The Corner Cleaners 24-hour laundromat has 16 washing machines. A machine breaks down every 20 days (exponentially distributed). The repair service the laundromat contracts takes an average of one day to repair a machine (exponentially distributed). A washing machine averages $5 per hour inrevenue. The laundromat is considering a new repair service that guarantees repairs in 0.50 day, but they charge $10 more per hour than the current repair service. Currently, how long does the laundromat have to wait for its equipment to be repaired? days, (Round your answer to 2 decimal places, the tolerance is +/-0.05) What is the cost of equipment downtime? I. (Round your answer to 2 decimal places, the tolerance is +2.5)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The Corner Cleaners 24-hour laundromat has 16 washing machines., A machine breaks down every 20 days (exponentially
distributed). The repair service the laundromat contracts takes anaverage of one day to repair a machine (exponentially
distributed). A washing machine averages $5 per hour in revenue. The laundromat is considering a new repair service that
guarantees repairs in 0.50 day, but they charge $10 more per hour than the current repair service.
Currently, how long does the laundromat have to wait for its equipment to be repaired?
days, (Round your answer to 2 decimal places, the tolerance is +/- 0.05.)
What is the cost of equipment downtime?
| (Round your answer to 2 decimal places, the tolerance is +2.5)
%24
Transcribed Image Text:The Corner Cleaners 24-hour laundromat has 16 washing machines., A machine breaks down every 20 days (exponentially distributed). The repair service the laundromat contracts takes anaverage of one day to repair a machine (exponentially distributed). A washing machine averages $5 per hour in revenue. The laundromat is considering a new repair service that guarantees repairs in 0.50 day, but they charge $10 more per hour than the current repair service. Currently, how long does the laundromat have to wait for its equipment to be repaired? days, (Round your answer to 2 decimal places, the tolerance is +/- 0.05.) What is the cost of equipment downtime? | (Round your answer to 2 decimal places, the tolerance is +2.5) %24
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.