The times required to complete each of eight jobs in a two-machine flow shop are shown in the table that follows. Each job must follow the same sequence, beginning with machine A and moving to machine B. a. Determine a sequence that will minimize makespan time. The sequence is _______ (A,B,C,D,E,F,G,H); (B,A,C,D,E,F,G,H); OR (E,B,G,H,D,C,A,F) b. Find machine B's idle time. Idle Time_Hrs. c. For the sequence determined in part a, how much would machine B's idle time be reduced by splitting the last two jobs in half? New idle time hrs,_ savings of hrs.__ Job a b C d e f 6 b TIME (hours) Machine A 16 3 9 8 2 12 18 20 Machine B 5 13 6 7 14 4 14 11
The times required to complete each of eight jobs in a two-machine flow shop are shown in the table that follows. Each job must follow the same sequence, beginning with machine A and moving to machine B. a. Determine a sequence that will minimize makespan time. The sequence is _______ (A,B,C,D,E,F,G,H); (B,A,C,D,E,F,G,H); OR (E,B,G,H,D,C,A,F) b. Find machine B's idle time. Idle Time_Hrs. c. For the sequence determined in part a, how much would machine B's idle time be reduced by splitting the last two jobs in half? New idle time hrs,_ savings of hrs.__ Job a b C d e f 6 b TIME (hours) Machine A 16 3 9 8 2 12 18 20 Machine B 5 13 6 7 14 4 14 11
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Please do not give solution in image format thanku

Transcribed Image Text:The times required to complete each of eight jobs
in a two-machine flow shop are shown in the
table that follows. Each job must follow the same
sequence, beginning with machine A and moving
to machine B.
a. Determine a sequence that will minimize
makespan time.
The sequence is
(A,B,C,D,E,F,G,H);
(B,A,C,D,E,F,G,H); OR (E,B,G,H,D,C,A,F)
b. Find machine B's idle time.
Idle Time _____Hrs.
c. For the sequence determined in part a, how
much would machine B's idle time be reduced by
splitting the last two jobs in half?
New idle time hrs,_____ savings of hrs._____
TIME (hours)
Job
a
b
с
d
e
f
g
h
Machine A
16
3
9
8
2
12
18
20
Machine B
5
13
6
7
14
4
14
11
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 5 steps with 5 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.