The call-center employees work five consecutive days and then have two consecutive days off. An employee may start work any day of the week. Each call-center employee receives the same salary. Assume that the schedule cycles and ignore start-up and stopping of the schedule. Develop a model that will minimize the total number of call-center employees needed to meet the minimum requirements. (Let X;= the number of call-center employees who start work on da i where i 1 Monday, i = 2 Tuesday, etc). Min

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Epsilon Airlines services predominately the eastern and southeastern United States. A vast majority of Epsilon's customers make reservations through Epsilon's website, but a small percentage of customers make reservations via phone.
Epsilon employs call-center personnel to handle these reservations along with any problems with the website reservation system and for the rebooking of flights for customers if their plans change or their travel is disrupted. Staffing the
call center appropriately is a challenge for Epsilon's management team. Having too many employees on hand is a waste of money, but having too few results in very poor customer service and the potential loss of customers.
Epsilon analysts have estimated the minimum number of call-center employees needed by day of week for the upcoming vacation season (June, July, and the first two weeks of August). These estimates are given in the following table.
Day
Min
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
Sunday
Minimum Number of
Employees Needed
75
50
45
70
95
85
50
The call-center employees work five consecutive days and then have two consecutive days off. An employee may start work any day of the week. Each call-center employee receives the same salary. Assume that the schedule cycles and
ignore start-up and stopping of the schedule. Develop a model that will minimize the total number of call-center employees needed to meet the minimum requirements. (Let X; = the number of call-center employees who start work on day
i where i = 1 = Monday, i = 2 = Tuesday, etc).
Transcribed Image Text:Epsilon Airlines services predominately the eastern and southeastern United States. A vast majority of Epsilon's customers make reservations through Epsilon's website, but a small percentage of customers make reservations via phone. Epsilon employs call-center personnel to handle these reservations along with any problems with the website reservation system and for the rebooking of flights for customers if their plans change or their travel is disrupted. Staffing the call center appropriately is a challenge for Epsilon's management team. Having too many employees on hand is a waste of money, but having too few results in very poor customer service and the potential loss of customers. Epsilon analysts have estimated the minimum number of call-center employees needed by day of week for the upcoming vacation season (June, July, and the first two weeks of August). These estimates are given in the following table. Day Min Monday Tuesday Wednesday Thursday Friday Saturday Sunday Minimum Number of Employees Needed 75 50 45 70 95 85 50 The call-center employees work five consecutive days and then have two consecutive days off. An employee may start work any day of the week. Each call-center employee receives the same salary. Assume that the schedule cycles and ignore start-up and stopping of the schedule. Develop a model that will minimize the total number of call-center employees needed to meet the minimum requirements. (Let X; = the number of call-center employees who start work on day i where i = 1 = Monday, i = 2 = Tuesday, etc).
s.t.
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
Sunday
X1, X2, X3, X4, X5, X6, X7 20
Find the optimal solution.
(X₁, X2, X3, X₁1 X5, X6, X 7) = (
4'
Give the number of call-center employees that exceed the minimum required.
(M, Tu, W, Th, F, Sa, Su) =
Transcribed Image Text:s.t. Monday Tuesday Wednesday Thursday Friday Saturday Sunday X1, X2, X3, X4, X5, X6, X7 20 Find the optimal solution. (X₁, X2, X3, X₁1 X5, X6, X 7) = ( 4' Give the number of call-center employees that exceed the minimum required. (M, Tu, W, Th, F, Sa, Su) =
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 9 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.