The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item LT (week) Amount on hand Click here for the Excel Data File B (2) Additional units End Item End 1 O C The latest week B 3 10 D (3) E (2) 649 C D 4 25 E 2 11 F 1 26 129 G 7 E (2) F(3) G (2) E (2) H (4) a. If 24 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.) H 1 0 b. An order for the end item is scheduled to be shipped at the start of week 16. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don't need to develop an MRP plan for this part either.)
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item LT (week) Amount on hand Click here for the Excel Data File B (2) Additional units End Item End 1 O C The latest week B 3 10 D (3) E (2) 649 C D 4 25 E 2 11 F 1 26 129 G 7 E (2) F(3) G (2) E (2) H (4) a. If 24 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.) H 1 0 b. An order for the end item is scheduled to be shipped at the start of week 16. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don't need to develop an MRP plan for this part either.)
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
![**Assembly Components and Requirements**
The following table lists the components needed to assemble an end item, lead times, and quantities on hand:
| Item | End | B | C | D | E | F | G | H |
|------|-----|---|---|---|---|---|---|---|
| LT (week) | 1 | 3 | 4 | 4 | 2 | 1 | 2 | 1 |
| Amount on hand | 0 | 10 | 9 | 25 | 11 | 26 | 7 | 0 |
**Diagram Explanation:**
The diagram illustrates the hierarchical structure of components needed for assembling the end item.
- End Item
- B (2)
- E (2)
- F (3)
- C (2)
- G (2)
- E (2)
- D (3)
- H (4)
- E (2)
**Problem A:**
a. If 24 units of the end item are to be assembled, how many additional units of E are needed? *(Hint: You don't need to develop an MRP plan to determine this.)*
**Answer Box:** `[Additional units]`
**Problem B:**
b. An order for the end item is scheduled to be shipped at the start of week 16. What is the latest week that the order can be started and still be ready to ship on time? *(Hint: You don't need to develop an MRP plan for this part either.)*
**Answer Box:** `[The latest week]`](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fa7b40a41-3ef4-4ce0-8815-6254b6673f01%2F42d43653-335f-44f7-ae7d-d8b4d017f91f%2Fdj5ulw_processed.jpeg&w=3840&q=75)
Transcribed Image Text:**Assembly Components and Requirements**
The following table lists the components needed to assemble an end item, lead times, and quantities on hand:
| Item | End | B | C | D | E | F | G | H |
|------|-----|---|---|---|---|---|---|---|
| LT (week) | 1 | 3 | 4 | 4 | 2 | 1 | 2 | 1 |
| Amount on hand | 0 | 10 | 9 | 25 | 11 | 26 | 7 | 0 |
**Diagram Explanation:**
The diagram illustrates the hierarchical structure of components needed for assembling the end item.
- End Item
- B (2)
- E (2)
- F (3)
- C (2)
- G (2)
- E (2)
- D (3)
- H (4)
- E (2)
**Problem A:**
a. If 24 units of the end item are to be assembled, how many additional units of E are needed? *(Hint: You don't need to develop an MRP plan to determine this.)*
**Answer Box:** `[Additional units]`
**Problem B:**
b. An order for the end item is scheduled to be shipped at the start of week 16. What is the latest week that the order can be started and still be ready to ship on time? *(Hint: You don't need to develop an MRP plan for this part either.)*
**Answer Box:** `[The latest week]`
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.