Time Estimates (Weeks) Activity Predecessor a Activity Description a Order new 1 3. machinery Plan new physical layout 2 Determine safety 1 changes in existing machinery Receive equipment 4 10 25 a Hire new employees 3 e a 12 Make plant alterations f 10 15 25 Make changes in existing machinery 5 9. 14 h Train new employees d, e 2 3. Install new d, e, f 4 machinery Relocate old d, e, f, g 5 10 machinery Conduct employee safety orientation h, i.j a. Expected activity times b. Earliest and latest activity times and activity slack c. Critical path d. Expected project duration and variance e. The probability that the mill will be fined $300,000 5.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The Stone River Textile Mill was inspected by OSHA and found to be in violation of a number of safety regulations. The OSHA inspectors ordered the mill to alter some existing machinery to make it safer (e.g., add safety guards); purchase some new machinery to replace older, dangerous machinery; and relocate some machinery to make safer passages and unobstructed entrances and exits. OSHA gave the mill only 35 weeks to make the changes; if the changes were not made by then, the mill would be fined $300,000. The mill determined the activities in a PERT network that would have to be completed and then estimated the indicated activity times, as shown in the table below. Construct the PERT network for this project and determine the following:
Time
Estimates
(Weeks)
Activity
Predecessor a
Activity Description
a
Order new
1
2
3.
machinery
Plan new physlcal
layout
b.
Determine safety
changes in existing
machinery
Receive equipment
4
10
25
a
Hire new employees
12
f
Make plant
b
10
15
25
alterations
Make changes in
existing machinery
9.
14
Train new employees
d, e
7
Install new
d, e, f
1
4
6.
machinery
Relocate old
machinery
d, e, f, g
10
Conduct employee
safety orientation
h, i.j
a. Expected activity times
b. Earliest and latest activity times and activity slack
c. Critical path
d. Expected project duration and variance
e. The probability that the mill will be fined $300,000
日
7.
3.
Transcribed Image Text:Time Estimates (Weeks) Activity Predecessor a Activity Description a Order new 1 2 3. machinery Plan new physlcal layout b. Determine safety changes in existing machinery Receive equipment 4 10 25 a Hire new employees 12 f Make plant b 10 15 25 alterations Make changes in existing machinery 9. 14 Train new employees d, e 7 Install new d, e, f 1 4 6. machinery Relocate old machinery d, e, f, g 10 Conduct employee safety orientation h, i.j a. Expected activity times b. Earliest and latest activity times and activity slack c. Critical path d. Expected project duration and variance e. The probability that the mill will be fined $300,000 日 7. 3.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 6 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.