Case Study: Ruritania public health project contract provision Background The Ministry of Finance in Ruritania, a tropical country, has allocated the equivalent of  US $100 million to the Ministry of Health (MOH) for the purpose of expanded health  services delivery in the southern part of the country (it is anticipated that necessary  funds would be derived from projected export earnings and that no support from  international institutions would be necessary). The MOH has conducted an  international competition in accordance with its new procurement law and regulation.  It has selected a consortium (OPTIMA) of international and domestic contractors and  suppliers to execute the project. Project scope of work: The principal elements of the project scope of work are the following: 1. Repair and rehabilitation of three (3) existing hospitals, selected by the MOH; 2. Construction of five (5) new health clinics, especially for victims of AIDS, at sites  to be determined by the MOH; and 3. Creation of low-cost facility for the benefit of orphans and other child-centred  activities in Ruritatnia. Contract provisions: On January 1, 2005, the contract was signed between the Ruritania MOH and  OPTIMA. The contract called for OPTIMA to begin on February 1, 2006 and to  complete the project by August 1, 2006. The MOH agreed to pay a fixed sum of US  $95 million, payable at performance milestones as follows: a) Twenty (20) % advance payment (US $19 million) upon signing of the contract  and posting of a satisfactory advance payment bond or guarantee; b) Thirty (30) % progress payment upon satisfactory completion of detailed  engineering plans regarding the repair and rehabilitation of the 3 hospitals and  construction of the three (3) new health clinics; c) Thirty (30) % payment upon substantial completion of the repair and  rehabilitation and construction work outlined above; d) Ten (10) % payment upon establishment and initial operation of the credit  facility; and e) Ten (10) % retention payment upon submission of a satisfactory final report. The contract also provided that there would be a ten (10) % bonus if the contract were  completed by April 1, 2006 and a penalty of 0.05% of the contract price for each day  completion was delayed beyond August 1, 2006. The contract provided that it could  be amended by the parties at any time and it included standard provisions concerning  the termination of the contract for convenience or default. It was agreed that any disputes concerning contract performance would be resolved in accordance with the  Rules of Conciliation and Arbitration of the United Nations Commission on  International Trade Law (UNCITRAL). The contract signing was accompanied by considerable public ceremony and press  coverage and OPTIMA began performance of the contract with much enthusiasm.  OPTIMA immediately posted performance security in the form of commercial letter of  credit, valid for two (2) years from the date of contract signing and payable upon  demand, provided the demand was accompanied by a certificate from the Minister of  Health that OPTIMA had failed to perform. With the initial US $19 million payment received on February 1, 2006, OPTIMA was  able to prepare the engineering designs and to mobilise its equipment for construction.  On July 1, 2006, OPTIMA submitted its engineering plans for review by the MOH and submitted its second invoice for payment of US $19 million. OPTIMA then began to  perform its obligations regarding the credit facility. In August, 2006, however, the Ruritania Ministry of Finance advised the MOH that,  due to failing prices for exports, and adverse weather affecting production levels, the  revenue from export earnings was failing short of expectations. Accordingly, the MOH  would now be allocated only US $30 million in 2007, and US $35 million in 2008. In view of these developments the MOH project manager determined not to make  payment against the second invoice of OPTIMA until a full review of the project status  could be completed. The project manager assembled a team of advisers (engineer,  lawyer, financial analyst) to conduct this review. When the second payment from the MOH was not forthcoming on timely basis,  OPTIMA became concerned about the implementation of the project. The OPTIMA  project manager assembled a team of advisers (engineer, lawyer, financial analyst) to  review the status of the project. Consider these questions: OPTIMA: d) What advice would you give the OPTIMA project manager? e) Should OPTIMA stop work until payment is received? f) Should the project manager of OPTIMA begin action to terminate the contract?  On what grounds?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question
100%

