a Using the data in the table, calculate the expected time (ET) and VAnace uI expected time (ET) Job Predecessor a mb variance number Job(s) 4 56 12 3 --- 23 4 36 9 C C, D 4512 C,E 14 7 b [Skotch the network diagram for the project on a sheet of paper YOU DO NOT HAVE TO SUBMIT THE SKETCH AS PART OF YOUR ANSWER] c List each unique path through the network For example, "A. B,C would indicate a path consisting of activity A, followed by activity B, which is followed by activity C d. Indicate the critical path (You can do this by inspecting the palhs- you do not bave to calculate ES, EF, LS, LF.) What is the expected completion time for the project? e. What is the probability that the project wil be completed in 25 days or less? 1. What is the probability that the project will take more than 25 days to complete?
a Using the data in the table, calculate the expected time (ET) and VAnace uI expected time (ET) Job Predecessor a mb variance number Job(s) 4 56 12 3 --- 23 4 36 9 C C, D 4512 C,E 14 7 b [Skotch the network diagram for the project on a sheet of paper YOU DO NOT HAVE TO SUBMIT THE SKETCH AS PART OF YOUR ANSWER] c List each unique path through the network For example, "A. B,C would indicate a path consisting of activity A, followed by activity B, which is followed by activity C d. Indicate the critical path (You can do this by inspecting the palhs- you do not bave to calculate ES, EF, LS, LF.) What is the expected completion time for the project? e. What is the probability that the project wil be completed in 25 days or less? 1. What is the probability that the project will take more than 25 days to complete?
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Question 9
![/mail/u/1/#inbox/FMfcgzGlIMH ZIZQjIFwwMxzWIkgFFB
O Maps
Q Search mail
1 of 73,747
11:39 AM (1 minute ag
bright effah kyeremeh <brighteffahkyeremeh@gmail.com>
to me -
QUESTION 9
The folowing table represents the set of activities required to complele a project, along with their time estimates for PERT calculations
a Using the data in the table, calculate the expected time (ET) and variance for each activity
Predecessor
a mb
Inumber Job(s)
expected
time (ET)
Job
variance
50
45 6
12 3
23 4
369
45 12
A
C
B
D
B
C, D
C, E 14 7
F
b [Sketch the network diagram for the project on a sheet of paper YOU DO NOI HAVE TO SUBMIT THE SKETCH AS PART OF YOUR ANSWER].
c. List each unique path through the network For example, "A, B, C" would indicate a path consisting of activity A, followed by activity B, which is followed by activity C.
d. Indicate the critical path. (You can do this by inspecting the paths - you do not have to calculate ES, EF, LS, LF.) What is the expected completion time for the project?
e. What is the probability that the project will be completed in 25 days or less?
f. What is the probability that the project will take more than 25 days to complete?
rarch
W
2°C Sunny
ho
%23
%24
&
3
4
6
7
8.
9.
E
Y
4
5.
6)
F
K
L
D.](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fce6bcfe6-8fd8-4d05-bdd9-202cdcc156fa%2Fc73f8702-15fb-43a2-b4dd-74414b4a41f3%2Fzjrz7uu_processed.jpeg&w=3840&q=75)
Transcribed Image Text:/mail/u/1/#inbox/FMfcgzGlIMH ZIZQjIFwwMxzWIkgFFB
O Maps
Q Search mail
1 of 73,747
11:39 AM (1 minute ag
bright effah kyeremeh <brighteffahkyeremeh@gmail.com>
to me -
QUESTION 9
The folowing table represents the set of activities required to complele a project, along with their time estimates for PERT calculations
a Using the data in the table, calculate the expected time (ET) and variance for each activity
Predecessor
a mb
Inumber Job(s)
expected
time (ET)
Job
variance
50
45 6
12 3
23 4
369
45 12
A
C
B
D
B
C, D
C, E 14 7
F
b [Sketch the network diagram for the project on a sheet of paper YOU DO NOI HAVE TO SUBMIT THE SKETCH AS PART OF YOUR ANSWER].
c. List each unique path through the network For example, "A, B, C" would indicate a path consisting of activity A, followed by activity B, which is followed by activity C.
d. Indicate the critical path. (You can do this by inspecting the paths - you do not have to calculate ES, EF, LS, LF.) What is the expected completion time for the project?
e. What is the probability that the project will be completed in 25 days or less?
f. What is the probability that the project will take more than 25 days to complete?
rarch
W
2°C Sunny
ho
%23
%24
&
3
4
6
7
8.
9.
E
Y
4
5.
6)
F
K
L
D.
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 2 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.