The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. Job BR-02 CX-01 DE-06 RG-05 SY-11 Date Job Received 231 228 225 230 235 Due Date Duration (days) 310 300 270 320 360 30 15 25 35 40

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
he average tardiness (job lateness) for the sequence developed using the EDD rule =
vo decimal places).
Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the
rder in which the jobs were received):
Sequence
Job
1
2
I
3
4
5
he total flow time for the sequence developed using the SPT rule =
ecimal places).
he percentage utilization for the sequence developed using the SPT rule =
Dunded to two decimal places).
he average number of jobs in the system for the sequence developed using the SPT rule =
esponse to two decimal places).
he average tardiness (job lateness) for the sequence developed using the SPT rule =
vo decimal places).
Sequence
1
2
3
4
days (round your response to
days (round your response to two
5
sing the LPT (longest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order
n which the jobs were received):
he total flow time for the sequence developed using the LPT rule =
ecimal places).
% (enter your response as a percentage
Job
jobs (round your
days (round your response to
days (round your response to two
he percentage utilization for the sequence developed using the LPT rule=% (enter your response as a percentage
Dunded to two decimal places).
C
The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a
relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below
are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients
and contract numbers. Compute all times based on initiating work on day 241.
Job
BR-02
CX-01
DE - 06
RG-05
SY - 11
Date Job
Received
231
228
225
230
235
Due Date Duration (days)
310
300
270
320
360
30
15
25
35
40
Next
Transcribed Image Text:he average tardiness (job lateness) for the sequence developed using the EDD rule = vo decimal places). Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the rder in which the jobs were received): Sequence Job 1 2 I 3 4 5 he total flow time for the sequence developed using the SPT rule = ecimal places). he percentage utilization for the sequence developed using the SPT rule = Dunded to two decimal places). he average number of jobs in the system for the sequence developed using the SPT rule = esponse to two decimal places). he average tardiness (job lateness) for the sequence developed using the SPT rule = vo decimal places). Sequence 1 2 3 4 days (round your response to days (round your response to two 5 sing the LPT (longest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order n which the jobs were received): he total flow time for the sequence developed using the LPT rule = ecimal places). % (enter your response as a percentage Job jobs (round your days (round your response to days (round your response to two he percentage utilization for the sequence developed using the LPT rule=% (enter your response as a percentage Dunded to two decimal places). C The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. Job BR-02 CX-01 DE - 06 RG-05 SY - 11 Date Job Received 231 228 225 230 235 Due Date Duration (days) 310 300 270 320 360 30 15 25 35 40 Next
1
2
3
4
LO
5
The total flow time for the sequence developed using the SPT rule =
decimal places).
The percentage utilization for the sequence developed using the SPT rule= % (enter your response as a percentage
rounded to two decimal places).
The average number of jobs in the system for the sequence developed using the SPT rule =
response to two decimal places).
The average tardiness (job lateness) for the sequence developed using the SPT rule =
two decimal places).
Sequence
1
2
3
days (round your response to two
Using the LPT (longest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order
in which the jobs were received):
4
5
The total flow time for the sequence developed using the LPT rule =
decimal places).
Job
jobs (round your
days (round your response to
days (round your response to two
The percentage utilization for the sequence developed using the LPT rule = % (enter your response as a percentage
rounded to two decimal places).
The average number of jobs in the system for the sequence developed using the LPT rule =
response to two decimal places).
The average tardiness (job lateness) for the sequence developed using the LPT rule =
two decimal places).
jobs (round your
days (round your response to
The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a
relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below
are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients
and contract numbers. Compute all times based on initiating work on day 241.
Job
BR-02
CX - 01
DE - 06
RG-05
SY - 11
Date Job
Received
231
228
225
230
235
Due Date Duration (days)
310
300
270
320
360
30
15
25
35
40
S
Transcribed Image Text:1 2 3 4 LO 5 The total flow time for the sequence developed using the SPT rule = decimal places). The percentage utilization for the sequence developed using the SPT rule= % (enter your response as a percentage rounded to two decimal places). The average number of jobs in the system for the sequence developed using the SPT rule = response to two decimal places). The average tardiness (job lateness) for the sequence developed using the SPT rule = two decimal places). Sequence 1 2 3 days (round your response to two Using the LPT (longest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): 4 5 The total flow time for the sequence developed using the LPT rule = decimal places). Job jobs (round your days (round your response to days (round your response to two The percentage utilization for the sequence developed using the LPT rule = % (enter your response as a percentage rounded to two decimal places). The average number of jobs in the system for the sequence developed using the LPT rule = response to two decimal places). The average tardiness (job lateness) for the sequence developed using the LPT rule = two decimal places). jobs (round your days (round your response to The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. Job BR-02 CX - 01 DE - 06 RG-05 SY - 11 Date Job Received 231 228 225 230 235 Due Date Duration (days) 310 300 270 320 360 30 15 25 35 40 S
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.