The throughput time is minutes ​(enter your response as a whole​ number). ​b) The bottleneck time of this work cell is minutes per unit ​(enter your response as a whole​ number) ​c) is the bottleneck station. If the firm operates 11 hours per​ day, 6 days per​ week, the weekly capacity of this work cell is units​ (enter your response as a whole​ number).

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%
The​ three-station work cell at Pullman​ Mfg., Inc. is illustrated in the figure below. It has two machines at station 1 in parallel​ (i.e., the product needs to go through only one of the two machines before proceeding to station​ 2).
 
​a) The throughput time is
minutes ​(enter your response as a whole​ number).
​b) The bottleneck time of this work cell is
minutes per unit ​(enter your response as a whole​ number)
​c) is the bottleneck station.
If the firm operates 11 hours per​ day, 6 days per​ week, the weekly capacity of this work cell is
units​ (enter your response as a whole​ number).
The image represents a production flowchart with three stations involved in the manufacturing process.

1. **Station 1**: 
   - Two machines, Machine A and Machine B, operate independently at this station.
   - Both Machine A and Machine B take 20 minutes per unit.

2. **Station 2**:
   - This station processes each unit in 3 minutes.
   - Units from both Machine A and Machine B are directed to this station.

3. **Station 3**:
   - This station processes each unit in 4 minutes.
   - It receives units directly from Station 2.

Arrows indicate the direction of unit flow through the stations. The process begins at Station 1, moves to Station 2, and then proceeds to Station 3.
Transcribed Image Text:The image represents a production flowchart with three stations involved in the manufacturing process. 1. **Station 1**: - Two machines, Machine A and Machine B, operate independently at this station. - Both Machine A and Machine B take 20 minutes per unit. 2. **Station 2**: - This station processes each unit in 3 minutes. - Units from both Machine A and Machine B are directed to this station. 3. **Station 3**: - This station processes each unit in 4 minutes. - It receives units directly from Station 2. Arrows indicate the direction of unit flow through the stations. The process begins at Station 1, moves to Station 2, and then proceeds to Station 3.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.