The MPS start quantities for products A and B are given as follows: Product A B Product A B 1 2 20 30 O a. 5.15 Ob 10.35 c. 6.25 Lot size 20 3 20 The lot sizes, routing and standard time data for the products are given below. Assume that lead time is 1 week for each operation. 30 Operation 4 20 30 1 of 2 2 of 2 1 of 2 2 of 2 Week 5 20 Workstation 6 WS 100 WS 200 WS 100 WS 200 Setup time per batch 7 (hr) 0.100 0.250 0.100 0.200 8 Processing time per unit (hr) 0.125 0.300 0.105 0.200 Determine the capacity requirement (in hours) for WS 200 for week 4 using the resource profile method.
The MPS start quantities for products A and B are given as follows: Product A B Product A B 1 2 20 30 O a. 5.15 Ob 10.35 c. 6.25 Lot size 20 3 20 The lot sizes, routing and standard time data for the products are given below. Assume that lead time is 1 week for each operation. 30 Operation 4 20 30 1 of 2 2 of 2 1 of 2 2 of 2 Week 5 20 Workstation 6 WS 100 WS 200 WS 100 WS 200 Setup time per batch 7 (hr) 0.100 0.250 0.100 0.200 8 Processing time per unit (hr) 0.125 0.300 0.105 0.200 Determine the capacity requirement (in hours) for WS 200 for week 4 using the resource profile method.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
![The MPS start quantities for products A and B are given as follows:
Week
5n
Product
6.
20
30
4.
20
30
20
20
B
The lot sizes, routing and standard time data for the products are given below. Assume that lead
time is 1 week for each operation.
Setup time
per batch
(hr)
0.100
0.250
0.100
Processing
time per unit
(hr)
0.125
Product
Lot size
Operation
Workstation
1 of 2
2 of 2
1 of 2
WS 100
WS 200
WS 100
WS 200
A
20
0.300
0.105
30
2 of 2
0.200
0.200
Determine the capacity requirement (in hours) for WS 200 for week 4 using the resource profile
method.
O a 5.15
Ob. 10.35
Oc. 6.25](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F17705ca7-8b96-4d25-91b8-68e81eac83bb%2F9d0e5e99-393a-4981-8023-1e85651695fc%2F8m18hb8_processed.png&w=3840&q=75)
Transcribed Image Text:The MPS start quantities for products A and B are given as follows:
Week
5n
Product
6.
20
30
4.
20
30
20
20
B
The lot sizes, routing and standard time data for the products are given below. Assume that lead
time is 1 week for each operation.
Setup time
per batch
(hr)
0.100
0.250
0.100
Processing
time per unit
(hr)
0.125
Product
Lot size
Operation
Workstation
1 of 2
2 of 2
1 of 2
WS 100
WS 200
WS 100
WS 200
A
20
0.300
0.105
30
2 of 2
0.200
0.200
Determine the capacity requirement (in hours) for WS 200 for week 4 using the resource profile
method.
O a 5.15
Ob. 10.35
Oc. 6.25
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.