Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. Use Table B. TIME IN DAYS Immediate Activity Predecessor Optimistic Most Likely Pessimistic A 5 6 В 11 6 8 11 9 12 15 D 6. F 7 H B 4 I H 8. End E, G, I Click here for the Excel Data File a. What is the probability that the project can be completed in 24 days or less? In 21 days or less? (Round your te and z values to 2 decimal places and "Standard deviation" to 3 decimal places. Round your final answers to 4 decimal places.) Days Probability 24 days or less 21 days or less
Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. Use Table B. TIME IN DAYS Immediate Activity Predecessor Optimistic Most Likely Pessimistic A 5 6 В 11 6 8 11 9 12 15 D 6. F 7 H B 4 I H 8. End E, G, I Click here for the Excel Data File a. What is the probability that the project can be completed in 24 days or less? In 21 days or less? (Round your te and z values to 2 decimal places and "Standard deviation" to 3 decimal places. Round your final answers to 4 decimal places.) Days Probability 24 days or less 21 days or less
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
100%

Transcribed Image Text:Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities
listed in the following table. Use Table B.
ΤΙME IN DAYS
Immediate
Activity
Predecessor
Optimistic Most Likely Pessimistic
A
7
B
8
8
11
C
A
6
8
11
9.
12
15
E
6
F
D
7
G
F
2
3
7
H
B
4
4
I
H
7
8
End
E, G, I
Click here for the Excel Data File
a. What is the probability that the project can be completed in 24 days or less? In 21 days or less? (Round your te and z values to 2
decimal places and "Standard deviation" to 3 decimal places. Round your final answers to 4 decimal places.)
Days
Probability
24 days or less
21 days or less

Transcribed Image Text:b. Suppose it is now the end of the seventh day and that activities A and B have been completed while activity D is 50 percent
completed. Time estimates for the completion of activity D are 5, 6, and 7. Activities C and H are ready to begin. Determine the
probability of finishing the project by day 24 and the probability of finishing by day 21. (Round your intermediate calculations to 3
decimal places and final answers to 4 decimal places.)
Probability
Day 24
Day 21
c. The partners have decided that shortening the project by two days would be beneficial. They have estimated the daily crashing
costs for each activity in thousands, as shown in the following table. Which activities should be crashed?
Activity
First Crash
Second Crash
$8
$10
$9
$7
$8
$10
$11
$10
D
E
$9
$9
F
G
$7
$6
H
$8
First Activity to Crash
Second Set of Activities to Crash
o o 00
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 8 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.