The following table lists the components needed to assemble an end item, the manufacturing or purchase lead times (in weeks) for typical lot sizes, amount on hand, and the direct components of each item and, in brackets, the number of each component for each parent.   Item   Lead Time   Amount on Hand   Direct Components   End item 1 - L(2), C(1), K(3)   L 2 14 B(2), J(3)          C 3 30 G(2), B(2)          K 1 25 H(4), B(2)          B 4 15     J 2 10     G 4 5     H 2 -     a. Not available in Connect. b. If 46 units of the end item are to be assembled, how many additional units of B are needed? (You don’t need to develop the MRP tables.) Additional units ____ c. An order for 46 units of the end item is scheduled to be shipped at the start of week 11. What is the latest week that the components of the order can be started and the order still be ready to ship on time? (You don’t need to develop the MRP tables.) The latest week ____

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

The following table lists the components needed to assemble an end item, the manufacturing or purchase lead times (in weeks) for typical lot sizes, amount on hand, and the direct components of each item and, in brackets, the number of each component for each parent.

  Item   Lead Time   Amount on
Hand
  Direct
Components
  End item 1 - L(2), C(1), K(3)
  L 2 14 B(2), J(3)       
  C 3 30 G(2), B(2)       
  K 1 25 H(4), B(2)       
  B 4 15  
  J 2 10  
  G 4 5  
  H 2 -  
 


a. Not available in Connect.

b. If 46 units of the end item are to be assembled, how many additional units of B are needed? (You don’t need to develop the MRP tables.)

Additional units ____

c. An order for 46 units of the end item is scheduled to be shipped at the start of week 11. What is the latest week that the components of the order can be started and the order still be ready to ship on time? (You don’t need to develop the MRP tables.)

The latest week ____

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.