relesses to meet the gross requirements. Lead time is one week. (Leave the cells blank, whenever zero (0) is require NEEK NUMBER ITEM 3 1 2 3 4 Gross requirements On-hand Net requirements Planned-order receipt Planned-order release se 45 35 Period Grass requirements 80 45 60 Scheduled receipts Item: J Он: 35 LT: 1 SS: 0 Q L4L Projected available balance Net requirements Planned order receipts Planned order releases
relesses to meet the gross requirements. Lead time is one week. (Leave the cells blank, whenever zero (0) is require NEEK NUMBER ITEM 3 1 2 3 4 Gross requirements On-hand Net requirements Planned-order receipt Planned-order release se 45 35 Period Grass requirements 80 45 60 Scheduled receipts Item: J Он: 35 LT: 1 SS: 0 Q L4L Projected available balance Net requirements Planned order receipts Planned order releases
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
Related questions
Question
100%

Transcribed Image Text:In this educational example, you are provided with an MRP (Material Requirements Planning) schedule for Item J. The task is to fill out the table with correct net requirements, planned-order receipts, and planned-order releases to meet the gross requirements provided. The lead time is one week, and you should leave the cells blank when the value is zero.
**Initial Information:**
- Item J
- On-hand inventory: 35
- Lead time (LT): 1 week
- Safety stock (SS): 0
- Order quantity (Q): Lot-for-lot (L4L)
**MRP Table Breakdown:**
1. **Input Data (Top Table):**
- **Gross Requirements:**
- Week 2: 80
- Week 4: 45
- Week 5: 60
- **On-hand:** 35
2. **Output Data (Bottom Table):**
- **Period Columns (1 to 5):**
- **Gross Requirements:** Only periods where there are requirements are filled.
- **Scheduled Receipts, Net Requirements, Planned Order Receipts, Planned Order Releases:** These fields need to be updated based on calculations.
**Explanation for Calculation:**
- Begin with on-hand inventory and calculate for each period.
- Determine net requirements by considering the on-hand balance, scheduled receipts, and gross requirements.
- The planned-order receipt is the amount needed to meet net requirements, considering the lead time.
- Planned-order release is scheduled to ensure the receipt aligns with the lead time.
**Note:** This example assumes a blank cell indicates a zero value in the context of MRP planning. Calculations should derive when to order and how much based on these stipulations, ensuring inventory levels meet production requirements without excess stock.
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Marketing
Marketing
ISBN:
9780357033791
Author:
Pride, William M
Publisher:
South Western Educational Publishing

Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Marketing
Marketing
ISBN:
9780357033791
Author:
Pride, William M
Publisher:
South Western Educational Publishing

Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Contemporary Marketing
Marketing
ISBN:
9780357033777
Author:
Louis E. Boone, David L. Kurtz
Publisher:
Cengage Learning