TIT: The soil in a borrow pit has a void ratio of 0.90. A fill of volume 20000 m³ has be constructed with an in place dry density of 19.2 kN/m³. If the owner of borrow pit to be compensated t rate 2.5 per cubic metre of excavation, determine the cost of compensation. Take G = 2.68, Yw = 9.81 kN/m³.

Principles of Foundation Engineering (MindTap Course List)
8th Edition
ISBN:9781305081550
Author:Braja M. Das
Publisher:Braja M. Das
Chapter16: Soil Improvement And Ground Modification
Section: Chapter Questions
Problem 16.12P
icon
Related questions
Question
The soil in a borrow pit has a void ratio of 0.90. A fill of volume 20000 m³ has
to be constructed with an in place dry density of 19.2 kN/m³. If the owner of borrow pit to be compensated
at rate 2.5 per cubic metre of excavation, determine the cost of compensation.
Take G= 2.68, Yw = 9.81 kN/m³.
רןןןדרי
Transcribed Image Text:The soil in a borrow pit has a void ratio of 0.90. A fill of volume 20000 m³ has to be constructed with an in place dry density of 19.2 kN/m³. If the owner of borrow pit to be compensated at rate 2.5 per cubic metre of excavation, determine the cost of compensation. Take G= 2.68, Yw = 9.81 kN/m³. רןןןדרי
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Pricing excavation and backfill
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781305081550
Author:
Braja M. Das
Publisher:
Cengage Learning
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning