The following table gives data on nomal time and cost and crash time and cost for a project. Precedence Normal Time (weeks) Cost (K) Time (weeks) Activity Crash activity Cost (K) A 300 2 400 B A 3 30 3 30 A 720 7 810 A 420 580 250 4 300 F D 20 1 40 G C, E, F 320 4 410 4 400 3 470 G 13 780 10 900 J H 10 1000 1200 a) Draw the network b) Identify the critical path c) What is the normal project duration and associated cost? d) Find the total float, free float for each activity. e) Crash the relevant activities systematically and determine the optimum tim e and cost.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Need help with sub question c, d and e.

The following table gives data on nomal time and cost and crash time and cost for a
project.
Activity
Precedence
Crash
Normal
Time (weeks) Cost (K)
Time (weeks)
activity
Cost (K)
A
3
300
2
400
A
3
30
3
30
C
A
720
7
810
D
A
7
420
580
300
40
5
250
4
F
D
2
20
1
G
C, E, F
320
4
410
G
4
400
3
470
G
13
780
10
900
J
H
10
1000
9.
1200
a) Draw the network
b) Identify the critical path
c) What is the normal project duration and associated cost?
d) Find the total float, free float for each activity.
e) Crash the relevant activities systematically and determine the optimum tim
e and cost.
Transcribed Image Text:The following table gives data on nomal time and cost and crash time and cost for a project. Activity Precedence Crash Normal Time (weeks) Cost (K) Time (weeks) activity Cost (K) A 3 300 2 400 A 3 30 3 30 C A 720 7 810 D A 7 420 580 300 40 5 250 4 F D 2 20 1 G C, E, F 320 4 410 G 4 400 3 470 G 13 780 10 900 J H 10 1000 9. 1200 a) Draw the network b) Identify the critical path c) What is the normal project duration and associated cost? d) Find the total float, free float for each activity. e) Crash the relevant activities systematically and determine the optimum tim e and cost.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 1 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.