The manager at East Coast Manufacturing organizes costs to prepare the Costs of Quality report. The manger compiled the following data: Employee training $161,000 Warranty costs $185,000 Rework $263,000 Product testing $190,000 Cost of rejected units $40,000 Sales return processing costs $35,000 Lost profits from lost sales $720,000 Inspection at State I of Production $100,000 Preventative maintenance $105,000 Improved equipment $115,000 What of the following cost is the total cost of quality the manager should use to report the costs in the internal failure cost category? Question 12 options: $303,000 $263,000 $190,000 $649,000 $185,000
The manager at East Coast
Employee training $161,000
Warranty costs $185,000
Rework $263,000
Product testing $190,000
Cost of rejected units $40,000
Sales return
Lost profits from lost sales $720,000
Inspection at State I of Production $100,000
Preventative maintenance $105,000
Improved equipment $115,000
What of the following cost is the total cost of quality the manager should use to report the costs in the internal failure cost category?
Question 12 options:
|
$303,000
|
|
$263,000
|
|
$190,000
|
|
$649,000
|
|
$185,000
|
Trending now
This is a popular solution!
Step by step
Solved in 2 steps