Case Study: Ruritania public health project contract provision
Background
The Ministry of Finance in Ruritania, a tropical country, has allocated the equivalent of 
US $100 million to the Ministry of Health (MOH) for the purpose of expanded health 
services delivery in the southern part of the country (it is anticipated that necessary 
funds would be derived from projected export earnings and that no support from 
international institutions would be necessary). The MOH has conducted an 
international competition in accordance with its new procurement law and regulation. 
It has selected a consortium (OPTIMA) of international and domestic contractors and 
suppliers to execute the project.
Project scope of work:
The principal elements of the project scope of work are the following:
1. Repair and rehabilitation of three (3) existing hospitals, selected by the MOH;
2. Construction of five (5) new health clinics, especially for victims of AIDS, at sites 
to be determined by the MOH; and
3. Creation of low-cost facility for the benefit of orphans and other child-centred 
activities in Ruritatnia.
Contract provisions:
On January 1, 2005, the contract was signed between the Ruritania MOH and 
OPTIMA. The contract called for OPTIMA to begin on February 1, 2006 and to 
complete the project by August 1, 2006. The MOH agreed to pay a fixed sum of US 
$95 million, payable at performance milestones as follows:
a) Twenty (20) % advance payment (US $19 million) upon signing of the contract 
and posting of a satisfactory advance payment bond or guarantee;
b) Thirty (30) % progress payment upon satisfactory completion of detailed 
engineering plans regarding the repair and rehabilitation of the 3 hospitals and 
construction of the three (3) new health clinics;
c) Thirty (30) % payment upon substantial completion of the repair and 
rehabilitation and construction work outlined above;
d) Ten (10) % payment upon establishment and initial operation of the credit 
facility; and
e) Ten (10) % retention payment upon submission of a satisfactory final report.
The contract also provided that there would be a ten (10) % bonus if the contract were 
completed by April 1, 2006 and a penalty of 0.05% of the contract price for each day 
completion was delayed beyond August 1, 2006. The contract provided that it could 
be amended by the parties at any time and it included standard provisions concerning 
the termination of the contract for convenience or default. It was agreed that any
disputes concerning contract performance would be resolved in accordance with the 
Rules of Conciliation and Arbitration of the United Nations Commission on 
International Trade Law (UNCITRAL).
The contract signing was accompanied by considerable public ceremony and press 
coverage and OPTIMA began performance of the contract with much enthusiasm. 
OPTIMA immediately posted performance security in the form of commercial letter of 
credit, valid for two (2) years from the date of contract signing and payable upon 
demand, provided the demand was accompanied by a certificate from the Minister of 
Health that OPTIMA had failed to perform.
With the initial US $19 million payment received on February 1, 2006, OPTIMA was 
able to prepare the engineering designs and to mobilise its equipment for construction. 
On July 1, 2006, OPTIMA submitted its engineering plans for review by the MOH and
submitted its second invoice for payment of US $19 million. OPTIMA then began to 
perform its obligations regarding the credit facility.
In August, 2006, however, the Ruritania Ministry of Finance advised the MOH that, 
due to failing prices for exports, and adverse weather affecting production levels, the 
revenue from export earnings was failing short of expectations. Accordingly, the MOH 
would now be allocated only US $30 million in 2007, and US $35 million in 2008.
In view of these developments the MOH project manager determined not to make 
payment against the second invoice of OPTIMA until a full review of the project status 
could be completed. The project manager assembled a team of advisers (engineer, 
lawyer, financial analyst) to conduct this review.
When the second payment from the MOH was not forthcoming on timely basis, 
OPTIMA became concerned about the implementation of the project. The OPTIMA 
project manager assembled a team of advisers (engineer, lawyer, financial analyst) to 
review the status of the project.
Consider these questions:
OPTIMA:
d) What advice would you give the OPTIMA project manager?
e) Should OPTIMA stop work until payment is received?
f) Should the project manager of OPTIMA begin action to terminate the contract? 
On what grounds?
General:
How does a contractor protect itself from the risk of slow payment from the 
government?

Expert Solution
steps

Step by step

Solved in 5 steps

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.