
Job
The following jobs are waiting to be processed at Rick Solano's machine
center. Solano's machine center has a relatively long backlog and sets a fresh
schedule every 2 weeks, which does not disturb earlier schedules. Below are the
jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names
refer to names of clients and contract numbers. Compute all times based on
initiating work on day 241.
2
3
4
5
...
The total flow time for the sequence developed using the SPT rule = days (round your
response to two decimal places).
The percentage utilization for the sequence developed using the SPT rule = ☐ % (enter
your response as a percentage rounded to two decimal places).
The average number of jobs in the system for the sequence developed using the SPT
rule = jobs (round your response to two decimal places).
The average tardiness (job lateness) for the sequence developed using the SPT rule =
days (round your response to two decimal places).
Job
Date Job
Received
Due Date Duration (days)
BR-02
225
270
25
CX-01
230
320
35
DE-06
235
360
40
RG-05
231
310
30
SY-11
228
300
15
Transcribed Image Text:Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): Sequence 1 Job The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. 2 3 4 5 ... The total flow time for the sequence developed using the SPT rule = days (round your response to two decimal places). The percentage utilization for the sequence developed using the SPT rule = ☐ % (enter your response as a percentage rounded to two decimal places). The average number of jobs in the system for the sequence developed using the SPT rule = jobs (round your response to two decimal places). The average tardiness (job lateness) for the sequence developed using the SPT rule = days (round your response to two decimal places). Job Date Job Received Due Date Duration (days) BR-02 225 270 25 CX-01 230 320 35 DE-06 235 360 40 RG-05 231 310 30 SY-11 228 300 15
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.